HomeMy WebLinkAbout880962 CONTRACT CHANGE ORDER CHANGE ORDER: NO. 1, Schedule I DATE: 9-12-88 Street Improvements PROJECT: Weld County Business Park PROJECT NO. 8733F OWNER: Weld County CONTRACTOR: Hall-Irwin Const. Co. To the Contractor: You are directed to make the following changes or modifications to the work. All other terms and conditions of the contract expressly modified herein shall remain in full force and effect: CHANGE: 1. A. ADD- trash rack shown by detail on Plan Sheet 23 . B. CHANGE- striping width from 5" to 4" and ADD- 6 turn arrows and 6 each, word "Only" . C. ADD- 8 rectangular traffic signs shown on Sheet 32 of the plans. 2. ADD- 4258 sy 8" base furnished by Owner and placed by Contractor. 3 . ADD- 2 foot shoulder along acceleration and decelera- tion lanes on "O" Street. CHANGE IN CONTRACT PRICE: 1. A. Add-trash rack 1 ea @ 380. 00 380. 00 B. Change striping width & add 6 turn arrows' and 6 word "Only" 0.00 C. Add rectangular traffic sign 8 ea @ 150. 00 1200.00 1580. 00 2. Add 8" base furnished by Owner 4258 sy @ 0. 88 3747. 04 3. Add 2 ' shoulder on lane on "O" Street Add 3" AC Pavement 237 sy @ 3 . 76 891. 12 Add 12" base furnished by Owner 237 sy @ 1. 30 308. 10 Add common excavation 99 cy @ 5. 60 554. 40 1753 . 62 NET CHANGE IN CONTRACT COST: $ 7,080. 6§ I ��^ 860962 JUSTIFICATION: 1. Ciy of Greeley required change for plan approval. 2. Correct deductive Alternate No. 1 quantity to equal quantity shown in Schedule I base bid. 3 . City of Greeley required change for plan approval. Original Contract Amount $ 510,531.80 Net change by previous change orders $ 0.00 New contract amount including this change order . . . $ 517,612.46 Contract time will be ( inoroaccd) (dcorcaacd) by zero (0) days. Completion as of the date of this change order therefore is January 30, 1989. CONTRA OR: NORTON UNDERWOO D , INC. By; �' i./' �f�� _ V4//Ylit'(' By Date: 74; AX Date: OWNER APPROVAL BY: JAW( an DATE: ATTEST: `Iyy72i1r ��� WELD COUNTY U EPK 4.ND PSCORDER AND CU Pi< TO THE [CARD BY:.A.: a77?,i}z,.-e_ u L.c DDputy Cc :nty Clerk '4. 880332 CONTRACT CHANGE ORDER CHANGE ORDER: NO. 1, Schedule II DATE: 9-12-88 Sewer Lines PROJECT: Weld County Business Park PROJECT NO. 8733F OWNER: Weld County CONTRACTOR: Hall-Irwin Const. Co. To the Contractor: You are directed to make the following changes or modifications to the work. All other terms and conditions of the contract not expressly modified herein shall remain in full force and effect. CHANGE: 1. ADD- 1200 cy of County select material and dispose of 1200 cy of unstable material. CHANGE IN CONTRACT PRICE: 1. Add County Pit Run 1200 cy @ 1.16 1392. 00 Dispose of unstable material 1200 cy @ 1.16 1392.00 2784. 00 NET CHANGE IN CONTRACT COST: $ 2,784. 00 JUSTIFICATION: Request by City to prevent waiting for material to dry. Original Contract Amount $ 284, 534. 94 Net change by previous change orders $ 0. 00 New contract amount including this change order $ 287, 318. 94 Contract time will be (increased) (decreaced) by zero ( 0) days. Completion as of the date of this change order therefore, is January 30, 1989. CONTRAC R: // NORTON, DERWOOD , INC. ,,*# Date: 7/�%/- Date: q -is ER PP OVAL BY: a //Jj4/fAftelke.---1DATE: WELD C i fl' C'_ERK AND RECORDER AP CLIRK TO Tf1E BOARD 880962 4 BY' / yij,._n.c�.r __( L. ,--2( c‘.. Decqty County Cerk CONTRACT CHANGE ORDER CHANGE ORDER: NO. 1, Schedule III DATE: 9-12-88 Water Lines PROJECT: Weld County Business Park PROJECT NO. 8733F OWNER: Weld County CONTRACTOR: Hall-Irwin Const. Co. To the Contractor: You are directed to make the following changes or modifications to the work. All other terms and conditions of the contract not expressly modified herein shall remain in full force and effect. CHANGE: 1. A. ADD- 6" fire service with valve to five ( 5) feet behind property line and plug. B. ADD- 8 - 2" water services. C. DELETE- 10 - 1" water services. D. ADD- 1 - 3" ductile iron water service with valve at main and property line. 2. ADD- 430 lf of 8" DIP with 8" valve and fire hydrant along west property line of motor pool site. 3 . ADD- 2 - 16" gate valves. 4. ADD- 3 fire hydrants on 11th Avenue off of 16" line. CHANGE IN CONTRACT PRICE: 1. A. Add 6" fire service for motor pool building 1 ls 1510. 00 B. Add 2" water service 8 ea @ 987. 65 7901. 20 C. Delete 1" water service 10 ea @ 344. 68 ( 3446 .80) D. Add 3" D.I . water service and valves 1 ea @ 1738. 00 1738.00 7702.40 2. Add fire hydrant at south- west corner of motor pool site Add 8" DIP 430 lf @ 13 . 16 5658. 80 Add 8" gate valve 1 ea @ 484. 00 484. 00 Add hydrant at end of 8" line 1 ls 1558 .00 7700. 80 3 . Add 16" gate valve 2 ea @ 2440. 00 4880.00 4. Add hydrants 3 ea @ 1912. 34 5737 .02 Thrust protection, shipping & handling 1162. 98 6900.00 NET CHANGE IN CONTRACT COST: $ 27, 183 . 20 JUSTIFICATION: 1. A. Request by Owner for sprinkler system in motor pool building. 3. ,C. , D. 3" service for motor pool building, also change 1" services to 2" services to allow for more flexi- bility in future building. 2 . Request by Owner, fire protection for fuel storage area. 3 . Change proposal quantity to plan quantity. -4. City of Greeley request to be paid for out of City dire hydrant fund. Original contract amount $469,391. 64 Net change by previous change orders $ 0. 00 New contract amount including this change order $496,574. 84 Contract time will be ( incroasod) (dcorcaccd) by zero ( 0) days. Completion as of the date of this change order therefore is: January 30, 1989 CONTRACTOR: NORTON UNDERWOOD L , INC. BY: ` �L� % 'v By: Date: 717, Date: 9 OWNER APPROVAL BY: afff #Yede/lat DATE: ATTEST: , WELD COON i� ��-FRK AND RECORDER AND CI E ZK TO THE BOARD z“ii "-./ Deputy C.cunty Clerk • 8809432 Hello