HomeMy WebLinkAbout851158.tiff 2J``Epn aeG�<gr UNITED STATES
y `< '< NUCLEAR REGULATORY COMMISSION
S
REGION IV
o 3
r e q y 611 RYAN PLAZA DRIVE, SUITE 1000
217 • ARLINGTON, TEXAS 76011
MAY 2 2 1985 kID/C�oui Tt
In Reply Refer To: D {r a°?`i
Docket: 50-267/84-32 Wor
a 8 isas
JiRgELeY,
Public Service Company of Colorado cocci.
ATTN: 0. R. Lee, Vice President
Electric Production
P. 0. Box 840
Denver, Colorado 80201
Dear Mr. Lee:
This refers to the Management Conference conducted in the Region IV offices on
November 14, 1984, to review the major conclusions of NRC's October 1984
Assessment Report, to discuss operations of the Fort St. Vrain facility and to
review outstanding licensing actions. Since this conference there have been a
number of technical meetings with your staff and you have submitted a
substantial amount of information pertaining to the matters that were
discussed. We have also carried out a number of related inspections.
Based on a detailed review of records related to issues raised in the
Assessment Report and on follow-up inspection effort, we have concluded that
no violations of NRC requirements were identified therein. However, there are
two matters which must be brought to your attention.
As we discussed with you and members of your staff on several different
occasions, it is possible to come to an ambiguous interpretation of
10 CFR 50.72 concerning whether the failure of six control rods to
automatically insert during the scram event which occurred on June 23, 1984,
should have been reported at the time of the initial report to the NRC
Operations Center.
You should emphasize to your operations staff that it is the intent of this
regulation that any known condition involving potentially serious degradation
of a component or system required for plant safety be reported at the time an
event notification is made pursuant to 10 CFR 50.72. Likewise, your training
programs and plant procedures should be clear on this point.
Section 4.2.5.6 (page 4-8) of the Assessment Report discusses your program for
verification of the correct performance of operating activities. (TMI Action
Plan Requirements , NUREG-0737, item 1.C.6. ) Your position on implementation of
this item was apparently accepted without sufficient consideration to the need
for double verification of system or equipment status, particularly in
connection with maintenance activities. You should review your procedures
851158
h,J n-N TC D../ ha
Public Service Company of Colorado -2-
with this in mind and assure that you implement a system of "double
verification" to the maximum extend practicable in view of the design of your
plant. Your response to this item should be provided within 120 days of the
date of this letter. If you have any questions concerning this letter, we
will be pleased to discuss this with you.
Sincerely,
E. H. Johnson, Chief
Reactor Project Branch 1
Enclosure:
Appendix - NRC Inspection Report
50-267/84-32
cc:
Mr. D. W. Warembourg, Manager
Nuclear Engineering Division
Public Service Company of Colorado
P. 0. Box 840
Denver, Colorado 80201
Mr. David Alberstein, 14/159A
GA Technologies, Inc.
P. 0. Box 85608
San Diego, California 92138
Kelley, Stansfield & O'Donnell
Public Service Company Building
550 15th Street, Room 900
Denver, Colorado 80202
L2"° 'rman, Board of County Comm.
of Weld County, Colorado
Greeley, Colorado 80631
Regional Representative
Radiation Programs
Environmental Protection Agency
1860 Lincoln Street
Denver, Colorado 80203
(cont. on next page)
Public Service Company of Colorado -3-
Mr. H. L. Brey, Manager
Nuclear Licensing/Fuels Div.
Public Service Company of Colorado
P. 0. Box 840
Denver, Colorado 80201
J. W. Gahm, Manager, Nuclear
Production Division
Fort St. Vrain Nuclear Station
16805 WCR 19}
Platteville, Colorado 80651
L. Singleton, Manager, Quality
Assurance Division
(same address)
Colorado State Department Health
APPENDIX
U. S. NUCLEAR REGULATORY COMMISSION
REGION IV
NRC Inspection Report: 50-267/84-32 License: DPR-34
Docket: 50-267
Licensee: Public Service Company of Colorado
P. 0. Box 840
Denver, Colorado 80201
Facility Name: Fort St. Vrain Nuclear Generating Station
Conference Conducted: November 14, 1985
Report prepared by:
R. E. Ireland, Chief, Special Projects and if/tie
Engineering Section
Approved: m'4\' ≥ S/21 I4c
E. H. Johnson, Chief, Reactor Projects Branch 1 Date
Conference Summary
A management conference was held at the NRC Region IV offices in Arlington,
Texas, on November 14, 1984, with officials of the Public Service Company of
Colorado to discuss a number of issues related to restart and continued
operation of the Fort St. Vrain Nuclear Generating Station (FSV). The
discussions covered (a) the major conclusions of NRC' s October 1984 Assessment
Report transmitted to PSC on October 16, 1984, by the Director, Office of
Nuclear Reactor Regulation, (b) NRC perspectives on management and operation of
the FSV facility, and (c) current licensing items. The slides used during
these discussions are attached to this report.
Results: The licensee stated that the Public Service Company of Colorado will
do whatever is necessary to correct any outstanding problems and that the
company will apply those resources necessary to put the facility in a safe and
reliable operating condition. The NRC staff stated that, in addition to issues
already identified, the problems with the reserve shutdown system and the
control rod suspension cables would have to be resolved prior to restart of the
-2-
reactor. The staff also stated that it had not yet determined whether any
specific enforcement actions would be taken as a result of the problems
identified in the assessment report. Further inspection effort would be needed
to make this determination.
It was emphasized that NRC would need a documented commitment from the
licensee, in the near future, which could be used to form the basis for
scheduling and planning those NRC inspection and technical review activities
which would be necessary in connection with supporting a decision to allow the
facility to resume power operations. The licensee agreed that such information
would be provided.
The NRC staff stated that PSC should consider the Assessment Report as examples
of NRC findings that warrant attention but not as a necessarily complete
compilation. Each of the Assessment Report actions that would need to be
completed prior to restart was briefly summarized. It was emphasized that PSC
would need to provide timely and complete documentation for review by NRC with
respect to each of these actions if delays were to be avoided owing to the need
for NRC to request additional information. It was agreed that a meeting
between PSC and NRC technical staff should be scheduled in the near future to
discuss actions in greater detail .
With respect to ongoing licensing actions, the staff emphasized that PSC should
see early resolution of matters related to the PCRV tendons and that the work
related to fire protection issues (Appendix R) should get moving. It was noted
that PSC has the lead on resolving technical questions in connection with
LC0 4. 1.9 and that PSC should either commit to carryout the 100% load rejection
test or justify why it need not be done. With respect to Building
10 structural design criteria and electrical modifications, the staff stated
that further review was to be done.
A number of items concerning plant management, plant operations and PSC/NRC
communication, were discussed. It was agreed the scope and schedule for the
management review being carried out for PSC by the NUS Corporation would be
submitted for NRC comment in the immediate future. PSC also agreed that NUS
should submit its reports to NRC and PSC simultaneously. PSC' s schedule and
plans for implementation of any recommendations would be submitted soon
thereafter.
With respect to improvement in communications between PSC and NRC, the staff
stated that openness and candor were need to assure that misunderstandings do
not occur regarding identification of requirements which must be met and the
nature and relevance of commitments made by PSC in meeting those requirements.
It was stated that, if misunderstandings do arise, they should be brought to
NRC management attention so that clear, singular resolution could be achieved.
The staff stated that the forthcoming management audit and the resolution of
technical issues could be separated.
-3-
It was agreed by NRC and PSC that there would be need for additional meetings
at both technical and management levels to assure that problems needing
resolution are clearly defined and answered and that schedules are established.
The staff stated that its inspection activities would likely be increased to
follow PSC activities prior to resumption of reactor operations.
Persons Participating in the Conference:
NRC:
RIV: R. D. Martin, Regional Administrator
P. S. Check, Deputy Regional Administrator
E. H. Johnson, Chief, Reactor Projects Branch 1
R. A. Cooley, Chief, Operator Licensing Section
R. E. Ireland, Chief, Special Projects and Engineering Section
P. C. Wagner, Project Manager
D. A. Powers , Technical Reviewer
IE: J. T. Collins ,
NRR: G. C. Lainas , Assistant Director, Operating Reactors,
Division of Licensing
J. R. Millen, Chief, ORB-3
Licensee:
R. F. Walker, President
C. K. Miller, Senior Vice President, Operations
0. R. Lee, Vice President, Electric Production
J. W. Gahm, Manager Nuclear Product
H. L. Brey, Executive Staff Assistant
B. W. Diest, Licensee Consultant (NUS)
State of Colorado:
A. J. Hazle, Colorado Department of Health
Attachment
PUBLIC SERVICE COMPANY OF COLORADO
MANAGEMENT MEETING
PURPOSE
• To REVIEW THE MAJOR CONCLUSIONS OF THE ASSESSMENT REPORT
• To PROVIDE NRC PERSPECTIVE ON RELATED ISSUES
• To OUTLINE CURRENT LICENSING ITEMS
1
ASSESSMENT REPORT ACTIONS
ACTIONS TO BE COMPLETED PRIOR TO RESTART :
• CONTROL ROD PROBLEM:
• IDENTIFY AND CORRECT FAILURE MECHANISM OR PROVIDE OTHER
COMPENSATORY MEASURES
• PERIODIC SURVEILLANCE/INSPECTION/PREVENTIVE MAINTENANCE
PROGRAM
• PREVENT OVERDRIVING RODS (PROCEDURAL )
• RESERVE SHUTDOWN HOPPER TEST
• PROCEDURE FOR REACTOR SHUTDOWN UNDER MOISTURE INGRESS
OR LOSS OF PURGE FLOW
• TAKE TEMPERATURE READINGS OF CONTROL ROD DRIVES
• OVERALL CONDUCT OF OPERATIONS :
• THIRD PARTY REVIEW OF PSC MANAGEMENT STRUCTURE AND
PRACTICES (SCOPE AND SCHEDULE PRIOR TO REVIEW)
• NRC TO RECEIVE REPORTS SIMULTANEOUSLY
• TECHNICAL SPECIFICATION UPGRADE :
• REVIEW AND REVISE (NEW PROPOSED TECHNICAL
SPECIFICATIONS TO BE SUBMITTED BY APRIL 1 , 1985)
• INTERIM PROCEDURES IMPLEMENTED ON SPECIFIC ITEMS
• WATER INGRESS :
• DEVELOP A PLAN TO CARRY OUT PSC "MOISTURE INGRESS
COMMITTEE" RECOMMENDATIONS
• PERIODIC REPORTS ON PROGRESS TO THE NRC
• SCHEDULE FOR LONGER RANGE ITEMS :
• WITHIN 60 DAYS AFTER RESTART
2
MANAGEMENT INVOLVEMENT
ISSUES
• FREQUENCY AND TYPE OF PLANT TOURS BY PLANT SUPERVISORS AND
PSC SENIOR MANAGERS ,
• NRC INSPECTORS OFTEN ARE THE FIRST TO IDENTIFY OFF-NORMAL
CONDITIONS WHICH SHOULD HAVE BEEN REPORTED BY SHIFT CREWS OR
MAINTENANCE PEOPLE TO PLANT MANAGEMENT ,
• MANAGEMENT PHILOSOPHY
3
PSC'S OPERATING ATTITUDE
ISSUES
• INITIATIVE IN PURSUING REGULATORY MATTERS
• HTGR "DIFFERENCES"
• PSC LICENSING STAFF CAPABILITIES
• TECHNICAL STAFFING
• DESIGN CONTROL
4
PLANT OPERATIONS
ISSUES
• PROCEDURAL VIOLATIONS
• CORRECTIVE ACTIONS
• FORMALITY OF OPERATIONS
• HOUSEKEEPING
• MAINTENANCE
• MORALE
5
COMMUNICATIONS AND COMMITMENTS
ISSUES
• LICENSING CORRESPONDENCE IS SIGNED BY A VARIETY OF
INDIVIDUALS, THERE IS NOT A SINGLE POINT OF CONTACT WITH THE
NRC,
• COMMITMENT TRACING
• INTERNAL COMMUNICATIONS
• KEEPING NRC INFORMED
• MEETING SCHEDULES
6
LICENSING ITEMS
• PCRV TENDON WIRES
• IDENTIFICATION OF CORROSION MECHANISM
• MITIGATION OF CORROSION
• SURVEILLANCE PROGRAM
• APPENDIX R
• COMPLETE TECHNICAL EVALUATIONS
• PERFORM MODIFICATIONS THAT ARE NECESSARY
• POWER TO FLOW TECHNICAL SPECIFICATION ( 4 . 1 . 9)
• DEVELOP APPROPRIATE REVISION
• STARTUP TEST PROGRAM
• DEVELOP JUSTIFICATION FOR CHANGES TO THE TEST PROGRAM,
OR COMMIT TO PERFORMING 100% LOAD REJECT TEST
• BUILDING 10 AND ELECTRICAL MODIFICATIONS
• NRC REVIEWING ADEQUACY OF THE DESIGN BASES
7
Hello