PROJECT: WELD COUNTY, COLORADO CHANGE ORDER NUMBER: THREE
MOTOR POOL SERVICE CENTER BUILDING
(name, address)
_
WELD COUNTY BUSINESS PARK
TO (Contractor) GREELEY, COLORADO
Jerald Construction Co. , Inc. 7 ARCHITECT'S PROJECT NO: 8803
P.O. Box 1962 CONTRACT FOR: MOTOR POOL
Fort Collins , Colorado 80522 SERVICE CENTER BUILDING
GREELEY, COLORDO
L J CONTRACT DATE:September 1 , 1989
You are directed to make the following changes in this Contract:
1 . Electrical changes as per Contractor's letter
dated June 21 , 1989. ADD: $5,052.00
2. Landscaping credi;tas per Contractor's letter
dated May 1 , 1989. 'DEDUCT: $ 346.00
The original Contract Sum was $ 1 ,511 ,000.00
Net change by previous Change Orders $ 20,748.00
The Contract Sum prior to this Change Order was $ 1 ,531 ,748.00
The Contract Sum will be (increased) (dec ease4) (.0 ehangeel) by this Change Order . . $ 4,706.00
The new Contract Sum including this Change Order will be $ 1 ,536,454.00
The Contract Time will be (increased4 (docceased) (unchanged) by ( -0- ) Days.
The Date of Completion as of the date of this Change Order therefore is February 1 , 1989 .
LARRY E. STEEL ASSOCIATES JERALD CONSTRUCTIONS. , INC. WELD COUNTY, COLORADO
ARCHITECT CONTRACTOR OWNER
Greeley National Plaza. Suite P.O. Box 1962 P.O. Box 758
Address 640 Address Address
Greeley, Colorado Q 80631 R A Fort Collins , Colorado 80522 Greeley, Colorado 8.0632
BYla4 E . h�/tK✓<.l AIA BY BY
DATE G/ 'S/Fjg DATE DATE /Z ki
AIA DOCUMENT 0701 • CHANGE ORDER • APRIL 1970 COITION • AlAS • 09 1970 • THE ( ONC PAGE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., NW, WASHINGTON, D.C. 20006 890552
eGOOr 4- :�
"
ConeRruc oon
1314 Webster 482-0414
P.O. Box 1962 Fort Collins, CO 80t-^2
June 21 , 1989
Larry E. Steel & Associates
822 7th Street, #640
Greeley, CO 80631
Re: Weld County Motor Pool
Attn: Mr. Steel
This letter is in request of electrical change items as discussed and
agreed upon with the electrical engineer and owner on June 14, 1989.
As follows:
Item // 1 : Add outlet for landscape sprinkler control $ 245.00
Item // 2: Conduit to sump pump for Johnson Control 241 .00
Item // 3: Add smoke detectors 300.00
Item /1 4: Air supply blower 240.00
Item 1/ 5: Door operators 1 ,900.00
Item // 6: Three-Phase pumps 440.00
Item 1/ 7: Add relay for lighting in wash bay 206.00
Item # 8: Lights in Room 116 167.00
Item 1/ 9: New lamps 370.00
Item #10: Credit for lights Room 113 -<130.00>
Item #11 : Conduit for waster oil and antifreeze tanks 414.00
Sut-total $ 4,393.00
P & 0 15% 659.00
Total Add
$ 5,052.00
Sincerely,
JE LD CONSTRUCTION CO. , INC.
iZc(o-alci
Douglas R. McCarthy
Project Manager