BUILDING SYSTEMS, INC. Number 1
2430 6TH AVENUE - GREELEY, CO 80631 /PHONE DATE
303353-7364 353-0540 9-19-84
JOB NAME/LOCATION
TO Weld County Division of Human Resources 520 13th Avenue
% Mr. Walter Speckman
JOB NUMBER JOB PHONE
84-19
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT
RE: 520 13th Avenue Greeley, Colorado
We hereby agree to make the change(s)specified below:
Addition of 1 - 3 °7 ° Steel exterior door system with
panic hardware, weatherstrip and thresholds. •
722 . 00 installed 722 . 00
Addition of 2 - 6°4° Mill finish aluminum windows,
single glass
175.00 each installed 350 . 00
Relocation of 4 - 6 °4 ° existing windows
85. 00 340. 00
• Relocate existing door and install new weatherstrip,
threshold and sweep.n 167 . 50
NOTE: This Change Order becomes part of and in conformance with the existing contract.
WE AGREE hereby to make the change(s) specified above at this price 4. $ 1 , 579 50
OATE
PREVIOUS CONTRACT AMOUNT $ 55, 000 00
AJTHORIZED SIGNATURE(CONTRACTOR) _
j - REVISED CONTRACT TOTAL/ $, 56 , 579 50 ,5'
ACCEPTED -The above prices and specifications of ��%
this Change Order are satisfactory and are hereby ac- Date of acceptance
cepted. All work to be performed under same terms and \\
conditions as specified in original contract unless other- ' Signature r., `YMs n yti
wise stipulated. iO NE
//
/D ;1 840256