HomeMy WebLinkAbout20010011.tiff BOARD OF DIRECTORS NORTH WELD COUNTY-WATER DISTRICT
GARY SIMPSON 33247 HIGHWAY 85 • LUCERNE,CO 80646
ERNEST ROSS
W.M.McKAY DON POSSELT,DISTRICT MANAGER
CHARLES ACHZIGER `f
ROBERT ARNBRECHT P.O.BOX 56 • PHONE(970)356-3020 • FAX(970)395-0997
e-mail:nwcwd@bwn.net
September 6,2000
Hoshiko Farms,Inc.
28607 WCR 50
Kersey,CO 80644
This letter is in response to your inquiry regarding water service to the following described property,
Approximately 19100 WCR 66,in a portion of the
NW''A of Section 29,T6N,R65W of the 6th Prime Meridian
1.- Water service is presently being provided to the above described property.
2.North Weld County Water District is able and intends to provide water service to the above mentioned property,
provided all requirements of the District are satisfied. Before a tap may be purchased,a line extension from Hwy 392
&WCR 41 to the eastern edge of the property must be completed.
If contracts have not been completed with North Weld County Water District within one year from the date of this
letter,this letter shall become null and void. The Tap Fees quoted below,shall be valid for ten(10)business days from
the date the applicant receives this letter. After ten days,the costs will be subject to the current cost established by the
District. The applicant can avoid the Raw Water portion of the Tap Fee,by permanently transferring one unit of
Colorado Big Thompson(CBT)Water to the District.
•
TAP FEES INSTALLATION COST ESTIMATE
Raw Water for an Acre-Foot Unit(AFU) $14,000 Meter Set TBD
Base Portion of Plant Investment Fee $5,000 Range:$500 to$2500
Distance Portion of Plant Investment Fee $1,900 Line Extension Participation TBD
TOTAL COSTS $20,900 $TBD
Before a water tap may be purchased,the applicant must provide a copy of a Warranty Deed,and Physical Address.
The applicant should also bring a copy of a surveyed plat of the property(required for a recorded exemption)and this
letter. After the water tap has been purchased(Raw Water AFU&Plant Investment Fee)the applicant has one year
in which to have the meter set. The District requires 45 days prior notice to setting a meter. If the meter has not been
set within one year from the purchase of such meter,the District shall refund the applicant 75%of the purchase price
that was paid by the applicant. If any line extensions,road bores or additional installation costs are estimated to be
more than$5,000,then Proof that"Loan Funds or a Line of Credit"are Available and ready to reimburse the District
at the time of completion,for 110%of the estimated cost. The applicant will pay such costs before the tap is activated
(water is turned on).
•
Water tap/service shall be placed on the physical property,defined by a legal description. In case of a Recorded
Exemption,the water tap shall be located on the physical property of the Recorded exemption defined by a legal
description before a water tap/service will be transferred from seller to buyer.
The District recommends that anticipated water usage be purchased through the District. The District guarantees
treatment and delivery of water purchased. MI rental water and water that is delivered with surcharge is subject
to water availability and will be issued on a first come-first serve basis and is not guaranteed to be available.
The District requires that 1 Acre-Foot Unit(AFU)is purchased. With 1 AFU purchased any usage beyond 228,000
gallons will be in surcharge.
The Plant Investment Fee shown above pays for the infrastructure required to deliver 1 AFU(228,000 gallons).
If usage exceeds the number of Plant Investment Fees that were purchased,additional charges will be applied
to your account.
Alan Overton
North Weld County Water District
U:\Legal Documents\Letter of Intent\2000W oshikoFanns(9b-00).doc 2001-0011
Hello