444;ft MEMORANDUM
TO: File, USR 1217 DATE: June 28, 2000
COLORADO' FROM: Kim Ogle, Planner
SUBJECT: Chronology of Events for Faith Tabernacle Church
June 22, 2000 Mika telephone call with Perdew to discuss proposed sign issue. Perdew
indicated that he wanted to have a Board of Adjustment hearing to resolve
sign dimension issue. Perdew also indicated he wanted the Board to
consider the repel of any fees associated with his request.
June 15, 2000 Letter from Perdew requesting fee waiver for BOA hearing concerning the
size of the sign.
June 19, 2000 Letter from Sprague to Perdew concerning the one-hour fire wall rating within
the building and the upcoming inspection by Zoyiopoulos regarding all fire
rating issues.
June 15, 2000 Letter from Perdew seeking relief from BOA for sign
June 9, 2000 Applicant's Sign representative (Larry Biggers)obtained WCZO Section 42.1
pertaining to signs in the R-1 Zone District. Ogle stated thirty-two(32)square
feet is permitted. Ogle noted one sign per principal use is allowed.
June 8, 2000 Applicant's sign representative (Larry Biggers) faxed drawings for sign to
Planning Office for review and direction on how to proceed with building
permits. Dimension of sign exceeds dimensions permitted in the R-1 Zone
District.
May 19, 2000 Ogle letter to Perdew/Watson regarding outstanding issues to be addressed
prior to the recording of the USR 1217 mylar, Letter is itemized according to
Resolution (PL1325)..
May 16, 2000 Letter dated May 1,2000 from Watson regarding Phasing of project per COA
item # 2p
Letter dated May 1, 2000 from Watson regarding amending out the Family
Life Center and the associated primary and secondary leach fields.
Photocopy of the Outside of City Water Agreement between the City of
Greeley and Faith Tabernacle Church. Date of Agreement is May 4, 2000.
May 11, 2000 Applicant provided paper copy of mylar for staff review.
Copy of petition signed by SPO Weiderspon for Resubdivision application.
No letter received from Milliken Fire Department regarding fire hydrant sign-
off.
Faith Tabernacle Case Chronology, page 1
2 —338q
P.[33-6
Ogle notified by Applicant that Kenney Associates no longer associated with
project. Previously Kenney Associates were Project Architects.
Letter from Sprague, Weld County Building Inspection to Perdew identifying
the requirements for a one-hour rated building as Perdew fetter dated May
4, 200O stated their intent to not sprinkle the building.
May 4, 2000 Letter from Perdew to City of Greeley regarding their intent to not sprinkle
building due to financial concerns and not being credited by the insurance
company for their upgrades.
Photocopy of Approval from the Weld County Department of Public Health
& Environment for the engineered designed septic system.
May 200O Ogle telephone log notes numerous telephone conversations with Perdew/
Watson, of Faith Tabernacle regarding outstanding/current issues that need
to be addressed.
April 14, 2000 Meeting with City of Greeley, County (Mika, Sprague, Ogle), and Fire District's
to discuss the water issue, fire suppression issue, and related water matters
for Faith Tabernacle Church. Perdew nor any representative of the
Church was asked to attend.
April 6, 2000 Ogle letter to Perdew stating more than sixty (60) days had passed since
Board of County Commissioner approval. Letter further stated the need to
submit a complete application for the Re-subdivision of the Peterson-
Alexander Subdivision.
February 10, 2000 BOA hearing regarding variance to height of building in the R-1 Zone District.
Variance was approved by the Board of Adjustment.
February 2000 Ogle telephone log notes numerous telephone conversations with Perdew/
Watson, of Faith Tabernacle regarding outstanding/current issues that need
to be addressed.
January 13, 2O00 Utility Board Hearing for Resubdivision of Peterson-Alexander Subdivision.
Utility Board requests fifteen (15) feet on north property line be reserved for
utility corridor. Responding Fire Department to sign off on fire hydrant
location(s). Perdew to revise drawings and obtain letter from Fire District.
January 10, 2000 Ogle memorandum to Morrison regarding protocol of Boyle engineering
design review. Morrison instructed Ogle to mail copy to applicant's engineer,
Tom Cope of Total Engineering for his review and use.
January 7, 2000 Weiderspon submitted copy of letter from Ed Toms of Boyle Engineering
Corporation regarding the Irrigation Design Review of the relocated
Boomerang Lateral,
January 4, 2000 Letter from Hall to Perdew dated December 29, 1999 regarding Ordinance
210 for Road Impact Fees. Board instructed staff to not impose fees for
Phase one construction.
January 2000 Ogle telephone log notes numerous telephone conversations with Perdew/
Watson, of Faith Tabernacle regarding outstanding/current issues that need
Faith Tabernacle Case Chronology, page 2
to be addressed.
December 27, 1999 Perdew asked for early release of building permits. Early release was granted
for footings and foundation only (BC-9901172) until the Department of
Building Inspection completed the Plan Check for his facility. The early
release was granted by the Board of County Commissioners.
December 19, 1999 Drawing received from Total Engineering for Utility Board Hearing
December 7, 1999 Incomplete Resubdivision Application received by Staff. No signatures for
SPOs. Seventy (70) percent required.
December 1999 Ogle telephone log notes numerous telephone conversations with Perdew/
Watson, of Faith Tabernacle regarding outstanding/current issues that need
to be addressed.
November 3, 1999 Resolution dated October 25, 1999, regarding COA item 2.n specific to
Irrigation Ditch Agreement, and the deletion of item # 7 pertaining to
interference of proposed piped irrigation ditch and proximity of roots from
surrounding plant material.
November 1, 1999 Resolution to Approve USR # 1217
November 1, 1999 Hearing Certification Docket Number 99-56
November 1999 Ogle telephone log notes numerous telephone conversations with Perdew/
Watson, of Faith Tabernacle regarding outstanding/current issues that need
to be addressed.
October 25, 1999 Revised Site Plan with Landscape Plan overlay received at hearing
October 21, 1999 Ogle Memorandum of meeting with Weiderspon regarding outstanding
issues, water agreement and landscape plan problems
Letter dated October 19, 1999 from Bryan Elwood, Eaton Grove Nursery
regarding plant material adjacent to the proposed below grade irrigation pipe.
Memorandum from Weiderspon regarding outstanding issues and concerns
specific to Faith Tabernacle.
October 13, 1999 Board of County Commissioners hearing for Faith Tabernacle Church
October 12, 1999 Letter from Kim Lawrence dated October 11, 1999 to Perdew concerning
Irrigation Ditch Agreement.
October 11, 1999 Letter from Ron Brinkman to Weiderspon concerning re-routing of Boomerang
Lateral.
Letter from Urano &Weiderspon concerning design issues pertaining to the
re-routing of Boomerang Lateral.
Letter from Urano & Weiderspon to Perdew dated October 9, 1999
concerning outstanding issues pertaining to the re-routing of Boomerang
Lateral.
Faith Tabernacle Project Chronology page 3
Letter from Perdew to Urano dated October 8, 1999 regarding Irrigation
issues.
Letter from Perdew to Weiderspon dated October 8, 1999 regarding Irrigation
issues.
October 10, 1999 Correspondence from Weiderspon regarding dates for meeting with Perdew
to discuss and finalize Irrigation Water Agreement.
October 2000 Ogle telephone log notes numerous telephone conversations with Perdew/
Watson, of Faith Tabernacle regarding outstanding/current issues that need
to be addressed.
September 20, 1999 Drainage Report by Total Engineering Service, Inc. Submitted to the
Department of Planning Services for review and approval.
August 3, 1999 Planning Commission Resolution of recommendation to the BOCC
August 1999 Ogle telephone log notes numerous telephone conversations with Perdew/
Watson, of Faith Tabernacle regarding outstanding/current issues that need
to be addressed.
July 8, 1999 Ogle asked for continuance until August 3, 1999, as Site Plan submitted to
City of Greeley for Water Agreement differed substantially from Site Plan staff
had in file
July 2, 1999 Letter from Jon G. Monson, City of Greeley, Water & Sewer Department
outlining requirements for the acquisition of water services that will be
contingent upon several factors. Reference is made to their letter of
December 9, 1998.
July 1, 1999 Letter from Weiderspon outlining outstanding issues yet to be met and
addressed
July 2000 Ogle telephone log notes numerous telephone conversations with Perdew/
Watson, of Faith Tabernacle regarding outstanding/current issues that need
to be addressed.
June 24, 1999 Revised Site Plan received from City of Greeley, per agreement between
Faith and City for Conditions for receipt of water.
June 22, 1999 Telephone conversation with Greg Thompson regarding water issue. Perdew
to comply with City conditions or will not receive public water. Minimum level
of service will not be extended unless conditions are met.
June 1, 1999 Letter from Thompson,City of Greeley Community Development Department
to Ogle outlining conditions to be met by Faith Tabernacle Church including
development standards such that Church may obtain City water. Conditions
include Phase 1 and Phase 2 requirements.
June 2000 Ogle telephone log notes numerous telephone conversations with Perdew/
Watson, of Faith Tabernacle regarding outstanding/current issues that need
to be addressed.
Faith Tabernacle Project Chronology page 4
March 16, 1999 Planning Commission Hearing, continued indefinitely by Planner Ballstadt
until issues with City are addressed.
Letter from Thomas Hellerich, Attorney, to Reverend Perdew regarding the
construction of the Church to City of Greeley standards.
March 15, 1999 Letter from Urano stating concerns
March 10, 1999 Letter to Greg Thompson from Jim Birdsall of Kenney Associates, Architects
to Faith Tabernacle, later faxed to Planning Services regarding the time
needed to complete a new site plan. Planning Staff received Revised Site
Plan June 24, 1999.
March 1, 1999 Memorandum from Ballstadt to Planning Commission outlining a lack of water
agreement from City of Greeley and determination from staff that evidence
of water had not been met.
February 10, 1999 Continuance of case before Planning Commission as Department of Public
Health and Environment has several outstanding issues that need to be
addressed.
February 3, 1999 Interoffice memorandum from Ballstadt noting numerous telephone
conversations with Kaylun Watson, of Faith Tabernacle regarding
outstanding/ current issues that need to be addressed.
February 2, 1999 Barker electronic mail to Ballstadt, concur with continuance.
Barker electronic mail to Ballstadt, regarding Annexation by the City of
Greeley. The Board has not received a request by the City for Annexation
of 71st Avenue.
January 29, 1999 Electronic mail from Ballstadt to Morrison. Faith has no water. City of
Greeley has conditions for extension of water service. City must approve
plans prior to extension of water. Asking for continuance until all issues are
resolved. Do you concur...?
Electronic mail from Morrison to Ballstadt. County cannot approve USR
without water.
January 18, 1999 Application for USR 1217 received
December 9, 1998 Letter from Jon Monson to Kaylun Watson of Faith Tabernacle outlining
conditions to be met for water service outside of the City Limits.
November 4, 1998 Barker electronic mail to Board copied to Mika. Flagpole annexation
proposed by City thus giving Faith Tabernacle city water. Not approved by
State. Board polled. Board expressed concerns. Adjacent neighbor,
Weiderspon, expressed objections.
August 4, 1998 City of Greeley Council Proceedings for Faith Tabernacle outlining water
issue.
July 7, 1998 Site Plan for Faith Tabernacle first delineated, per date of drawing.
Faith Tabernacle Project Chronology page 5