July 26, 2001
Mr. & Mrs. Dean Mirabassi
4414 WCR 5
Erie, CO 80516
Dear Mr. & Mrs. Mirabassi:
An inspection of your road by the Public Works Department has identified and isolated
the problem you refer to in your letter to the Weld County Assessor.
While WCR 5 is one of the best paved roads in Weld County, it does have a minor
imperfection in the pavement, and unfortunately that location is in front of your house.
Jeff Jerome, Public Works Operations Division Manager, will design a repair strategy
and program the repairs into this maintenance season.
Quality control has become a steadfast focus on our roads and I apologize for any
inconvenience.
If you have any questions please contact Jeff at (970)356-4000, Ext. 3754.
Sincerely,
BOARD OF COUNTY COMMISSIONERS
M. J. Geile, Chair
cc: Frank B. Hempen, Jr.
Director of Public Works/County Engineer
Jeff Jerome, Public Works Operations Division Manager
Cam' il
/if7 a 2001-2281
To WELD COUNTY ASSESSOR Mr Stanley F:�Sessions
RECEIVED
fax# 970 304 6433
"= 15 JUL 1 7 2001
From Dean and Ann Mirabassi
4414 WCR 5 80516 F t WELD COUNTY ASSESSORt
phone 303 828 0736 GREELEY, COLORADO
As it concerns the property assessment of 4414 Weld County Road 5 I would like to state the
following. The last time an assessment was done on this property, I wrote to your office to
complain about the condition of Weld County Road 5. In particular the noise created by trash
trucks as they come and go from the two landfills to the south of my property. At that time my
assessment was lowered. Since then the road has been repaved but the job that was done is
deplorable. If a private contractor had done the work, I doubt that Weld County would have
accepted the job. The problem was that the crew ran out of pavement right in front of my house
less than 150 feet from where they intended to meet the previous days paving. Instead of creating
a proper joint, the pavement was raked to meet existing and the crew went home. When the work
continued the crew simply started where they left off creating a hump that has only gotten worse.
The problem is bad enough that the empty trash boxes of the roll-offs actually bounce off the
frames of the trucks landing with a deafening crash. I understand that property values in my area
have gone up and I do not have a problem with my assessment if the portion of the Weld County
Road 5 in front of my house was at least equal in quality to the rest of the road. I don't want my
assessment lowered. I would like to have the road fixed. It seems to me that the revenue that this
road produces for the County should more than offset the cost to maintain it. I do not think it is
fair to me or my family that we should have to put up with the noise created by this problem while
the rest of the County benefits from it's use. Please contact me or my wife if you have any
questions.
Thank you for your time,
Dean Mirabassi
CORRESPONDENCE RIESPONS_E
DEPARTMENT OF Fat'-C i>m Gv RECEIVED
* * * PLEASE RESPOND WITHIN THREE DAYS.* * * JUL 2 0 2001
IF RESPONSE WILL BE DELAYED, WELD Counry
PUBLIC%HOPI'S DEPT
PLEASE NOTIFY "CTB GROUP" BY E-MAIL
OF EXPECTED DATE FOR RESPONSE.
RECOMMENDED ACTION:
Narrative:
METHOD OF RESPONSE:
Board Action
- Work Session
Letter (Attached)
- Telephone Call
- No Response (explain)
Department Head Si re