Loading...
HomeMy WebLinkAbout20010753.tiff r -470 Public highway Authority Quarterly (ipclate m a 't m�' B 14#0 P ,a �,ssa I z, � !•avl B"'aw$ irzRa r ai 4z8s r :»Ms ex nE "•%!:rr, : S' ? �{Wr;.,.b °C ��£ gr % V °b4 & H .xi. �saE �e 6 9d.aT . i , p 'dP•_ {.{�iriris .. .,:' C '` P&$ ttr fl� deF P3' _ }' z - ` .0 A^"i[Ir. 04S:4u ,.h u 711161 !i —t-r, _ it` -mss' IF - +-• '�" -r E. I '{£e'4#"P e e ate.^ k+X&8P 9� , q jyq _ .«.:ea«• 4 �' f•4°m..-' Quarterly report October I - December 31,2000 About the Tollway E-470 is a toll highway that runs along the eastern perimeter Fixed Contract Price of the Denver metropolitan area. Presently,the road extends The total price to be owed to the design-build contractor 34 miles from State Highway C-470 at 1-25 in Douglas County for the performance of all of its obligations with respect to the on the south,runs east then north through Aurora,passes along j Segment IV project is $233,051,777. The contract price includes the western edge of the Denver International Airport,and all design,construction,supervision,equipment,materials,labor, terminates at 120th Avenue just west of Tower Road in Adams and services relating to the design-build contractor's obligations County. under the design-build contract(including all equipment and The E-470 Public Highway Authority ("the Authority") services provided by sub-contractors and vendors and intellectual consists of eight member jurisdictions: Adams, Arapahoe and property rights necessary to perform the work). Douglas counties and the cities of Aurora,Brighton,Commerce City,Parker and Thornton. Affiliate,non-voting members are Guaranteed Completion Dates the cities of Arvada,Broomfield and Greeley,and Weld County. The design-build contractor is obligated to achieve final Ex-officio members are the Colorado Department of acceptance of the Segment IV project by the date that is 1,124 Transportation (CDOT),Denver Regional Council of days (June 10,2003)from the date of issuance of notice to Governments and the Regional Transportation District(RTD). proceed with Phase III work. The design-build contractor is required to achieve substantial completion of Sub-Package BI (120th Avenue to US 85) by 850 days (September 9,2002) About the rrO ect from the date on which the Authority gives notice to proceed on Phase II for Package B,and on all of Package B by 1,034 days (March 12,2003)from the date on which the Authority Segment IV,the final portion of the highway to be constructed, gives notice to proceed on Phase III for Package B. will connect E-470's present northern terminus at 120th Avenue with 1-25 on the north near the 157th Avenue alignment in Engineering Oversight Thornton. The Authority has retained the services of O'Brien A Segment IV design-build contract was signed in January Kreitzberg,Inc.as Project Oversight Engineer to assist with 2000 between MKK Constructors (MKK) and the Authority. design-review and construction implementation during the MKK,a joint venture between Washington Group International, Segment IV design-build contract Inc.(formerly Morrison Knudsen) and Kiewit Western,is I designing and building the final portion. (See page 3,"Design- Build Contractor" and page 6,"Subsequent Events.") Construction is scheduled to be completed in 2003. -rnra; Design-Build Contract s "Design-build" describes a project delivery method of • • °6• ''- 65 enhancing the likelihood of timely project completion and cost • des /& () control by permitting a variety of aspects of a project,including : it::: r b • • ir'design,obtaining governmental permits and right-of-way, i _ $ • •/ o subcontractor bidding,procurement and construction,to occur I96NAvenue '�9. ` N 3 • concurrently rather than in sequential completed steps. The r'", a ss.bpc �28128th . ei A„N.nriry c„ fa rnncrnincsri cnn.nnnec a 6rIA III frnm Avenue ! .' � Water, Water, if ver where Unlike any other portions of E-470,the dozens of water crossings along Segment IV have presented many design and construction challenges. Consequently,the extensive drainage works has created the need for bridges on the Platte River, Second Creek,Third Creek and Big Dry Creek. A major detention pond is being created for Third Creek,located south of 120th Avenue with Concrete Box Culvert(CBC) control release structures under 120th Avenue.Between Buckley Road and Sable Boulevard,a major portion of Third Creek has been developed for relocation while its wetland attributes have been maintained. Along the north side of E-470 and both sides of 1-76,over 30 acres of wetlands will be cultivated by the environmental design partner for the project. Extensive coordination has been required with the Urban Drainage and Flood Control District, Adams County,the Farmers Reservoir and Irrigation Company and all the affected cities. Along Segment IV,there are seven major canal and ditch companies,four of which are historic and date back to the turn of the 20th century. Bridges that cover the historic irrigation canals and ditches help preserve the open waterway aspect of these facilities,and have been designed for the E-470 crossings at the historic O'Brian Canal and the Burlington Ditch. Preceding east to west,E-470 spans the historic Fulton Ditch and the adjacent Union Pacific Railroad (UPR) and US 85,and over the historic Brantner Ditch,and Riverdale Road. The designs for the other three major irrigation crossings involve the following: •A 60 inch culvert crossing for the German Ditch under the Boulder Branch of the UPR and under E-470. •A drop structure and a 48 inch outlet culvert for the Signal Ditch with a 24 inch parallel siphon. •A CBC for the Bull Canal. The other IS irrigation facilities are major and minor laterals off the supply canals and ditches.One of these laterals has eight users and another has four users.The complexity of ownership for irrigation facilities complicates the design and agreement process,making it time consuming. A view from the road: Looking southeast towards E-470 along the O'Brian Canal. :. was 3"� ,i•a 'gyp,'�9� '' �a° , ,ar'. rya Sh ,. Segment IV Design-build rro'ect Progress Re ort Design-Build Contractor • Utility relocations continue to avoid conflict with The Authority entered into the Segment IV design-build construction improvements. contract on January 27,2000 with the design-build contractor,a • The worksite has been continually monitored for joint venture between Washington Group International,Inc. environmental and erosion control concerns. (formerly Morrison-Knudsen) and Kiewit Western Company. • Fencing has been erected to protect existing wetland areas Full notice to proceed was given during the first and second and silt fencing has been installed to control erosion. quarters of 2000 with formal groundbreaking occurring on • Earthwork has started at a number of bridge locations. September 7,2000. At the end of the fourth quarter,overall • Haul roads have been constructed through area B I to keep design-build construction was 19 percent completed. (See page the overflow of traffic off the local roads. 6,"Subsequent Events:') • Two temporary bridges were built over the O'Brian Canal to provide direct access from borrow pits to the alignment Design Progress Summary By year-end,design for the total project was 50 percent Right-of-Way complete. For the last quarter of 2000,E-470 acquired possession of As design progressed at a rapid pace,the fourth quarter saw nine additional parcels in Sub-Package B1 (120th Avenue to US the first significant construction on Segment IV. At the end of 85)which leaves only six parcels remaining out of a total of 87 2000,design for area BI was 60 percent complete while area B2 parcels.One parcel in Sub Package B2 (US 85 to 1-25 North) was estimated at 20 percent complete.Both design and was acquired,bringing all acquisitions in B2 to a total of 30 construction work started at 120th Avenue and proceeded west percent with the goal of completing these activities in time for opening For the year 2000,in all of Segment IV,56 parcels were from 120th Avenue to US 85. Significant events during the acquired,bringing possession to 36 percent of all parcels,which fourth quarter included the release of significant right-of-way to equates to 866 acres (47 percent of total acres) and the design-build contractor and obtaining crossing agreements approximately 7.3 linear miles. All relocations of owners and on three of the largest and most significant irrigation canals, tenants have been completed. namely the O'Brian,Burlington and Bull canals. Area BI right-of- Eight oil wells were acquired and two tank batteries were relocated or removed in oil and gas acquisitions completed in way was contractually due for release to the design-build contractor on November 8,2000. This was accomplished with 2000. All such acquisitions are to be completed by May 8,2001 the exception of one small ditch crossing,the Sable Ditch. to facilitate the construction schedule. I Condemnation is proceeding to allow release of the ditch for construction.Relocation of this ditch will be required but this Project Financial Highlights work is not critical to job progress. In May of 2000,the Authority closed on a $358,048,750 bond Significant early construction progress has been made. issue to finance Segment IV. This raised the total debt for E-470 Embankment work is well ahead of schedule and the design- to approximately$1,231,000,000. Through the fourth quarter, build contractor is ready to begin bridgework with piling and MKK had invoiced the Authority$44,508,000 or about 19 caisson construction at Second Creek, percent of the total contract value. Utilities Major Interchanges Fifteen out of 51 identified utility packages (all in the area B I) Working with CDOT,preliminary design is underway for completion of three interchanges (1-25,US 85 and 1-76) plus the have been released for construction. Utility nlans include water. later date when funding is generated from toll revenues.Land Timeline Milestones developers and member jurisdictions have requested that E-470's design-build approach allows portions of the highway certain interchanges be constructed in advance of the future to be designed even as other portions are being constructed, dates or under an accelerated timing from the original planned accelerating the completion schedule over the conventional construction date. In the fourth quarter,the Authority's Board design-bid-build process. of Directors approved a new policy for accelerated interchanges In Segment IV,that accelerated pace continued in the fourth that requires the proponents of the interchange undertake all quarter. In the Sub-Package BI,the eastern portion of the construction costs with any future reimbursements by the construction,earthwork was two months ahead of schedule by Authority made to member jurisdictions. year-end,and engineering design was already 60 percent The Gartrell Road interchange was the first such accelerated completed— on target for its scheduled completion in the interchange.Operating under a "shadow toll"agreement,US second quarter of 2001. Home,the financiers of the construction for the interchange, The western portion,Sub-Package 82,will finish paid all tolls for customers from its inception in April 2000 to E-470's semi-circular loop back to 1-25. Right-of-way year-end 2000,when regular tolls commenced. The two-lane acquisition and engineering— preparatory to construction this ramp at the Gartrell Road interchange is the prototype for all spring—were by year-end both 20 percent complete. Right-of- future diamond interchanges on E-470. The dual functionality at way progress was well-positioned to gain momentum in the each toll location allows ExpressTollTm customers to by-pass first quarter of 2001. Design should be on track for cash customers paying at the automatic coin machines. completion in mid-summer of 2001. The Quebec interchange has been proposed for accelerated implementation by a local developer,Gateway American Properties. Gateway has agreed to finance the design portion of the project.Once the design is complete,Gateway will make a decision on funding construction. Other accelerated interchange activity in the fourth quarter included: planning interchange completion of Potomac- Chambers and a new half-diamond at Jamaica (formerly Cottonwood) near 1-25 and C-470. E-470 Segment IV Completion Schedule Sub-Package B1 (120th Ave.to US 85) r Financing completed;Notice to Proceed given 20 Design 60 percent complete Engineering f r100 percent of right-of-way acquired ahead of schedule Right-of-Way III -Ground breaking held September 7,ahead of schedule Earthwork two months ahead of schedule Construction 5udget and Revenue On the (load • A final budget amendment E-470 The fourth quarter of Year 2000 Total EXpressToll"'Accounts and Transponders Issued for the year 2000 budget 000 2000 continued to show was made in December, growing public acceptance — E%p,aaTolf'RcrouM• 2000. 7°000 -mp.pood.c lou.e of paying tolls to receive • The final operating budget so 000 E-470's driving benefits of for the year was speed,safety,and reliable, $18,744,000. 50,000 - . uncongested traffic • Year-end revenue from conditions. tolls was $23,235,175 or 4°000 µ The number of 99.16 percent of the 000 ; ExpressTollT' transponders projected amount issued by the end of the • Vehicle Registration Fees 20,000 year reached 77,089—a 63 • amounted to $6,953,274 percent increase from the or 102 percent of budget 10,000 end of January. • Highway Expansion Fees l , , 'I l Monthly toll revenue in ° totaled $372,185 or 155 ski mss/ m Vic` / / 1 f cc, gyp` dt .,j` the fourth quarter was percent of the budget s°° Imo T ' q'v`° o& ., t solid too,averaging nearly $2.1 million. Weekday transactions averaged over 83,000 for the quarter,far E-470 surpassing the original trier Capital Year 2000 Monthly Toll Revenue 66,000 projected and $2,500,000 rro ect5 �••^T^x• making the final quarter the -Electronic Tolls . second strongest of the $2,000000 - year—both in transactions Maintenance and revenues. Support Sites $1,500000 Construction commenced in the fourth quarter at 5 �000 Maintenance Support Site A (MSS A),near Jordan Road $500,000 ; and E-470 in Segment 1,and also at MSS C,adjacent to 0 the Central Maintenance tco'a� eet 41) / 4,3; S I Sr O6amF'°9 F'°m Facility at Plaza C.MSS A is m eQ + scheduled for completion in November of 2001 while MSS C should be occupied E-470 around June 1,2001. Year 2000 Weekday Toll Transaction Average ,1 5oard of Area Activity and r conomic Impacts pirectors Management Following the November election and the failing of"slow growth" Roland E. Cole Edward J. DeLozier initiatives,development referrals evened off to 28 in the fourth City Council Member, Executive Director quarter. These referrals were evenly split between the northern and Commerce City, southern member jurisdictions of the Authority. Chairman John D. McCuskey American Furniture Warehouse's 635,000 square foot showroom, Diiecwr of Finance and Audit located near the Peoria Street exit,will open to the public in March Noel Rustic 2001, resulting in a positive traffic increase along Segment I due to this Mayor, Matthew M. ,McDole City of.Thornton, Chief retail development. Aurora's Segment III activity includes discussions 'Engineer regarding Kings Pointe,a development of 2,118 residential units on 944 FirstVice Chairman acres. Several major retail developments have been reviewed,including Lynn Myers David M. Kristiek M a 1.5 million square foot retail center at Smoky Hill Road and E-470. o Director f�erations The World Park,a 5,500-acre sports park proposed for Arapahoe County Commissioner, Arapahoe County, Timothy Paranto County,is on hold at this time. Residential development continues to Second Vice Chairman dominate the southern area.East and north of Parker Road to Smoky Director of Maintenance Hill Road,approximately 29,000 single and multi-family units are being Terry V. Lucero planned. Mayor,. The majority of referrals from the northern section of the E-470 City of Brighton, corridor are for residential or mixed-use developments. The City of Secretary N Thornton has secured several annexations which will bring retail and j jeao Qua rters commercial development to this portion of E-470. Gary Lasater Mayor,_. Address: Town of Parker, 22470 E.6th Parkway Treasurer Suite 100 Aurora,Colorado 80018 SulDse uent r vents James R. Sullivan County Commissioner, Telephone: In a press release dated March 2,2001,Washington International Douglas County, 303-537-3470 Group,Inc.("WGI"),one of the members of the Design-Build Director Contractor,announced that"the company faces severe near-term liquidity problems due to a delay in resolving purchase price Paul E. Tauer adjustments in connection with its acquisition of Raytheon Engineers& Mayon Constructors (RE&C),and due to substantial cost overruns and City of Aurora, Director negative cash flows associated with certain RE&C projects acquired." WGI also stated that it is in default under certain covenants in its Ted Strickland senior credit facilities with its banks and that its viability is dependent County Commissioner, upon resolution of its near-term liquidity problems. WGI stated that it Adams County, is considering alternatives to increase liquidity but,given the near-term Diret tor nature of its liquidity problems,WGI's alternatives are limited and there is no assurance it will be able to obtain additional funds. WGI et,t d tint if it it •melJo to nkt,in f,,nde "it ,nnyt ...,..nn L e. 1 1Y:M rr- as b F' �• J, } S e 144th A eat $. t � o . �" **/ > 13 II� .pF '� 5 0 1 136th Avenue c.) s tlit A <•:;y;:s ;,`:s 4t 128th Aveywe il . 124th Avenge • 20thAveoue '20th A '® 1" i L....______112th Avenue Denver International I y 104th Avenue 7 Ai ort J 104th Avenue rP 100th Avenue 1 I I __ I 96th Avenue lti - �l^ �— t 1 rl ,t 3 �• 76 t= D 88th Ave. e `-..., $ p ■il 1' , Rocky Mountain Arsenal Pella Blv.. , National Wildlife Refuge r. _ I I I e'? - $ e ton Redevelopment ', ° 1 ��o'•,� u 26th Avenu (——- Co� Ave. Monlview 0 131 7 ��I��iilfiil►� o�as•ve e x 7SmAvenue 6thAv:ri � r� 7. Aven � �' ; ad� II _ Lowry kkk!eyy Ave. Campus NahoitalGN •V Legend Base m a LI °E-470 Segment I o 1 3 Mississ o.i Ave 8 _ & g 1 4 E-470 Segment II a = _ - 're,,P . ' b_.� --E-470 Segment III a Evans A I• a; E-470 Segment IV m ■Yale Av _ t ve a Under Construction �11 $ Highways/Principal Arterials k HMmytlen A 13 ♦ _Hampden Avenn, ,..r, MaJOr Road � �, I r,`1 e County Border I ,,'^�t A - _a g. .. cs l k� ( 7.11 Lake '' 4 ' mokv Hill R 7. n E-470 Toll Plaza �-.. Hello