HomeMy WebLinkAbout20012900 CHANGE ORDER
CHANGE ORDER NO. 1
DATE: 10-09-2001
PROJECT: SOUTHWEST WELD COUNTY SERVICE CENTER ACCESS ROAD PROJECT COUNTY ROAD 24 1/2
TO (CONTRACTOR) : T & T Concrete, Inc
JUSTIFICATION: The completion of the Weld County Service Center Road.
You are directed to make the following changes in the work. All other terms and conditions of the
Contract not expressly modified hereby shall remain in full force and effect.
ITEM NO. DESCRIPTION EST.OTY. UNIT UNIT COST AMOUNT
201 Clearing & Grubbing 1 L.S. $9,325.09 $9,325.09
203 Unclassified Excavation 148 CU.YD. $1.49 $220.52
203 Embankment Material (Haul & Place Only) 725 CU.YD. $3.69 $2,675.25
304 Aggregate Base Course (Class 6) 547 Ton $12.43 $6,799.21
207 Top Soil
110 CU.YD. $1.73 $190.30
403 Hot Bituminous Pavement (Grading S) 170 Ton $39.80 $6,766.00
609 Curb & Gutter, Type 2 (Sec 1-0) 105 L.F. $22.13 $2,323.65
609 Curb & Gutter, Type 2 (Sec 11-B) 509 L.F. $8.85 $4,504.65
210 Manhole Adjustment 1 Each $1,677.65 $1,677.65
210 Relocate Sprinkler Head 6 Each $84.72 $508.32
210 Relocate Sprinkler Valve Box 3 Each $91.50 $274.50
411 Emulsified Asphalt (CSS-1H) 50 Gal. $1.09 $54.50
614 Sign Panel ClassIT-S.E. 9 Each $35.83 $322.47
614 Timber Sign Post 6"x6" 15 L.F. $10.38 $155.70
625 Construction Survey 1 L.S. $2,812.50 $2,812.50
Pavement Marking Paint 7 Gallon $89.71 $627.97
TOTAL $39,238.28
The original Contract sum was $ $434,389.66
Net change by previous change orders $ $ 0.0
The Contract sum prior to this Change Order was $ $434,389.66
The Contract sum will be (increased) (decreased) or
(unchanged) by this Change Order $ $ 39,238.28
The Contract sum including this Change Order will be $ $473, 627.94
The new Contract time will be (increased) (decreased) or (changed) by Ten ( 10 ) days.
The date of completion as of the date of this Change Order is therefore November 11 , 2001 .
ACCEPTED BY: ORDERED BY:
/
/ d" Cskit ;tide . THE BOARD OF WELD COUNTY COMMISSIONERS
Contractor Address: . 0. Box 758
.51-
Greeley, CO 80632
3000 - FBy f�
//'� Address/
6 N fe ir 4..Y 0 2-84.3 I . . Geile, Chair
By D , iYw.. Date IO-1Om2OO1
Date C?-4--/L 7, <2O0 i
2001-2900
Hello