HomeMy WebLinkAbout20033151.tiff AGREEMENT
Bridge Rehabilitations
THIS AGREEMENT,made this day of ,20
by and between Weld County, Colorado,hereinafter called"Owner"and
J-2 Contracting Company doing business as
(an individual,) or (a partnership,) or (a corporation)hereinafter called"Contractor".
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned:
1. The Contractor will commence and complete the following: Bridge Rehabilitations described in the Invitation
for Bids,Bid No. B0300209
2. The Contractor will furnish all of the material, supplies, tools, equipment, labor and other services necessary
for the construction and completion of the Project described herein.
3. The Contractor will commence the work required by the Contract Documents within ten(10) calendar days
after the date of the Notice to Proceed and will complete the Bridge Rehabilitations within 165 calendar days
unless the period for completion is extended otherwise by the Contract Documents.
4. The Contractor agrees to perform all of the Work described in the Contract Documents and comply with the
terms therein for the sum of$ 110,305.00 ,or as shown in the Bid Schedule.
5. The term"Contract Documents"means and includes the following:
(A) Invitation for Bids
(B) Instructions to Bidders
(C) Bid Proposal
(D) Bid Bond
(E) Statement of Qualifications and Subcontractors
(F) Required Project Forms
(G) Agreement
(H) Labor and Materials Payment Bond
(I) Performance Bond
(J) Notice of Award
(K) Notice to Proceed
(L) Change Order
(M) Certificate of Substantial Completion
(N) Lien Waiver
(O) Notice of Acceptance
(P) Specifications prepared or issued by the Weld County Public Works Department.
(Q) Colorado Department of Transportation "Standard Specifications for Road and Bridge
Construction"
(R) Colorado Department of Transportation Standard Plans"M&S Standards"
(S) Addenda:
No. , dated ,20
No. , dated ,20
6. The Owner will pay to the Contractor in the manner and at such times as set forth by the Contract
Documents,or otherwise agreed upon in writing.
C5M32Mt' 000000�jz.rdA.,
2003-3151
7. This Agreement shall be binding upon all parties hereto and their respective heirs, executors, administrators,
successors,and assigns.
8. Contract Appropriations: The Owner hereby states and affirms that the amount of money appropriated for
this Contract is equal to or in excess of the Contract amount. No change order to this Contract requiring
additional compensable work to be performed, which work causes the aggregate amount payable under the
Contract to exceed the amount appropriated for the original Contract shall be issued by the Owner unless the
Owner assures the Contractor, in writing, that lawful appropriations to cover the costs of the additional work
has been made or unless such work is covered under a remedy-granting provision contained in the Contract.
IN WITNESS WHEREOF,the parties hereto have executed,or caused to be executed by their duly authorized officials,this
Agreement in three(3)copies each of which shall be deemed an original on the date first above written.
ORDERED BY: ACCEPTED BY:
THE BOARD OF WELD COUNTY COMMISSIONERS CONTRACTOR
�e 7
BY V BY hcr<
NAME Robert D. Masden N John C . Leone
(Please Type)
TITLE Chair Pro Tem TITLE President
Date 11/05/2003 ADDRESS 929 38th Ave . Ct . #106
Greeley , CO 80634
(SEAL) (SEAL)
ATTEST: ELM ate` ATTEST:
Weld Coun C eer l.: ��;: _. 1♦�
BY BY John C. Leone Jr .
Deputy Clerk to�; /�rT \ P (Please Type)
TITLE Sec . /Treas .
rit-";),
MEMORANDUM
'Ripe TO: Esther Geisick, Clerk to the Board DATE : 11/3/2003
COLORADO FROM: Frank B. Hempen, Jr., P.E.
Director of Public Works/County Engineer
SUBJECT: Consent Agenda, Chair's Signature
Please submit the enclosed item for the Chair's approval:
Agreement for Bridge Rehabilitations with J-2 Contracting Company in the amount of
$110,305.00
The appropriate documentation is enclosed.
Enclosures
pc: Cameron Parrott, Engineering
M:AFrancieASignatureltem.DOC
66-Y1/21}J. OydALL
Hello