Loading...
HomeMy WebLinkAbout20031211.tiff CONTRACT FOR ENGINEERING SERVICES FOR THE DESIGN OF WELD COUNTY ROAD 13, FROM WCR 2 TO WCR 8 THIS AGREEMENT, made and entered into this ' ./ M day of (Y1f.q , 2003, by and between the COUNTY OF WELD, of the State of Colorado, with offices at 1111 H Street, P.O. Box 758, Greeley, Colorado, 80632, hereinafter referred to as "County", and the professional consulting firm of Jehn & Associates, Inc., with an office 4112 Kodiak Court, Frederick, CO 80504, herein after referred to as "Consultant". WITNESS ET H: THAT WHEREAS, the County has established a program of design and construction of public improvements on WCR 13, from WCR 2 to WCR 8; and WHEREAS, the County desires to obtain professional engineering services for the design of public improvements related to the heretofore-mentioned project; and WHEREAS, Consultant represents that they possess the necessary qualifications to perform these services. NOW, THEREFORE, for the consideration herein expressed, it is hereby agreed as follows by and between the County and Consultant: 1. EMPLOYMENT OF CONSULTANT The County hereby agrees to engage Consultant and the Consultant hereby agrees to perform the services hereinafter set forth. 2. SCOPE OF WORK Section 1 - PROJECT SPECIFIC INFORMATION 1.01 Planned Improvement Weld County Road 13 is classified as a major arterial. The general planned improvement is to design and construct a two lane roadway that consists of 12' paved lanes, 10' shoulders (8' paved — 2' gravel) for the three mile section of gravel roadway with consideration for the ultimate section. 1.02 Project Goals Weld County has established the following design goals for the project: Provide preliminary design for the ultimate roadway section consisting of 4-12' paved lanes, 12' paved right turning lanes, 16'-26' paved center left turn lanes, 6' paved bike lanes, curb &gutter and 8' concrete sidewalks. Provide final design for the interim roadway section stated in Section 1.01 above. Determine road drainage requirements. WCR E 13,from WCR 2 to WCR 8 /,_ F, 5-1- b 3 00 i Poi 2003-1211 E-oFr7 Design safe, adequate, and economical waterway crossing structures along the project, based upon the interim section, including any irrigation facilities that may be impacted. Design safe intersections, driveways, and field intersections onto the new roadway. Identify right-of-way requirements for individual parcels. Also identify easements necessary for utility relocations and/or slope construction. Increase the capacity of WCR 13 1.03 Project Location This project is located in the southwestern portion of Weld County on WCR 13, approximately 4 mile south of the Town of Dacono. 1.04 Construction Cost The construction cost is to be determined by the Consultant. 1.05 Work Duration The Consultant shall complete the Design Services defined in the Scope of Work, Section 7, within 200 calendar days from the date of Authorization to Proceed as described in Part 1, Section 1.07, of the RFP, exclusive of all days lost for review and approved by the County. All days lost for review shall be documented by the Consultant and submitted to the County for consideration. For each calendar day that the Work is incomplete after the time specified or as adjusted and approved by County in writing, a sum of $200.00 may be deducted from moneys due to the Consultant as liquidated damages. This sum is fixed and agreed upon between the County and Consultant because the actual loss to the County and to the public caused by delay in completion will be impractical and extremely difficult to ascertain and determine. 1.06 Consultant Responsibility The Consultant is responsible for the completion of services and submittals defined in the Scope of Work or modified otherwise by change order, in accordance with acceptable engineering practices and guidelines. 1.07 Work Product The general work products to be completed by the Consultant are: Reports and Submittals Project Survey Preliminary Plans and Cost Estimates Right-of-Way Plans Final Plans, Project Specifications, and Engineer's Estimate 1.08 Additional Project Information Additional information regarding this project is included in the following documents: None WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 2 Section 2 - PROJECT MANAGEMENT AND COORDINATION 2.01 Owner Contacts OWNER: Weld County Board of County Commissioners The Contract Administrator, having full responsibility for acting on behalf of the owner, for this project is: NAME: Frank B. Hempen, Jr., P.E. TITLE: Director of Public Works/County Engineer ADDRESS: P.O. Box 758, 1111 "H" St. Greeley, CO 80632 TELEPHONE: 970.356.4000, ext. 3750 The County Project Manager (C/PM), having active day-to-day administration for this project is: NAME: Wayne Howard, P.E. TITLE: Project Manager ADDRESS: P.O. Box 758, 1111 "H" St. Greeley, CO 80632 TELEPHONE: 970.356.4000, ext. 3788 2.02 Project Coordination Coordination will be required with the following: Weld County City of Northglenn Utility Owners Local Developers Local Land Owners Others as required The Consultant should anticipate that a design which affects an agency will have to be accepted by that agency prior to its acceptance by the County. Submittals to affected agencies will be coordinated with the County. Section 3 - PROJECT DESCRIPTION 3.01 Background Weld County Road 13 is classified as an arterial roadway and is considered a strategic corridor for the County roadway system. The steady increase of development along the Front Range has necessitated the need for north/south strategic corridors throughout the County. The project is funded by Weld County and is not subject to the administration of CDOT or FHWA. The consulting contract will be administered by the Weld County Department of Public Works. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 3 3.02 Project Limits The road limits extend from WCR 2 to WCR 8. The Consultant shall anticipate that enough survey data should be gathered north and south of the project limits to make necessary connection to the existing roadways. Survey data should also extend at a minimum, 100' east and 100' west of centerline of roadway. Additional survey data may be necessary at particular locations and the Consultant is responsible for making this determination. Section 4 - KNOWN EXISTING FEATURES 4.01 Structures Bridge WEL013.0-006.0A and miscellaneous small crossings 4.02 Utilities To be determined 4.03 Irrigation Ditches Bull Canal 4.04 Railroads None 4.05 Local Development Unknown NOTE: The above is a list of the known features in the area. It should not be considered as complete. The Consultant should be alert to the existence of other possible conflicts. Section 5 - ITEMS TO BE FURNISHED BY OWNER 5.01 Manuals, Specifications, Standards, etc. All County References and forms specified in this document Accident history data of WCR 13 and intersecting roadways Existing Bridge Inspection Reports Section 6 - PROJECT STANDARDS 6.01 Project Standards - In the absence of County defined procedures, some references have been adopted for use in the work defined by this Scope of Work. Roadway Design Manual, CDOT, Latest Edition Design Guide, Volume 1 w/AASHTO Chapters, CDOT, Latest Edition Standard Specifications for Road and Bridge Construction, CDOT, Latest Edition M & S Standards, CDOT, Latest Edition Drainage Design Manual, CDOT, Latest Edition A Policy on Geometric Design of Highways and Streets, AASHTO, Latest Edition WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 4 Manual on Uniform Control Devices, FHWA, Latest Edition Contract between County and Consultant Section 7 -WORK ACTIVITY ASSIGNMENTS This list establishes the consultant's individual task responsibility. The Consultant shall perform all work tasks which are indicated by an "X" mark in the Consultant column, in accordance with the conditions described. The Consultant is also responsible for coordinating the required work schedule for those tasks accomplished by the County and other agencies. PRECONSTRUCTION WORK TASKS The following includes work descriptions for all tasks normally accomplished during this phase of work. The Consultant should review this entire section to identify applicable material. Contact the C/PM if clarification is required. The following activities should be planned by the Consultant and coordinated with the C/PM. The time of their accomplishment will overlap and parallel paths of activity and should be planned to finish the development phase in accordance with the shortest possible schedule. The type and number of meetings, documents, etc., will depend on the category and characteristics of the project work. 7.01 Project Initiation and Continuing Requirements County Consultant Submittal Req'd 7.01.01 Initial Project Meeting. �r An initial meeting will be held and an on-site inspection (when appropriate) will be made to ensure that the Consultant is familiar with the existing conditions as well as the project requirements. A pre-survey conference may be held in conjunction with this meeting. This meeting will be coordinated by the Consultant and conducted by the C/PM. Notices for the meeting will be sent by the Consultant from a list provided by the C/PM. 7.01.02 Review Environmental Mitigation Requirements. ❑ Q Review mitigation requirements and ensure that they are included in the plan for design. 7.01.03 Independent Design Review. ❑ �r An independent design review shall be performed on the design accomplished by others that will be used in this project. 7.01.04 Project Schedule. ❑ �r The Consultant shall develop a detailed project schedule with assigned tasks and submit to the C/PM for approval. The schedule shall be updated as necessary. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 5 7.01 Project Initiation and Continuing Requirements County Consultant Submittal Req'd 7.01.05 Right of Entry and Permits 0 Q Some activities may require work on land not controlled by the County. In such cases the Consultant shall obtain the necessary written permission to enter the premises. Included in this written permission will be the names and telephone numbers of persons to contact should notification prior to entry be necessary. These written permissions will apply to County personnel as well as Consultant personnel. A Weld County Right to Enter Form may be used unless the Consultant has his own Right to Enter form and the format is approved by the C/PM prior to use. An Assessor's Map, identifying ownerships of all adjacent properties, individuals contacted, addresses & phone numbers shall be provided indicating which properties have signed right of entries. All signed copies of the written permission will be submitted to the C/PM prior to entering private property for survey work. The C/PM shall be notified immediately of any property owner refusing to sign the form or allowing permission to enter. Some activities such as materials testing on existing pavement and structures may require a permit. Permits will be obtained and copies submitted to the C/PM. 7.01.06 Traffic Control prior to construction. ❑ r-�r Consultant field activities that interfere with traffic operations within existing roadways will require control of existing traffic. The Consultant will plan and provide any required traffic control for the survey, testing, or design process. Traffic control operations will be in accordance with the MUTCD. A Traffic Control Supervisor, certified by the American Traffic Safety Services Association(ATSSA)will be required. 7.01.07 Initial Submittal. 0 Q Submit the following samples to the C/PM for approval: -An original plan sheet-Photogrammetric and/or survey data NO ORIGINAL PLAN SHEETS OR PHOTOGRAMMETRIC SURVEY WORK WILL BE ACCOMPLISHED UNTIL SATISFACTORY SAMPLES HAVE BEEN RECEIVED AND APPROVED BY THE C/PM. 7.01.08 Progress Meetings. r?r The County and Consultant Project Managers will meet periodically as required (typically monthly intervals). These progress meetings will be used to coordinate the work effort and resolve problems. The meetings will review the following: 1) Activities completed since the last meeting. 2) Problems encountered. 3) Late activities 4) Activities required by the next progress meeting. 5) Solutions for unresolved and anticipated problems. 7.01.09 Project Management. r�r The Consultant will coordinate all the work tasks being accomplished by all �J parties to ensure project work completion on schedule. 7.02 Project Development County Consultant Submittal Req'd WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 6 7.02 Project Development County Consultant Submittal Req'd 7.02.01 Communication and Consensus Building. Establish and maintain a computerized list of all appropriate receptors for the communication process. a.Contact list: ❑ The contacts will be compiled from the general list below as supplemented by the Project Review Team. The list will be used for notices regarding public meetings, mailing newsletters or other communications as appropriate. The information on the list shall include as a minimum, name, firm(if any),mailing address,and phone number. Project Review Team Elected/Appointed officials Utility Companies Property Owners/Tenants Railroad Companies Public Agencies b. Public Notices/Advertisements. ❑ ❑ ❑ Copies of the advertisement shall also be mailed to the individuals on the contact list. Following the public notice, conduct small group and general public meetings as approved by the C/PM to gather information which will be used to formulate and test the alternative designs. c. General Meetings. The types and number of meetings shall be flexible and determined by an interactive process as approved by the C/PM. Minutes of these meetings will be provided to all participants. Small Group Meetings(one-on-one). ❑ Meet with property and business owners or others directly affected by the project work to identify likely impacts and discuss possible mitigation or resolutions General Public Meetings(informal and workshops). ❑ ❑ ❑ The format of these meetings will be dictated by the project and goals for the meetings. Informal meetings may be used to establish communications with the public, add to the contact list,and gather information regarding local concerns. Project Review Meetings. ❑ ❑ ❑ These meetings are intended to disseminate project progress information to the public and representatives of local entities. The Consultant will provide the presentation aids,conduct the meeting,and provide complete minutes of the meetings. d. Communication Aids. ❑ El ❑ Graphic Support. Provide the graphics for public presentations and environmental documents. This could include slides, overhead projections, aerial maps and plan views, and other displays for visual presentations at meetings. 7.02.02 Project Review Team. A project review team shall be organized consisting of the County and Consultant project managers(along with others from key public agencies and other public and private interests, as appropriate). This team will meet as appropriate to coordinate activities required to accomplish the project goals WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 7 • 7.02 Project Development County Consultant Submittal Req'd and objectives. 7.02.03 Route Location Surveys. ❑ ❑ ❑ Surveys will be conducted in accordance with the CDOT Survey Manual and the latest addendum thereof. a. Survey data research. O ❑ ❑ b. Secure Rights of Entry. See Section 7.01.05 ❑ ❑ ❑ 7.02.04 Conceptual Design. Conceptual design development shall be managed by the Consultant to occur along with communication,project team reviews,data gathering,environmental mitigations,and documentation activities as appropriate to complete the process in the minimum time feasible.Conceptual Design shall consist of the following: a. Alternatives Analysis. Develop Alternatives Develop an agreed number of alternatives which will satisfy the operational requirements of the project. When required, conceptual layouts will be developed for major structures for each alternate, which shows satisfaction of the required span arrangement and the horizontal and vertical clearances. Examples of things to consider while developing alternatives are alternate routes, accident history, physical impacts,effects on the existing highway system, economic development impact, and local commitment to improving local roadways. These alternatives must respond to projected design year traffic volumes as developed for this scope. Evaluate the impacts of these alternative concepts and the degree to which they accomplish the objectives. These concepts will be described schematically and in narrative,and reviewed by County. Complete an initial design of the designated alternatives. Once the alternatives have been selected, general profile and cross section studies will be developed for critical areas to analyze the designated alternatives. This information shall be sufficient to determine general cut and fill limits, right-of-way and easement requirements, and earthwork and structural requirements. Design parameters such as design speeds, maximum grades, typical sections, intersection designs, and pedestrian routing will be determined at the beginning of the study. The conceptual design for the roadway alignments, detours, and major structures will be completed sufficiently so that preliminary cost estimates can be developed and the satisfaction of pertinent design criteria can be demonstrated. Necessary variances will be identified. Perform a financial analysis on the selected alternatives. A construction cost estimate will be developed for the alternatives selected by the C/PM. WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 8 7.02 Project Development County Consultant Submittal Req'd b. Final Alternatives Reports. IZI ❑ Complete the determination of the selected alternative. If specified, a Final Alternatives Report will be submitted documenting the analysis process. This shall include the environmental concerns, utility conflicts, drainage, right of way requirements, and total cost for the recommended alternatives. THE CONSULTANT IS RESPONSIBLE FOR ENSURING THAT THE RECOMMENDED ALTERNATIVE COMPLIES WITH APPLICABLE STANDARDS AND CRITERIA. WHERE APPROPRIATE,REQUIRED VARIANCES SHALL BE IDENTIFIED. 7.02.05 Gather Data,Analysis,and Mitigation Development. a. Traffic Related Studies Traffic Study. �-7( ❑ IJ Obtain the available present day and design year traffic volumes for the existing and planned improvements. When possible, local traffic patterns will be defined. The data shall include percentage trucks, directional splits, and turning movements. The alternative designs will be analyzed with the traffic projection data to develop the appropriate roadway geometry(i.e., number of lanes, auxiliary lanes, storage lengths, and weaving distances)in accordance with applicable standards. Accident Study. Obtain accident reports. Provide the data for the alternatives analysis activities. Alternative Transportation Systems. ❑ ❑ Evaluate the effect of other transportation systems on the proposed alternates when required. b. Archaeology ❑ ❑ ❑ Conduct a field survey and test excavations as specified. Accomplish a laboratory analysis of the diagnostic specimens. Write an archaeology survey report to recount the analysis of artifacts and describe the culture and importance. Develop and write the archaeology mitigation plan. Coordinate the plan with the State Historic Preservation Office and other agencies as required. Coordinate mitigation activities with the designated agencies. Excavate the site, analyze artifacts and prepare an archaeology survey report which describes the culture and importance of the artifacts. c. Paleontology. ❑ ❑ ❑ Determine if paleontology resources are present within the project site. Conduct field and literature surveys. If any resources are found, conduct an analysis to determine significance. Determine the potential for additional resources. Write a preliminary paleontology report and develop the mitigation report. Coordinate mitigation implementation activities as required. Excavate site, analyze resources and prepare the final Paleontology report. WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 9 7.02 Project Development County Consultant Submittal Req'd d. Initial Geology Investigation. ❑ ❑ A visual inspection of the project area shall be performed to determine possible geologic impacts on the alternative designs under consideration. Impacts such as major rock cuts, unsatisfactory subgrade materials,etc.,shall be evaluated. e. Water Quality. ❑ Determine the impact of the project during and following construction by considering the project location and design concept in relation to existing water resources such as streams and rivers (both surface and underground), lakes, and aquifers(particularly sole source). Develop a mitigation plan which includes erosion control measures. Identify necessary permits. g. Historical. ❑ ❑ ❑ Historical Bridge Clearance. Conduct a literature and records search. Consult the State Historic Preservation Office via the Region Environmental Manager, FHWA, and Staff Historian. Obtain clearance for non-eligible bridges. Historical Study and Clearance. ❑ ❑ ❑ Conduct a literature and records search. Consult the State Historic Preservation Office via the District Environmental Manager, FHWA, and advisory council. Write the cultural resources report. Determine effects and develop a mitigation plan. h. Floodplain and Drainage Assessment. ❑ ❑ ❑ Determine the probable impacts and adverse effects of each of the proposed alternatives on the project area with respect to the floodplain and drainage. Develop possible mitigating actions for the adverse impacts. Analyze the impacts and mitigation (if any). Include in the analysis a determination of significant impacts due to: -single community access routes -significant risk for social or economic losses due to flooding -alteration of beneficial floodplain values Complete a written"Floodplain and Drainage Assessment Report"which includes a detailed discussion of the pertinent aspects of the analysis, identification of possible practical mitigating actions for the alternatives. i. Right of Way(ROW) ❑ r�r r�r 1. Perform a field inspection of each short-listed alignment. Ascertain �J u the number of parcels and possible problem areas (mobile homes, functional replacements, historical sites,etc.). Prepare a property ownership map based on tax records which identifies ownerships for each alignment. WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 10 7.02 Project Development County Consultant Submittal Req'd 2. Prepare a land use map which identifies land usage along each ❑ ❑ ❑ alignment. The parcel use categories shall utilize appropriate categories, including; land in public ownership identified by specific use and responsible agency and jurisdiction; commercial (retail, wholesale, industrial, etc.); single or multi-family residential; vacant; mixed uses; or other specific uses. j. Threatened and/or Endangered species ❑ �7( n( Coordinate determination efforts with the Colorado Division of Wildlife and LI IJ USFWS. Prepare the T&E species assessment. k. Wetlands ❑ Q Q Conduct a field evaluation to determine the boundaries and size of all wetlands and determine how they may be affected by the project work. Affected wetlands will be mapped and the consultant shall provide a mitigation plan in the final construction plans. I. Hazardous materials ❑ Q Conduct a field research of project area. Research available records including: - Lists compiled by EPA or the Colorado Department of Health which identify:hazardous waste generators; hazardous waste transporters; hazardous water treatment/storage/disposal facilities (current and closed); locations of underground storage tanks; known and suspected or abandoned hazardous waste sites. - Records kept by EPA or Colorado Department of Health on hazard water regulation violations or citations. - Lists kept by the appropriate fire department on underground storage tank locations, HAZMAT incidents/accidents, and local emergency planning or hazard materials use reporting. - Available historic tax records which indicate past land use (coordinate with property ownership and land use data research). - Available historic aerial photos of the corridor. - Any other available pertinent records. m. Utilities ❑ Q 0 The effect of utilities will be investigated for each alternative. Collect the utility location maps for all utilities in the area. 7.02.07 Obtain permits. This activity is concurrent with final design and must be completed prior to the advertisement for construction. a. Determine impacts, prepare, and submit the 404 permit applications. Coordinate with the Corps of Engineers and County. Obtain the County's ❑ Q signature on permit. Transmit permit stipulations to the County b. Prepare the General Permit application for the Storm Water Discharge ❑ associated with Construction Activity. Coordinate any concerns with the application with the County. Submit the application to the County. Submittal 7.03 Preliminary Design County Consultant Req'd WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 11 7.03 Preliminary Design County Consultant Submittal Req'd 7.03.01 Design Field Survey. IZE Q a. Pre-survey Conference.(See section 7.01.01) b. Project Control. Survey the required project control(centerline/baselines and elevation reference) as required. Tie property corners and land monuments to the center/control line. c. Topographic Survey. Collect the data required to produce a planimetric map. Features located will include, but not be limited to, signs, mailboxes, fences, driveways and curb cuts, curbs, sidewalks, and edges of pavements. Horizontal accuracy shall be to the nearest one- tenth(0.1)foot. d. Vertical (relief or elevation) Survey. Collect elevation data. Natural ground elevations shall be to the nearest one-tenth (0.2)foot and man- made features (e.g., edges of pavement) shall be to the nearest one- hundredth(0.05)foot. e. Utilities. Located utility poles, manholes, valves, pedestals, guy wires, and other visible utility features. Survey underground utilities as marked by utility companies. Determine invert elevations of manholes and vaults. Survey the locations of utilities exposed by "potholing" done in accordance with Section 7.03.05. f. Drainage. Locate culvert and storm sewer pipes and determine invert elevations. Locate inlets and determine invert elevation of pipes. Accomplish drainage situation surveys for designated culverts and bridges. Material sources. Survey designated material sources as specked. h. Supplemental surveying. As required and specifically requested. THE COMPLETED SURVEY SHALL BE REVIEWED BY THE COUNTY. TWO WEEKS SHOULD BE PROVIDED IN THE SCHEDULE TO COMPLETE THE REVIEW AND SUFFICIENT TIME SHOULD BE PROVIDED TO ADDRESS ALL COMMENTS PROVIDED BY THIS REVIEW. DESIGN SHALL NOT PROCEED UNTIL ALL COMMENTS RESULTING FROM THIS REVIEW HAVE BEEN SATISFACTORILY ADDRESSED. 7.03.02 Traffic Engineering. ❑ a. Obtain the necessary data and necessary traffic counts (including percentage of trucks, directional split, and turning movements) and produce traffic projections for the design year in accordance with generally accepted procedures. b. Review accident data. Determine possible safety problems and recommend improvements. c. Analyze the proposed project design with the traffic projection data and recommend the appropriate geometry (Le., number of lanes, auxiliary lanes,access improvements,storage lengths). d. The proposed design shall be reviewed by the County for compatibility with existing signing procedures prior to the preliminary roadway design phases involving laneage,typical sections,earthwork,etc. e. Develop detour alternatives using current traffic volumes, pavement WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 12 7.03 Preliminary Design County Consultant Submittal Req'd conditions,and roadway geometry. f. Develop the total ESAL for the design period. g. Submit data and recommendations to the C/PM for acceptance. 7.03.03 Materials Engineering. a. Preliminary Soil Investigation. ❑ Determine test hole locations (horizontal and vertical). Collect soil samples and test for classification, moisture-density relationship, and resistance value. Analyze the test data to determine the soil structural capability. Prepare and submit a soils investigation report with recommendations to the C/PM. b. Pavement design report. ❑ Q Determine typical section pavement and base course designs based upon the information gathered. Include all the above tests, investigations, analyses, and calculation performed as a result of this section. c. Foundation investigation report. 0 0 Using the general structure layout and foundation investigation request, formulate the drilling pattern and perform the necessary subsurface investigation and collect samples as required. Perform the appropriate laboratory tests and determine strength and allowable bearing capacity of foundation material. Perform lateral analyses(deformation,moment, and shear) of the caissons or piles which are subjected to lateral loadings. Submit the Foundation Investigation Report to the County for approval. Prepare engineering geology plan sheet and foundation report with recommendations for type, size, and tip (bottom) elevation of the required foundation. Specify construction necessity for pre- drilling,pile tip,casing,dewatering,etc. 7.03.04 Hydrology/Hydraulic Engineering. a.Hydrology Establish drainage basin characteristics and data. Collect historical data including flood history, previous designs in the proximity, and data from other sources such as Urban Drainage & Flood Control District, Colorado Water Conservation, maintenance records, and local residents. Select a storm frequency based on the CDOT Design Manual criteria. Do a hydrological analysis using existing studies or approved methods. b.Hydraulics ❑ Determine location and crossing alignment of minor drainage structures, identifying channel centerline by road station or coordinates. Determine the allowable headwater. Assess the degree of sediment and debris problems to be encountered. Type, size and shape of structures. Prepare preliminary structure cross-sections to determine the elevations, flowlines, slopes and lengths of the structures. Indicate the flow quantity on the sections. Complete the design computations and documentation in accordance with the CDOT Drainage Design Guide. Determine high water level. A water surface profile and complete hydraulic analysis is required for major structures. Determine the required hydraulic size of the bridge (including the minimum low girder elevation using the CDOT Drainage Design Guide criteria), the predicted total scour depth, and the protection design. Recommend culvert pipe sizes for proposed on-site detours. WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 13 7.03 Preliminary Design County Consultant Submittal Req'd c. Storm Water Management Plan(SWMP). ❑ Q Prepare a Storm Water Management Plan in accordance with the CDOT Erosion Control and Stormwater Quality Guide, CDOT's Standard Specifications, Section 107.25, Standard Plan M-107-1 and other documents as appropriate. Include the following in the SWMP: Erosion and sediment control"Best Management Practices"(BMPs)to reduce pollutants in storm water discharges during construction operations. Consider: -Vegetative practices -Structural practices -Construction waste disposal(including excess excavation) -Compliance with applicable state or local sanitary or septic system regulations -Maintenance practices for sediment and erosion control features during construction Storm Water Management BMP's to reduce pollutants in storm water discharges after construction operations have been completed. Consider: -Vegetative practices -Structural practices d. Preliminary Hydraulics Report. Include the following: ❑ 1. Hydrology analysis 2. Minor structure hydraulic designs 3. Major structure hydraulic designs 4. Structure cross-sections 5. Stormwater pollution prevention plan 6. Drainage basin maps 7. Hydrology and hydraulic worksheets 7.03.05 Utility Coordination. ❑ Q a. Obtain available utility location maps from the utility companies which identify utility facility locations within the project limits. b. Conduct field reviews and utility investigations, as required, to ensure correct horizontal and vertical utility data. Utilities that have a possible conflict with the project shall be "potholed" utilizing non-destructive WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 14 7.03 Preliminary Design County Consultant Submittal Req'd investigative techniques. The horizontal and vertical locations will be shown in the FIR plans and cross-sections. (Weld County will pay for all "Potholing" required for the project. The Consultant shall receive pre- approval before"potholing"from the C/PM) c. Submit necessary information for the relocation or adjustments of affected utilities to the C/PM. The C/PM will process the required agreements. d. Contact ditch companies to coordinate design requirements for existing ditch relocations and/or modifications. Develop plans for the necessary irrigation structures and submit to the C/PM for review. 7.03.06 Roadway Design and Roadside Development. ❑ Roadway Design. Coordinate efforts with other design activities as required. Check and plot survey data. Draw a geometric layout to determine or verify the horizontal and vertical alignment. A project specific coordinate system shall be used to identify the horizontal locations of key points. The coordinate system used for roadway design and ROW shall be compatible. Check horizontal and vertical clearances against design criteria. Provide alignments and required ROW (preliminary design plans) to the manager responsible for producing the ROW ownership map. Plot all required information on the plans. Compute preliminary earthwork quantities. 7.03.07 Right of Way. ❑ �r Right of Way plans shall be researched and developed under immediate supervision of a Professional Land Surveyor(PLS). a. Research 1. Identify affected Ownership from preliminary design plans. 2. Obtain orthographic photography for the project limits from County's GIS Department. 3. Obtain parcel information from County assessor's records. 4. Obtain Title Commitment from each parcel of land affected. Title commitment shall include copies of all documents described and/or mentioned in legal descriptions and/or schedule B. 5. Physically inspect property. Note any physical evidence of easements,wells,ditches,ingress and egress. 6. Check for latest subdivisions plats and vacations of streets. b. Ownership map 1. Review preliminary design and field survey. 2. Establish basis of bearing prior to calculations. 3. Compute alignment and coordinates of all found legal monuments within the first tier of properties Lt and Rt of centerline. 4. Obtain and review memorandums of ownership, title commitments and supporting plats. The Consultant is responsible for supplying the C/PM with the parcel information (name. parcel WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 15 7.03 Preliminary Design County Consultant Submittal Req'd number,etc.,)requiring title commitments. 5.Calculate coordinates of lost or obliterated corners using guidelines established by the Bureau of Land Management. (To be used by field surveyor in resetting the monuments). 6. Establish subdivisions of sections using BLM guidelines. Show all section lines and aliquot parts on the ownership map. 7. Determine existing right of way limits from deeds of record and road records from Weld County. 8. Determine ownerships and existing easements of record. 9. Secure additional property owner ties and additional topography where the highway improvement may affect improvements adjacent to the right of way. This additional topography should include underground cables and conduits,wells, irrigation ditches and systems,and septic tanks,cesspools,and leaching fields. 10. Reconcile overlaps and gaps in ownerships as required, documenting method used (may required additional field work). After one deed is reconciled,submit documentation for approval before proceeding. Example: Used existing fence in field, used deed measurements,etc. Include in diary. 11. Plot the preliminary ownership map with orthographic photography. Normal scale, 1"=400'in rural areas, 1"=200'in urban areas. If entire ownership will not fit on the sheet at this scale, an additional abbreviated map may be used at a scale of 1"- 1 mile, or other suitable scale, to show the configuration of large ownerships. 12. Label all monuments found with description of monument and coordinates. 13. Show improvements and topography within the ownerships as well as existing access to the road system. 14. Number ownerships alternately as they occur along the centerline from south to north or west to east in the same direction as the stationing. Show current names of owners and lessees. 15. Calculate area of all ownerships affected, establishing bearings and distances on all ownership lines', including coordinates of all property corners. Deduct areas for existing road rights of way. Bearings, distances and coordinates do not need to be shown on 1"to mile abbreviated map. 16. Show areas of complex ownerships graphically by cross hatching different land uses. 17. In the lower right corner of the map, show seal, number and name of the PLS supervising the work. 18. Transmit finished reproducible preliminary ownership map and memorandums of ownership to C/PM along with all calculations, field notes, and supporting data. The preliminary ownership map will include a control and monument sheet. Note that only the project control data needs to be completed at this time. WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 16 7.03 Preliminary Design County Consultant Submittal Req'd 7.03.08 Structures Structures shall be designed in accordance with the AASHTO Standard Specifications for Highway Bridges and the CDOT Bridge Design Guide. The C/PM will participate in coordinating this activity. a.Structural data collection. 1. The following data, as applicable, shall be collected: typical roadway u u section, roadway plan and profile sheets showing all alignment data, topography, utilities, preliminary design plan, Right-of-Way restrictions, preliminary hydraulics and geology information, environmental constraints, guardrail types, recommendations for structure type and architectural recommendations. 2. When required, collect data on existing structures such as existing plans, inspection reports, structure rating, foundation information, and shop drawings. b.Structure Layout and Type Study ❑ 1. Review the structure site data to determine the requirements that will control the structure size, layout, type, and/or rehabilitation alternatives. On a continuing basis, provide data and recommendations to other members of the design team(e.g.,roadway, hydraulics,survey)to help finalize the structure site data. 2. Determine the structure layout alternatives. Determine the structure length, width, and span configurations that satisfy all horizontal and vertical clearance criteria. Working with the roadway designer, determine the necessary length of walls,and the top and bottom of wall profiles. 3. Determine the rehabilitation alternatives. Continued use of all or parts of existing structures shall be considered as applicable. The structural and functional adequacy of existing structures shall be investigated and reported. Determine the modifications and rehabilitation necessary to use all or parts of existing structures and the associated costs. 4. Determine the structure type alternatives. Consider precast and cast- in-place concrete and steel superstructures and determine the spans and depths for each. For walls, determine the feasible wall types in accordance with the CDOT Bridge Design Manual Section 5. 5. Determine the foundation alternatives. Consider piles, drilled shafts, spread footings, and mechanically stabilized earth foundations based on geology information from existing structures and early estimates from the project geologist. To obtain supporting information, initiate the foundation investigation as early as possible during the preliminary design phase. 6. Develop the staged construction phasing plan, as necessary for traffic control and detours, in coordination with the roadway design and traffic control plan. The impact of staged construction on the structure alternatives shall be considered and reported. 7. Compute preliminary quantities and preliminary cost estimates as necessary to evaluate and compare the structure layout, type, and rehabilitation alternatives. 8. Evaluate the structure alternatives. Establish the criteria for evaluating and comparing the structure alternatives that encompass all aspects of the project objectives. Elements typically considered include safety, construction costs, construct ability, life cycle costs (durability), environmental considerations, aesthetics, in service maintenance and inspection, and the ability to rehabilitate, widen and replace the new WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 17 7.03 Preliminary Design County Consultant Submittal Req'd structure. Based on this criteria, select the optimum structure layout type, and rehabilitation alternatives, as applicable,for recommendation to the County. 9. Prepare preliminary general layout for the recommended structure. Prepare the structure layout. Obtain a structure number from the County to show on the layout. Special detail drawings shall accompany the general layout where appropriate. Perform an independent design check of the general layout. c. Structure Selection Report ❑ r7( 1-7( Prepare a structure selection report to document and obtain approval for LI LI the structure preliminary design. By means of the structure general layout,with supporting drawings, tables, and discussion, provide for the following as applicable: 1. Summarize the structure site data used to select and lay out the structure. Include the following: -Project site plan -Roadway vertical and horizontal alignments and cross sections at the structure. -Existing structure data, including sufficiency rating and for HBRRP projects,whether or not the structure is on the select list. -Utilities on,below,and adjacent to the structure. -Hydraulics: Channel size and skew, design year frequency, minimum low girder elevation, design year and 100 year high water elevations, estimated design year and 500 year scour profiles, and channel erosion protection. -Preliminary geology information for structure foundations. -Architectural requirements. 2. Report on the structure selection and layout process. Include the following: -Discuss the structure layout, type, and rehabilitation alternatives considered. -Define the criteria used to evaluate the structure alternatives and how the recommended structure was selected. -Provide a detailed preliminary cost estimate and general layout of the recommended structure. 3. Submit the report for review and comment by County to obtain acceptance of the recommended structure type and its layout. Allow at least two weeks for review. The associated general layout, with revisions required by the County, will be included in the FIR plans. The work schedule shall be planned accordingly. d. Foundation Investigation Request. ❑ ❑ ❑ Initiate the foundation investigation as early in the preliminary design phase as practical. On plan sheets showing the project control line, its stations and coordinates, as well as any utilities, identify the test holes WCR 13,from WCR 2 to WCRB Engineering Contract-Page 18 7.03 Preliminary Design County Consultant Submittal Req'd needed and submit them to the project geologist. The available general layout information for the new structure shall be included in the investigation request. 7.03.09 Preparation for the Field Inspection Review(FIR) ❑ Q a. Coordinate, complete, and compile the plan inputs from other activities: materials,hydraulics,traffic, right of way,and major structures. b. If a major structure is included, a general layout, accepted by the County,will be included in the FIR plans. c. Prepare the preliminary cost estimate for the work described in the FIR plans based on estimated quantities. d. The FIR plans will include: title sheet, typical sections, general notes, plan/profile sheets, and preliminary layouts of intersections. The plan and profile sheets will include the following: all existing topography, survey alignments, projected alignments, profile grades, ground line, existing ROW, rough structure notes (preliminary drainage design notes),and existing utility locations. The following items will be mandatory for the FIR plans: -preliminary earthwork (plotted cross-sections at critical points with roadway template and utility lines at known or estimated depths) -catch points -proposed right of way -soil profile and stabilization data -structure general layouts -plan and profile sheets e. The ROW ownership map shall be included in the FIR plan set. f. The preliminary traffic control plan with proposed detours will be included. g. The plans shall be submitted to the C/PM for a preliminary review one week prior to the FIR. 7.03.10 Field Inspection Review(FIR). a. Attend the FIR. b. The FIR meeting minutes shall be prepared by the Consultant, approved by the C/PM,and distributed as directed. c. The FIR original plan sheets shall be revised and corrected in accordance with the FIR meeting comments within ten (10) working days. d. Design decisions concerning questions raised by the FIR will be resolved in cooperation with the C/PM. The Consultant shall document the decision and transmit the documentation to the C/PM for approval. e. A list of all deviations from standard design criteria along with the written WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 19 7.03 Preliminary Design County Consultant Submittal Req'd justification for each one shall be submitted to the C/PM. 7.03.11 Post-FIR revisions. ❑ Q The revisions required by the FIR shall be completed before this phase of work is considered to be complete. NOTICE: FINAL DESIGN SHALL NOT PROCEED UNTIL WRITTEN NOTICE IS PROVIDED BY THE COUNTY. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 20 Submittal 7.04 Final Design County Consultant Req'd 7.04.01 Project Review. ❑ Q Update project schedule and coordinate activities. 7.04.02 Design Coordination. r7( r7( The design for each aspect of the project shall be reviewed during periodic lJ lJ meetings and approved by the C/PM prior to inclusion in the final plans. Specifically,the designs for each of the following must be coordinated:-Roadway geometry-Hydraulics-Roadside-Landscaping-Permanent signing and striping 7.04.03 Utility Coordination. r7( Following the finalization of the roadway horizontal alignment and profile grade L�J and the horizontal location of drainage structures, sewers, and other underground structures,coordinate with the County to finalize utility clearance. 7.04.04 Hydraulic Design. a. Review data and information developed under the preliminary hydraulic ❑ investigation and update in accordance with decisions made at the FIR. b. Update the storm water pollution prevention plan in accordance with ❑ decisions made at the FIR and on additional investigation since the FIR. c. Major structure channel design. The final design shall include: ❑ ❑ -The configuration,size and skew of the channel -Water surface elevations -Elevations,Bowlines and hydraulic information -Channel erosion protection for the structure -Recommend a low girder elevation for the type of structure proposed -Predict scour depth in the channel for the proposed structure, and recommend mitigation measures d. Final hydraulics report will consist of the following: ❑ 1. Revised pages to the preliminary hydraulics report. 2. Bridge hydraulic information on an original plan sheet. e. Coordinate with ROW plans ❑ 7.04.05 Interim Plans. ❑ Q a. Coordinate with the C/PM to initiate the ROW authorization process. Typically, the corrected FIR plans (with final hydraulic design inputs)will be used as the design basis for the ROW authorization plans. b. The final utility plans shall be prepared following the resolution of the FIR comments, the completion of the final hydraulic design, and the completion of the design of the other items comprising the final utility plans. The final utility plans shall include: -Title sheet -Typical section -Plan and Profile sheets WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 21 Submittal 7.04 Final Design County Consultant Req'd -Drainage plans -Cross sections -Any other details which would indicate possible utility conflicts The new or revised utility locations will be added to the plan topography. Conflicts will be resolved and appropriate pay items and specifications added, if required,to adjust utilities. c. Coordinate with the C/PM to develop the railroad encroachment plan(with cross sections)in accordance with railroad requirements. Define construction responsibilities between the railroad and County. Develop cost estimates based upon cost allocation previously determined. Submit plans to the C/PM for authorization and acceptance. 7.04.06 Right of Way. a. Right of Way plans will include: ❑ Q Q -Sheet No. 1 Title Sheet -Sheet No.2 Tabulation of properties. If more than one sheet is required, the following sheets will be numbered 2A,2B etc. -Sheet No.3 Control Survey Diagram. Tabulate the coordinates and physical description of all found monuments and other physical evidence. It will also be depicted in a diagram form. As above, additional sheets after the first will be numbered 3A, 38,etc. -Sheet No.4 Monumentation Sheet. Tabulate coordinates and type of all monuments to be set. Same numbering as above. -Sheet No.5 Tabulation of road approaches. Same numbering as above. -Sheet No. 6 Plan sheet. If more than one sheet is required, the sheets will be number sequentially 6,7,8 etc. -As appropriate: Ownership maps. These sheets will be the numbered following after the"plan sheets". c. Authorization Plan ❑ n( n( 1) Integrate toes of slopes and other design details such as lane lines, IJ LI culverts, road approaches, etc. into Ownership map (base map for ROW Plans). 2) Determine new Right-of-Way requirements, access control, and easements from design plans following the FIR and plot on ownership/base maps. Normal scale, 1"=50'in urban areas, 1"=100' in rural areas. Revise numbering of ownerships to correspond to ROW acquisitions. 3) Calculate areas of parcels,easements,and remainders. 4) Prepare ROW plan sheets. 5) Prepare legal descriptions and exhibit maps of parcels, easements and access control. 6) Prepare tabulation of properties sheet. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 22 7.04 Final Design County Consultant Submittal Req'd 7) Prepare right of way title sheet. 8) Incorporate the Control Survey into the plans. 9) On the Control Survey Sheet, list the right-of-way, easement, control,etc., points to be set and the aliquot corners to be reset. 10) Prepare Right-of-Way Tabulation of Road Approaches, if applicable. Show owner, station, right or left of centerline, width of approach, skew angle, and any remarks as directed 11) Hold ROW Plan Review with Consultant's designers and construction personnel, C/PM and County ROW Consultant to determine if ROW plans are sufficient to proceed with appraisals. 12)Transmit originals of the plan sheets, title sheet, tabulation of properties sheet, and revised ownership (memoranda of ownership and title commitments), calculations and supporting data (i.e. parcel diaries),and final electronic data for all work products. d. Appraisal Staking. ❑ ❑ Stake the proposed ROW line, easements and existing ROW line, if required by the C/PM. Set lathes or wooden stakes at all angle points and on line as necessary to have at least three stakes visible from any point on line. The appraisal stakes shall be set at an accuracy of+/-1.0 foot, unless the point falls near improvements,then+/-0.25 foot is necessary. e. Right of Way Plan Revisions ❑ Q 1) The Consultant shall make revisions to the Right of Way plans as needed through out the appraisal and negotiation process for those changes approved by County. 2) All plan revisions shall be submitted by the Consultant to the C/PM within 5 working days for transmittal to initiate authorization and appraisal. 7.04.07 Materials Engineering. ❑ a.Materials data. Formulate all job-mix formulas. b. Review the Pavement Design Report and the FIR plans to verify the validity of the pavement and stabilization design. c. Prepare the Stabilization plan and submit it to the C/PM for acceptance. 7.04.08 Traffic Engineering. ❑ a. Permanent signing and pavement marking plans. Inventory existing traffic controls. Prepare plan sheet with exiting roadway,edge-of-travel way(ETW) shoulder, signs, structures, and topography. Locate and place on the plans the required traffic controls (pavement markings, signs, etc.). Prepare the Tabulation of Traffic Engineering Items. Prepare traffic specifications and special provisions in accordance with CDOT Guide Sign Policy and the MUTCD. b.Traffic control plan. Prepare the traffic control plan and Tabulation of Traffic Control Devices and estimate quantities. 7.04.09 Roadside Planning. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 23 7.04 Final Design County Consultant Submittal Req'd a. Landscaping. Determine most economic alternative, finalize concept, and ❑ ❑ ❑ complete the plans and special provisions. Verify that an acceptable safe recovery distance exists between traveled way and all trees to be planted. Coordinate ROW requirements and special permits that may be required. Verify availability of plant materials and submit letter to the C/PM certifying that designated plants are available. 7.04.10 Roadway Design ❑ Complete the roadway design based on the inputs from all applicable entities and agencies. The plans shall comply with the design standards referenced in the applicable manuals. 7.04.11 Major Structure Final Design. The Consultant will be responsible for conducting the following activities after the FIR. a. Structural Design and Preparation of Plans and Specifications. ❑ ❑ 1. Perform the structural analysis and design. Document the work with design notes,detail notes and computer output. 2. On a continuing basis, update the general layout, as necessary, on receipt of the final design information from other disciplines,keeping the design team apprised of any changes to the general layout. Obtain the final geology and hydraulics reports early in the design process. 3. Prepare all detail drawings in accordance with the CDOT Bridge Detailing Manual and Bridge Design Manual. Obtain the current standard worksheets and specifications from CDOT's Staff Bridge standards unit. 4. Prepare the special provisions applicable to the project. The Consultant Structural Engineer shall provide the special provisions applicable to the major structures. 5. Compute the quantities and complete the summary of quantities. b. Independent Design, Detail,and Quantity Check ❑ ❑ 1. Perform independent detail check and design check from the plans and special provisions. 2. Revise all plan sheets, special provisions and design notes to correct any deficiencies found in the design and detail checks. 3. Perform an independent check of quantities and revise the summary of quantities as necessary c. FOR. Completed structural plans and special provisions shall be included in ❑ ❑ the FOR plan set. The Consultant Structural Engineer shall review the FOR plans to verify design information received from other disciplines,and attend the FOR to obtain review comments on the structural design. After the FOR, the plans and specifications shall be revised as needed and included in the final plan set. d. Bridge Rating and Field Packages. Prepare the rating packages in ❑ ❑ accordance with the CDOT Bridge Rating Manual. Prepare the structure field packages in accordance with the CDOT Bridge Detailing Manual. 7.04.12 Plan preparation for the Final Office Review(FOR). ❑ a. Coordinate the packaging of the plans. Collect plans from all design elements and collate the plan package. Calculate plan quantities and prepare the tabulations and summary of quantities. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 24 7.04 Final Design County Consultant Submittal Req'd b. New or revised utility locations shall be added to the plan topography. Conflicts shall be resolved and appropriate pay items and specifications added,to adjust utilities. c. The Final Office Review(FOR) plans shall include the following sheets(as appropriate): Title Sheet Standard Plans List Typical sections Irrigation reconstruction General Notes Landscaping Summary of Approximate QuantitiesWetland Mitigation Plans Appropriate quantity tabulations Storm Water Management Plan Special details Signing and striping Structure details Detour plans Bridge hydraulic information sheets Utility locations Roadway Plan&Profile sheets Structure cross-sections Roadway cross-sections with quantities Note: This list may not include all necessary sheets and may include some subjects not applicable. The content of the plans will be approved by the County. d. Special Provisions shall consist of those unique project special provisions which have to be written specifically for items, details and procedures not adequately covered by Standard Specifications and Standard Special Provisions. Also a list of the Standard Special Provisions which are applicable to the project shall be provided in an approved format and submitted with the project plans. e. Preliminary calculations and worksheets will be provided. f. Prepare the FOR estimate. Item numbers, descriptions, units, and quantities shall be listed and submitted to the C/PM. g. Submit the FOR plans and specifications (originals) to the C/PM for a preliminary review prior to the FOR. 7.04.13 Final Office Review(FOR) The Consultant will attend the FOR and prepare the meeting minutes. The minutes shall be approved by the C/PM and distributed as directed. 7.04.14 Construction Plan Package ❑ a. The FOR original plan sheets and the specifications shall be revised in accordance with the FOR meeting comments and submitted to the C/PM within two(2)weeks after the FOR. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 25 7.04 Final Design County Consultant Submittal Req'd b. The plans may require final revision which shall be done by the Consultant. c. The bid plan construction contract package shall consist of the revised final review plans and will completely describe the work required to build the project including project dated special provisions and detailed quantities. d. Consultant submittal. In addition to the plans and specifications the Consultant will provide the following information. 1) Roadway. The Consultant shall submit a hard copy of the following: -Profile -Staking -Earthwork quantities -Mass Diagram -Terrain listing -Roadbed Fisting When required the Consultant shall also submit design data in an electronic format acceptable by County. 2) Major structures a) A letter to the County certifying that the structural plans and specifications have been prepared in accordance with all the appropriate design standards. b) A final complete set of original design notes (including output from computer programs) which reconciles any differences between the original design and independent design check and any design changes resulting from subsequent reviews. c) Independent design check notes. d) The bridge rating package: Rating Summary sheet for girders and deck, rating information and hand calculation sheets, rating computer output,and electronic copy of rating input file. 3) Construction Engineer's action package. The consultant shall submit 2 copies,in 3-ring binders of the following: a) All project calculations or worksheets. b) All final reports and their approvals: Traffic, hydraulics, pavement design, geology foundation report, etc. All reports will have the latest revisions included. c) Copies of variances,design decisions,and variance approvals. d) The FIR and FOR meeting minutes. e) Utility agreements and information regarding the utility location and clearance conditions. f) Environmental clearances,404,wetlands,endangered species,etc. g) Bridge construction packet,which includes bridge grades,geometry,and quantity calculations or worksheets. WCR 13,from WCR 2 to WCRB Engineering Contract-Page 26 7.04 Final Design County Consultant Submittal Req'd h) Any other information unique to this project and deemed important to the effectiveness of construction. e. Record Plan sets. Two half size(11"x17") record plan sets for final design of roadways and structures will be produced which shall bear the seal and signature of the responsible Consultants engineer on each sheet. One set shall be retained by the Consultant for three years. The other set shall be submitted to the County. The original plan drawings shall not bear a seal. 7.05 Services After Design County Consultant Submittal Req'd 7.05.01 Review and Approve Shop Drawings ❑ 1-7f 7.05.02 Construction Services LI The County has estimated that 900 man hours will be required to complete the construction services for the activities defined below. This number shall be used to estimate the lump sum costs for construction services.Only actual man hours used during construction will be paid by the County; therefore, monthly invoices to the C/PM shall be supported by time sheets. a.Attend Pre-Bid Conference and Pre-Construction Meeting. Both meetings ❑ will be held at Weld County Public Works Department b. Provide Field Observation(The field inspector shall be equipped with a cellular phone) 1. Day to Day Construction and Coordination of Activities ❑ The Consultant shall determine when full time inspection is required based upon the work being performed and necessity for inspection of said work. 1. Perform Traffic Control Inspection ❑ The Consultant shall monitor compliance with and take appropriate action to preserve safety on the project for all workers and traveling public in accordance with the Method of Handling Traffic, MUTCD, and the plans and specifications. Document monitoring of compliances in project diary. 2.Major Concrete Pours ❑ All major concrete pours shall be inspected for compliance and acceptance. The Consultant shall coordinate the testing of materials for all major concrete pours with the tester and Contractor. 4. Pile Driving/Caisson Drilling ❑ ❑ 5. Placement of Girders ❑ ❑ 6. Placement of Embankment Material ❑ Placement of embankment material shall be inspected during the placement for compliance with the plans and specifications. The Consultant shall coordinate the testing of embankment materials with the tester and Contractor. 7. Prepare responses to the Contractor's and Supplier's requests for ❑ information,submittals,change orders,claims,and correspondence. c. Technical assistance ❑ d. Submittals WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 27 7.05 Services After Design County Consultant Submittal Req'd 1. Project Diary ❑ Q 2. Documentation/Justification ❑ Maintain current time counts,project files,and contractor submittals. 3. Review Monthly Periodic Pay Requests ❑ Q Q The Consultant shall review and approve the monthly periodic pay requests submitted by the Contractor for completeness and accuracy prior to submittal to the C/PM. 4.Calculations,drawings,and specifications ❑ 7.05.03 Post Construction Services a.As-built plans ❑ Q Q Maintain accurate notes reflecting actual construction details to be used in preparation of the as-built plans. The Consultant shall prepare and submit the As-built plans to the C/PM at the end of the project. 7.05.04 Construction Materials Testing All testing shall be completed in accordance with the methods defined in the CDOT Field Materials Manual,AASHTO Standard Specifications for Transportation Materials and Methods of Sampling, and/or ASTM Standards and Tentatives, in this order. The tester will not be authorized to alter or waive the provisions of the contract or issue instructions contrary to the plans and specifications already in place. Since the County receives a warranty on all construction, testing services performed by the Consultant should comply more with the quality assurance program already in place at the County, rather than with the full quality control plan utilized by CDOT. The tester provided by the Consultant shall meet or exceed all of the qualifications and requirements of Colorado Law and rules concerning such testing set forth by CDOT. a.Concrete Sampling and Testing ❑ ❑ ❑ b. Embankment and Base Course Material Testing ❑ The County has estimated that 50 In-Place Density tests will be required for the roadway embankment and 25 In-Place Density tests will be required for the aggregate base course. These numbers shall be used to estimate the lump sum costs for testing services. Information required to perform such tests shall be provided by the Contractor. Only actual tests performed during construction will be paid by the County; therefore, monthly invoices to the C/PM shall be supported by test results. c.Asphalt Testing ❑ The County has estimated that 50 In-Place Density tests will be required for the H.B.P. These numbers shall be used to estimate the lump sum costs for testing services. Information required to perform such tests will be provided by the Contractor. Only actual tests performed during construction will be paid by the County; therefore, monthly invoices to the C/PM shall be supported by test results. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 28 Section 8 -CONTRACT CONCLUSION 8.01 Supplemental Work It is anticipated that this contract may be supplemented for: Preliminary Design Final Design Construction Services (specific scope of work will be determined. This work may consist of but not limited to, coordinating the schedule, provides field observation, technical assistance, and post design modifications. Construction Engineering Completion of the "As built" plans and/or final ROW plans Supplementing this contract will depend on available funding and County personnel resources. 8.02 Contract Completion This contract will be satisfied upon acceptance of: X FIR Plans X Construction Plan Package X FOR Plans and the completion and acceptance of: X Review of contractor submittals X Construction services Section 9 -SUBMITTALS 9.01 Reports All required reports and studies shall be submitted for review to the C/PM. Final submittals shall incorporate the corrections and/or revisions resulting from the review. 9.02 Data. The following field survey data must be submitted if produced during the work: -Handwritten field notes. -Electronic field data. Prior to collecting data by electronic means, the Consultant shall submit a sample and receive approval to continue the work. A sealed and signed hard copy shall be submitted with all electronic data. Electronic data shall comply with the requirements outlined below. -Photogrammetric Data. Prior to generating mapping data the Consultant shall submit a sample of data and receive approval to continue the work. A sealed and signed hard copy (map sheets when appropriate) shall be submitted with all electronic data. WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 29 9.03 Plans Plan and map sheets shall comply with the following requirements: a. The sheets shall be half size, 11" x 17", including the border, unless otherwise specified. b. Drawings with colors shall be reproducible by all printing media in black and white. c. All drafting and lettering shall be of the proper density and legibility for a 25 percent reduction during reproduction. Also, final drawings for reproduction will have all of the drafting work and image on one side of the sheet. Plan sheets that do not comply with the above criteria will be replaced by the Consultant without additional compensation. The Consultant shall submit an example of an original plan sheet and receive approval from the C/PM prior to drafting the plans. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 30 3. COUNTY'S RESPONSIBILITIES The County shall: 3.1 Provide the Consultant full information as to the County's requirements and existing project related information previously mentioned or described herein. 3.2 The County shall receive and examine documents submitted by the Consultant, interpret and define the County's policies, and render decisions and authorizations in writing promptly to prevent unreasonable delay in the progress of the work. 3.3 Make available any and all information, requested by the Consultant, in existing County files pertinent to the project site. 3.4 Furnish above services at the County's expense, in such a manner that the Consultant may rely upon them in the performance of his services under this Agreement. 3.5 The County will perform the construction bidding process. The Consultant shall furnish all project special provisions and standard specifications necessary for project construction. 3.6 For the required design work and services described herein, the County agrees to pay the Consultant, and the Consultant agrees to accept lump sum compensation as follows: ITEM Proposal Cost Breakdown 7.01 Project Initiation and Continuing Requirements 7.01.01 Initial Project Meeting $400 7.01.02 Review Environmental Mitigation $200 Requirements 7.01.03 Independent Design Review $200 7.01.04 Project Schedule $300 7.01.05 Right of Entry and Permits $2,252 7.01.06 Traffic Control prior to construction $804 7.01.07 Initial Submittal $120 7.01.08 Progress Meetings $4,600 7.01.09 Project Management $9,000 Subtotal -Section 7.01 $17,876 7.02 Project Development 7.02.01 Communication and Consensus Building $3,640 WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 31 7.02.02 Project Review Team $1,520 7.02.04 Conceptual Design $2,500 7.02.05 Gather Data, Analysis, and Mitigation $6,500 Development 7.02.07 Obtain Permits $500 Subtotal -Section 7.02 $14,660 7.03 Preliminary Design 7.03.01 Design Field Survey $14,800 7.03.02 Traffic Engineering $7,500 7.03.03 Materials Engineering $9,500 7.03.04 Hydrology/Hydraulic Engineering $3,500 7.03.05 Utility Coordination $600 7.03.06 Roadway Design and Roadway $13,880 Development 7.03.07 Right of Way $1,500 7.03.08 Structures $6,000 7.03.09 Preparation for the Field Inspection $2,320 Review(FIR) 7.03.10 Field Inspection Review(FIR) $1,152 7.03.11 Post- FIR revisions $2,800 Subtotal -Section 7.03 $63,552 7.04 Final Design 7.04.01 Project Review $200 7.04.02 Design Coordination $504 7.04.03 Utility Coordination $304 7.04.04 Hydraulic Design $1,956 7.04.05 Interim Plans $3,680 7.04.06 Right of Way $1,664 7.04.07 Materials Engineering $1,200 7.04.08 Traffic Engineering $14,500 7.04.10 Roadside Design $8,500 7.04.12 Plan preparation for Final Office Review $1,900 (FOR) 7.04.13 Final Office Review(FOR) $1,152 7.04.14 Construction Plan Package $6,500 Subtotal -Section 7.04 $42,060 7.05 Services After Design 7.05.01 Review and Approve of Shop Drawings $2,750 7.05.02 Construction Services $67,500 WCR 13,from WCR 2 to WCR 8 Engineering Contrail-Page 32 7.05.03 Post Construction Services $5,500 7.05.04 Construction Materials Testing $4,500 Subtotal -Section 7.05 $80,250 Cost Summary Subtotal - $17,876 Section 7.01 Subtotal - $14,660 Section 7.02 Subtotal- $63,552 Section 7.03 Subtotal- $42,060 Section 7.04 Subtotal - $80,250 Section 7.05 GRAND *$218,398 TOTAL * Includes title commitment costs All invoices shall be submitted by the Consultant to the County for payment pursuant to the terms of the contract. Upon approval thereof, the County will pay the appropriate amount of each invoice to the Consultant within 30 days of receipt of each invoice. Progress payments may be claimed on a monthly basis as the percentage of the total lump sum fee that represents the ratio of work performed during the month to the total amount of work. 4. TIME OF PERFORMANCE The Consultant shall complete the design services defined in the Scope of Work, Section 7, within 200 calendar days from the date of Authorization to Proceed as described in Part 1, Section 1.07 of the RFP, exclusive of all days lost for review and approved by the County. All days lost for review shall be documented by the Consultant and submitted to the County for consideration. For each calendar day that the Work is incomplete after the time specified or as adjusted and approved by County in writing, a sum of $200.00 may be deducted from moneys due to the Consultant as liquidated damages. This sum is fixed and agreed upon between the County and Consultant because the actual loss to the County and to the public caused by delay in completion will be impractical and extremely difficult to ascertain and determine. 5. TERMINATION OF AGREEMENT The Agreement may be terminated for cause by the County or Consultant upon fifteen (15) days written notice. In the event of termination, Consultant shall be paid for services performed to termination date as mutually determined by County and Consultant. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 33 6. CHANGE OR EXTRA WORK In the event the County shall require changes in the Scope of Work to be performed, which said changes cause an increase or decrease in the Consultants total lump sum fee, the Consultant shall be compensated as mutually agreed upon by and among the County and Consultant. Any claim by the Consultant for compensation must be made in writing prior to performance of any changed work or services. 7. INSURANCE The Consultant shall carry the following minimum amounts of insurance: (1) Workmen's Compensation in statutory limits (2) Comprehensive General and Automobile Liability Policy for amounts not less than: Bodily Injury Each person $150,000 Each Accident $600,000 Property Damage Each Accident $150,000 Aggregate $600,000 (3) Architect's and/or Engineers' Professional Liability Policy for amounts not less than $600,000 aggregate Said insurance shall be maintained in full force and effect during the term of this contract and for two (2) calendar years thereafter. Certificates showing the engineering firm is carrying the above-described insurance shall be furnished to the County prior to commencement of the work. Said insurance in paragraph (1) and (2) shall include as an additional named insured, Weld County, Colorado, by and through the Board of Weld County Commissioners, including its agents and employees. 8. VENUE This transaction shall be governed by the laws of the State of Colorado. 9. NON-DISCRIMINATION The Consultant shall not commit any of the following employment practices and agrees to prohibit the following practices in any subcontracts. WCR 13,from WCR 2 to WCR 8 Engineering Contract-Page 34 To discharge from employment or refuse to hire any individual because of their race, color, religion, sex, national origin, disability, age, or marital status. To discriminate against any individual in terms, conditions, privileges or employment because of their race, color, religion, sex, national origin, disability, age, or marital status. 10. BENEFITS The Consultant, as an independent contractor, its agents or employees, will receive no benefits directly or indirectly that accrue to County employees, in the performance of this contract. 11. OWNERSHIP OF ENGINEERING DOCUMENTS All plans, specifications, estimates, and miscellaneous items purported to contribute to the completeness of the work shall be delivered to and become the property of the County. The Consultant will retain reproducible copies of plans. Basic notes, drawings, charges, computations and other data prepared hereunder hall be made available to the County upon request. All documents, including drawings and specifications prepared by the Consultant pursuant to the Agreement, are instruments of services in respect to the project. They are not intended or represented to be suitable for reuse by County or others on extensions of the project or on any other project. Any reuse without written verification or adaptation by Consultant for the specific purpose intended will be at County's sole risk without liability or legal exposure to Consultant and the County shall indemnify and hold harmless the Consultant from all claims, damages, losses and expenses including attorney's fees arising out of, or resulting there from. Any such verification or adaptation will entitle Consultant to further compensation at rates to be agreed upon by County and Consultant. WCR 13,from WCR 2 to WCR S Engineering Contract-Page 35 IN WITNESS WHEREOF, the parties hereto have executed, or caused to be executed by their duly authorized officials, this Agreement, each of which shall be deemed an original on the date first written above. COUNTY OF WELD, STATE OF CONSULTANT COLORADO, by and through the Board of County Commissioners of Weld County II By: (Firm Name): C1 )13.3°C c David E. Long, Ch r nsio7)03 Name: -7;73c J 4 Date 17/16 7 ,9-e1D Title: G n (Seal) ATTEST: ..� , r � � "� _i �� 3 C�5- �� 7 gas 3 Wa.��wo 3 � Address: By: _l _ ��.. 1 C +- i'�, , : : 90'07 Clerk totT .:". 1 � I? Cr L tti i � Itt •O n' (SEAL) tt :af;J•' t ATTEST: nn , ,1,�► �.�, / Name: 1. -L InJG3 'k Title: c 0 WCR 13,from WCR 2 to WCR8 Engineering Contract-Page 36 ta MEMORANDUM Will TO: Clerk to the Board DATE : April 28, 2003 • COLORADO FROM: Drew Scheltinga, Engineering Division Manager SUBJECT: Agenda Item Please submit the enclosed item for the Chair's signature: Contract for Engineering Services for the Design of WCR 13 from WCR 2 to WCR 8 The appropriate documentation is enclosed Enclosures pc: Wayne Howard, Engineering \F RA NC I E\AG EN DA-4.DOC a MUj- ti- 7-:)c.,o3 Hello