HomeMy WebLinkAbout20031324.tiff AGREEMENT
WCR 15, Fly Ash Treatment
THIS AGREEMENT, made this 21st day of May, 2003, by and between Weld County, Colorado, hereinafter
called"Owner"and
Son-Haul, Inc., P.O. Box 1449, Ft. Morgan, CO 80701 doing business as (an individual, ) or (a partnership,)
or (a corporation)hereinafter called"Contractor".
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned:
1. The Contractor will commence and complete the following: The soil stabilization using fly ash
treatment on WCR 15,just north of Windsor, Colorado, as described in the Invitation for Bids,
Bid No.B0300107.
2. The Contractor will furnish all of the material, supplies, tools, equipment, labor and other services
necessary for the construction and completion of the Project described herein.
3. The Contractor will commence the work required by the Contract Documents within ten (10)
calendar days after the date of the Notice to Proceed and will complete the Project within 7
calendar days unless the period for completion is extended otherwise by the Contract Documents.
4. The Contractor agrees to perform all of the Work described in the Contract Documents and
comply with the terms therein for the sum of $45,741.41,or as shown in the Bid Schedule.
5. The term"Contract Documents"means and includes the following:
(A) Invitation for Bids
(B) Instructions to Bidders
(C) Bid Proposal
(D) Bid Bond
(E) Agreement
(F) General Conditions
(G) Project Special Conditions
(H) Labor and Materials Payment Bond
(I) Performance Bond
(J) Notice of Award
(K) Notice to Proceed
(L) Change Order
(M) Certificate of Substantial Completion
(N) Lien Waiver
(O) Notice of Acceptance
(P) Specifications prepared or issued by the Weld County Public Works
Department.
(Q) Colorado Department of Transportation "Standard Specifications for Road and
Bridge Construction"
(R) Colorado Department of Transportation Standard Plans"M&S Standards"
(S) Addenda:
No. , dated ,20
No. , dated ,20
6. The Owner will pay to the Contractor in the manner and at such times as set forth in the General
Conditions such amounts as required by the Contract Documents.
�� �,, ,, M�hAccttiiv,,e-Projects\WCRl5-flyashAGREEMENT.doc 2003-1324 EG0047
6 7 vc,t �+f e'V`ob
5 1-Qat):3 Ca : Pe3
AGREEMENT
WCR 15,Fly Ash Treatment
7. This Agreement shall be binding upon all parties hereto and their respective heirs, executors, administrators,
successors, and assigns.
8. Contract Appropriations: The Owner hereby states and affirms that the amount of money appropriated for this
Contract is equal to or in excess of the Contract amount. No change order to this Contract requiring additional
compensable work to be performed, which work causes the aggregate amount payable under the Contract to
exceed the amount appropriated for the original Contract shall be issued by the Owner unless the Owner assures
the Contractor,in writing,that lawful appropriations to cover the costs of the additional work has been made or
unless such work is covered under a remedy-granting provision contained in the Contract.
IN WITNESS WHEREOF,the parties hereto have executed,or caused to be executed by their duly authorized officials,this
Agreement in three(3)copies each of which shall be deemed an original on the date first above written.
ORDERED BY: ACCEPTED BY:
THE BOARD OF WELD COUNTY COMMISSIONERS CONTRACTOR 7;
lit L,
BY &r BY — G e1_,--•-C �hc
NAME David E. Lon NAME Pc, ct ^< - F F v
(Please Type)
TITLE Chair TITLE N d
Date C—A/— 3 ADDRESS
c9c / L cal L_3
�♦ �r (
f . I /ice` s n�t ��y « �
lot
� �� � � �
,A"s .
ta,t1k tie::
_S-. (SEAL)
N�► l'� . ' .�� ��/
/kiletA a'i( ATTE(T:
Weld County Clerk to the Board \ V`��
BY / `l/L�" .f/ sc BY 'frla ;e.,\
Deputy Clerk 4o the Board ---, (Please Type)
Title 0 2 CQ AAMILV ft)/
a
MEMORANDUM
CTO: Clerk to the Board DATE: May 15, 2003
•
COLORADO FROM: Frank B. Hempen, Jr., P.E.
Director of Public Works/County Engineer
SUBJECT: Item for Chair's Signature
Please submit the enclosed item for the Chair's signature.
Two original, duplicate Agreements for Fly Ash Treatment on WCR 15 with Son-H— '-la i
Please send immediately after executed one original Agreement back to Public Works
for distribution.
The appropriate documentation is enclosed
Enclosures
pc: Wayne Howard, Project Manager
M:\FRANCIEASIGNATURE.WPD
). ()I- .,k01
Hello