HomeMy WebLinkAbout20042888.tiff CHANGE ORDER NO. 1
Potholing Services for WCR 47, Between WCR 50 and 54
Date:
Project: Potholing Services for WCR 47,Between WCR 50 and 54 as described in the
Request for Bids,Dated: June 22,2004
Owner: Weld County, Colorado
Contractor: Colorado Boring Company
The following change is hereby made to the Contract Documents:
26 Additional Potholes @$125 per pothole.
CHANGE TO CONTRACT PRICE:
Original Contract Price: $ 4,250.00
Current Contract Price adjusted by previous Change Order: $ 4,250.00
The Contract Price due to this Change Order will be increased by: $ 3,250.00
The new Contract Price,including this Change Order,will be$ 7,500.00
CHANGE TO CONTRACT TIME:
The Contract Time will be increased by 0 calendar days.
The date for completion of all Work will be August 20,2004 .
RECOMMENDED:
Owner Representative:
Date:
Engineer: C 1 ir— Date: 9/7.4/0`f
APPROVALS:
/
Contractor: _ — Date: 1/4//:"b�
Owner: Date: 81/04
Owner: N Date:
SEP 2 9 2004
Robert D.Masden,Chair
eld County Cle,k to the Board
(SEAL) F
186! r ,jg"A
O • Deputy Clerk to
j Al fES TO 9' P.0 GruP1TY
M:\-Active Projects WCR 47,WCR 5 A 54\Construcfion\Contracts\POTHOLING CHANGE ORDER doc
/O—a(o-01/ cCI . PA))/t, Q5e.. COQ `C6
•
. a
i MEMORANDUM
CTO: Clerk to the Board DATE: September 23, 2004
•
COLORADO FROM: Frank B. Hempen, Jr., P.E.
Director of Public Works/County Engineer
SUBJECT: Agenda Item
Change Order No. 1 for WCR 47 Potholing Contract with Colorado Boring Company.
Enclosures
pc: Dean Dreher
Cameron Parrott
M:\Franc ie\Agend-I.doc
h.5
I � 4
LJ1
2004-2888
MEMORANDUM
Date: September 23, 2004
1"1! To: Frank B. Hempen, Jr., P.E., Director of Public Works/County Engineer
VIDe From: Cameron Parrott, P.E., Engineer II (
COLORADO RE: Change Order No. 1 for WCR 47 Potholing Contract
The potholing/utility-locating has been completed for the contract for potholing services on WCR 47,
between WCR 50 & 54. The contract was set up based upon a cost per pothole. There were 34 potholes
initially estimated. The cost from Colorado Boring Company was $125/pothole for a total contract
amount of$4,250.00. After utility locates were performed, it was determined that more potholes would
be needed to avoid conflicts with utilities during road construction. Colorado Boring Company finished
60 potholes total. This is an increase of 26 potholes at $125/pothole for a total change order increase of
$3,250.00. The final contract amount with the change order would be $7,500.00.