HomeMy WebLinkAbout20042735.tiff CHANGE ORDER NO.
2004 Slurry Seal Projects
Date: August 26, 2004
Project: 2004 Slurry Seal Projects described in the Invitation for Bids,Bid No.B0400034
Owner: Weld County,Colorado
Contractor: Quality Resurfacing CO
The following change is hereby made to the Contract Documents:
Additional mobilization cost to complete missed section.
CHANGE TO CONTRACT PRICE: •
Original Contract Price: $ $808,116.42
Current Contract Price adjusted by previous Change Order: $ $808,116.42
The Contract Price due to this Change Order will be increased by: $ $2,656.00
The new Contract Price,including this Change Order,will be$ $810,772.42
CHANGE TO CONTRACT TIME:
The Contract Time will be increased by 1 calendar days.
The date for completion of all Work will be Completed
RECOMMENDED:
i
Owner Representative: 'om. - /isujiil Date: £ 26 "- ) �/
Engineer: //Tn Date:
APPROVALS:
Contractor. � �w i� Date: S 12:1 ( 4
�(/j p
Owner: / /i Date:04
Chairman, Bo of u y C mi -'•`�
ATTEST: ;is6i °, '-
'�WELD C• NTY CLERK-1O T�' B�� R� �;,,y.
S.
BY:
DEPUTY CLE . O HE BOARD � UN 1>'�
Page 29 €(rPOS l
2004-2735
0 -o8-oy (10 P(,(w/ ( f1z, K ,7
MEMORANDUM
TO: Clerk to the Board DATE: August 30, 2004
COLORADO FROM: Frank B. Hempen, Jr.,
Director of Public Works/County Engineer
SUBJECT: Agenda Item
Change Order No. 1 for the 2004 Slurry Seal Project.
The appropriate documentation is attached.
Enclosures
pc: Keith Meyer, P.E.
Dean Dreher
NI:AFrancfeVAgenda-2.doc
KistLe".••
MEMORANDUM
CTO: Keith Meyer, P.E., DATE : 8/30/2004
• Engineering Division Manager
COLORADO Clerk to the Board
FROM: Dean Dreher, Civil Tech III
SUBJECT: Chair's Signature Item
Please submit the enclosed item on the signature agenda.
Change Order No. 1 for Public Works Project 2004 Slurry Seal.
Change Order No. 1 is to revise the contract between Weld County and Quality Resurfacing Co. for
the mobilization and seal coat work on 4000 feet of Weld County road 52. The Change Order
includes an increase to the project cost for completion of work requested by the Public Works
Department. Additional contract time to perfoun the extra work will be included in the Change
Order.
The appropriate documentation is enclosed.
Enclosures
pc: Dean Dreher, Civil Tech III
M-A—Maintenace Contracts,Slurry Seal\2004VChange order AGENDADOC