HomeMy WebLinkAbout20040272 CHANGE ORDER NO. 1 WCR 13,from WCR 2 to WCR 8 Date: Project: Road improvements of Weld County Road 13,from WCR 2 to WCR 8. The general planned improvement is to design and construct a two lane roadway that consists of 12'paved lanes, 10' shoulders(8'paved—2'gravel)for the three mile section of gravel roadway with consideration for the ultimate section. Owner: Weld County,Colorado Consultant: Jehn Engineering,Inc.,4112 Kodiak Court,Frederick,CO 80504 The following change is hereby made to the Contract Documents: Include change of the Scope of Work to include pothole testing for utilities and prepare and conduct a public open house meeting. (See attached support documentation) Add additional calendar days due to rime lost for County review and public review and input of preliminary plans. (See attached support documentation) CHANGE TO CONTRACT PRICE: Original Contract Price: $ 218,398.00 Current Contract Price adjusted by previous Change Order: $ 218,398.00 The Contract Price due to this Change Order will be increased by: $ 8,616.00 The new Contract Price,including this Change Order,will be$ 227,014.00 CHANGE TO CONTRACT TIME: The Contract time will be increased by 111 calendar days. The date for completion of all Design Work will be March 21,2004 . RECOMMENDED: Ike Owner Representative: Date: 1/19/2004 Robert D.Masden,Chair ,/ Engineer: =1,,,d Date: /AO 4 APPROVALS: Consultant: elm Engineering,Inc. � By: C .�� Date: / / 3 — '7 Title: /KC- JeHN h.GIMFER '!CJ_ January 6, 2004 Wayne Howard, P.E. Weld County P.O. Box 758 1111 H Street Greeley, Colorado 80632 RE: WCR 13 Change Order#1, Time lost to review, and revised schedule Jehn Engineering Job# 1528-203-070 Dear Wayne: This letter is address the change of scope for including a public meeting scheduled for December 11, 2003 as part of our contract. Van Thuyne-Downs, Inc. completed potholing activities and the invoice is included in Change Order#1. I also am submitting documentation for days lost to review, and estimated time to complete the design portion of the work. • Change Order#1 Jehn Engineering provided materials and personnel necessary to hold a public meeting on December 11, 2003 at the City of Dacono. Jehn Engineering prepared exhibits suitable for public discussion, which included the aerial view with the proposed 140' ROW, the interim section, existing and proposed utilities, and existing and proposed profiles. 2 sets of 11" X 17" construction plans were available for reference, specifically the ownership maps and cross sections. Additionally, Jehn Engineering prepared a "Fact Sheet" at the request of Keith Meyer using an example he had forwarded. The following is a breakdown of Change Order# 1. Open House Senior Project Manager 8 hours @ $100.00/hour= $800.00 Senior Technician 12 hours @ $68.00/hour= $816.00 Senior Technician (Fact Sheet) 10 hours @ $68.00/hour= $680.00 Clerical 6 hours @ $50.00/hour = $300.00 Reimbursables Exhibits $500.00 Total Open House $3,096.00 Potholing Invoice 949 from Van Thuyne-Downs $4,800.00 15% Subconsultant Fee $720.00 Total Potholing " $5,520.00 Total Change Order#1 $8,616.00 a�tl4 n Ld ' ';�p� F JeHN ®. Eti5INEERINGJE This change order shall conform to the terms and conditions of the agreed upon Contract. • Jehn Engineering is requesting 69 days lost to review to be credited to the schedule. Jehn Engineering had submitted the alignment shift exhibits and Bull Canal hydraulics evaluation on 10/07/03 and we received feedback at our scheduling meeting on October 14, 2003. Jehn Engineering submitted the F.I.R. plans on October 21, 2003 and we received comments at the F.I.R. meeting on October 28, 2003. The time lost for determining the interim section and potential changes in alignment began on November 12, 2003 with the recommendation of an interim section and should continue until January 13, 2004. Please let me know if you do not agree with the requested days lost. • Jehn Engineering estimates the time to complete the design portion of the project to be 42 days once we receive feedback from the January 13, 2004 follow-up meeting with the property owners. We estimate 14 days to revise the F.I.R. plans and 28 days to complete the F.O.R. plans, exclusive of additional time lost for review. Please contact me if you have any questions or comments. If the change order is acceptable, please sign and return one copy. Thank you, Accept Change Order#1 Chuck Weiss, P. E. Senior Project Manager lc; f A nR Title voya9 Date y'HG a ilk • ;J JUIG' • , I \\C at, z'ig MEMORANDUM 119 € TO: Esther Geisick DATE : 1/14/2004 Clerk to the Board COLORADO FROM: Keith Meyer, P.E., Engineering Division Managergl SUBJECT: Chair's Signature Item Please submit the enclosed item on the signature agenda. Change Order No. 1 for Public Works Project WCR 13, from WCR 2 to WCR.8. Change Order No. 1 is to revise the contract between Weld County and Jehn Engineering,Inc. for the design and construction inspection of WCR 13, from WCR 2 to WCR 8. The Change Order includes an increase to the project cost for additional design work requested by the Public Works Department. Additional contract time to perform the extra work and time lost for plan review by the County will be included in the Change Order. The appropriate documentation is enclosed. Enclosures pc: Wayne Howard, P.E., Project Manager MA—Active Projects Strategic Corridor WCR 13,from WCR 2 to 8VDesignAContractsAChange order AGENDA.DOC treCt57) 2004-0272 Hello