HomeMy WebLinkAbout20042863.tiff CHANGE ORDER NO. 3
Weld County Bridge 27/58A Over Sheep Draw
Date:
Project: Weld County Bridge WEL027.0-058.0A over Sheep Draw. The project is located on Two Rivers Parkway or
83rd Ave.just south of West 10th St., Greeley, CO and is funded with a Federal Bridge Replacement Grant. Sear-Brown
was selected as the consultant for the project to provide engineering design and construction management services.
Owner: Weld County,Colorado
Consultant: Stantec Inc.,(Sear-Brown)209 S.Meldrum,CO 80521
The following change is hereby made to the Contract Documents:
o The Consultant's company name "Sear-Brown" shall be changed to "Stantec Inc.". The company Sear-
Brown was purchased by Stantec Inc. during the course of the contract. (See attached Exhibit A)
o Additional services to the original Scope of Work were required. Additional services included: (See attached
Exhibit B)
• Resetting section corner in State Hwy 34
• Supplementary surveying for landowner's utilities and driveway
• Design landowner's leach field impacted by the project
• Design landowner's private waterline impacted by the project
• Change hourly rate of pay for Stantec's construction staff
CHANGE TO CONTRACT PRICE:
Original Contract Price: $ 169,718.00
Current Contract Price adjusted by previous Change Order: $ 177,174.67
The Contract Price due to this Change Order will be increased by: $ 9,032.00
The new Contract Price,including this Change Order,will be$ 186,206.67
CHANGE TO CONTRACT TIME:
The Contract time will be increased by 0 calendar days.
RECOMMENDED:
\�� S
Owner Representative: - Date: EP 2 7 2004
Ro ert D.Masden,Chair p
Engineer: /4 Date: 9/ac/�7
APPROVALS
Consultant: Sttaanntec Inc.
By: ' %
" --Z(//_)�y/2 Date: (f 5- /o 91
Title: ---R,_„ .-,,, .- /L'�n r c.csLe c .4C50('/CIA-C_
2004-2863
�
ec : ✓U%. ?CC_,,f.:Ty4.,1f-, c.
StaMec Consulting Inc. NA.
xA I S 1 1
209 South Meldrum Street
Fort Collins CO 80521-2603
Tel:(970)482-5922 Fax:(970)482-6368
stantec.com
. NMILOAr4
.,g
\s >
Stantec �\
Wayne Howard June 25, 2004
Attention: Accounts Payable
1111 H. Street, PO Box 758
Greeley, CO 80632-0758
To Whom It May Concern:
Your Reference: Weld County Sheep Draw & WCR27 Bridge
Please be informed that on April 2, 2004, Stantec Technology International Inc. acquired The Sear-Brown
Group, Inc. ("Sear-Brown"), with the result that Sear-Brown is a wholly owned subsidiary of Stantec
Technology International Inc. Stantec Technology International Inc. reassigned Sear-Brown's Colorado',,
operations to Stantec Consulting, Inc., also a wholly owned subsidiary of Stantec Technology International,
Inc. Stantec Consulting Inc. is the western states operating entity for the Stantec group of companies. !,
Stantec will maintain Sear-Brown's present geographic locations with no interruption in operations or client
services, and all future projects and operations will be under the Stantec name. Stantec and its affiliates offer '.
knowledge-based solutions for infrastructure and facilities projects through professional services in
management, planning, design, and implementation, provided by more than 4,000 employees in over 52
locations, principally in North America.
Above all else, Stantec's primary focus is client satisfaction. Accordingly, please be assured that the continuity
of your current project will be unaffected by this new arrangement. The personnel currently working on your
project will not change, and except for the assignment requested herein, no other aspect will be affected.
In this regard, we request your approval to assign the above-noted contract in the name of Sear-Brown Group,
Inc to Stantec Consulting Inc. Kindly indicate your consent to the request for assignment by returning a
duplicate copy of this letter, executed on behalf of Wayne Howard.
Sincerely,
Stantec Consulting, Inc.
Bret A. Cummock, P.E.
Senior Associate
1
The undersigned hereby consents to the assignment of the Contract noted above to Stantec Consulting, Inc.
effective April 2, 2004.
City 60.44
L1
N
TA) ibli B
Stantec Inc.
10160-112 Street
Edmonton AB T5K 2L6
Tel:(780)917-7000 Fax:(780)917-7330 D E c js I n vq
stantec.com l�J IS
s. . AUG 2 7 •
WELD COUNTY PUBLIC WORKS DEPT
Stantec
August 23, 2004
File: 114005, Contract
Wayne Howard
Weld County
Public Works Department
1111 H Street
Greeley, CO 80632-0758
3
Reference: RE: Bridge Project WEL027.0-058.0A, Change Order #x Request
Dear Mr. Howard:
Thank you for allowing us to submit the following fee as additional services the Sheep Draw
Bridge Project (Bridge 27/58A). The fees below cover additional services rendered during
original design, and increases related to an updated Specific Rate of Pay table to be utilized for
final design and construction administration.
Additional Services during original Desikn
• Addition survey that was needed at the Morgan's property to perform a design of his
septic tank and a driveway entering the rear of his house $1,598
• Design adjustments to the Morgan leach field were required in order to remove a leach
line that was within the proposed right-of-way and replace a leach line outside of the
proposed right-of-way. Charge includes work performed by Stantec, Terracon and John
Brunner & Company. $3,545
• Additional design effort was required to assemble a set of plans for the construction of a
waterline service to the Morgan property. This was needed in order to allow Mr. Morgan
to install a new waterline prior to the start of the bridge project. $980
fr t„b 1- B
Stantec
August 23,2004
Page 2 of 2
Reference: Budget Update for Bridge Project WEL027.0-058.0A
• Weld County requested that Stantec set a survey corner within the intersection of US-34
and WCR 27. $1,525
Additional Fee for Final Design and Construction Administration
• Weld County has agreed to compensate Stantec for final design and construction
administration based on an updated rate of pay. This is due to normal salary increases
since the signing of the original contract in August 2001 $903
• Additional mileage will be required in order to allow Stantec to visit the construction site
during construction. This is due to the fact that Bridge 27/58A and 13/27A were not
constructed simutaniously $481
3
Total requested for Change Order # $9,032
Contract Summary:
Original Budget $169,718
Additional Services outside of the scope
Change Order#1 (Preble's Mouse Investigation) 7,457
Change Order#2 (Cknnjc sVafF e4' 9032,O
C�ryrsc OrcLcr 43 '1,0 .2
Total Budget $ 186,207
Sincerely,
STANTEC INC.
l�ff mple le
Tel: 970-482-5922
Fax: 970 482 6368
Attachments: SRP, SRP Comparison, &Additional Cost spreadsheets
i„ ; B
ADDITIONAL COSTS
23-Aug-04
Sheep Draw Additional Services
Labor Category Pro)Mgr Pr0j Eng, SR Des,Eng, Survey Crew CADD:I Clencal:Expenses TASK TOTAL.
Lahti Sur
Rate/hour $90 $55 $70 $75 $50 $40
SURVEY
1.Morgan Property 1 12 3 8.5 $ 1,598
2.Set Corner in US-34 2 4.5 8 $ 430 $ 1,525
DESIGN
4.Leach Field Design 16 7 $ 1,825
5.Leach Field Expenses
Terracon($550+$670+$200) $ 1,420 $ 1,420
Brunner $ 300 $ 300
6.Waterline Design 4 4 8 $ 980
Final Design Construction
7.Increase in specific rate of pay $ 903 $ 903
8.Additional Milage $ 481 $ 481
Total Additional Design $ 9,032
Item#1 through#6 were approved through a Weld County letter dated October 15,2003
Item#7 is addition cost based on Stantec's updated Rate of Pay
Item#8 are additional direct miles required for one weekly visit for a duration of 6 months
1 Add Ser SD-8-23-04 xIs
1, i,,s + 6
STANTEC'S SPECIFIC RATE OF PAY TABLE-COMPARISON
PROJECT NUMBER: Bridge 27/58A
LOCATION: Sheep Draw
FIRM NAME: Stantec
NAME OF PREPARER: Jeff Temple PHONE No: (970)482-5922
PREPARATION DATE: 23-Aug-04
1.SPECIFIC LABOR RATES SHADED CELLS REPRESENT UPDATED;INFORMATIOM -I1
ORIGINAL NEW. ORIGINAL NEW ORIGINAL NEW
EMPLOYEE EMPLOYEE DIRECT SALARY DIRECT SALARY INDIRECT INDIRECT ORIGINAL #dk1�t SPECIFIC RATE SPEEIFIC RATE
NAME CLASSIFICATION COST/HOUR ;OST/MQUR COST(141%) COST(1.6034) FEE(12%) HOUR Oti
Gary Oberling Engineering Manager $40.70 $42.84 " $57.39 $66.54' $11.77 5
Jeff Temple Senior Engineer I $33.20 $36.08 $46.81 357,73 $9.60 _ 31!3'3 ... , 5109.86 $124:75
(Joe Delich) Engineer $18.20 $29.00 $25.66 ',Moo $5.26 $89.61 405,
Cortni Ward II :• ''°. llICi is,r tl $49.13 ;166:96
Keith Smith Construction Administrator $20.10 $22_B2 $28.34 ;•336.51 $5.81 ._l!`,.II3 :+:,.°I;. $54.25 16645
2.OTHER DIRECT COST RATES
Vehicle Expense $0.37 per mile
3 ESTIMATED HOURS FOR DESIGN COMPLETION AND CONSTRUCTION ADMINISTRATION
ORIGINAL NEW DIFFERENCE ADDITIONAL
EMPLOYEE ESTIMATED HOURS SPECIFIC RATE SPECIFIC RATE SPECIFIC RATE COST WITH
' NAME ON 13/26A $/HOUR S/HOUR ti/HOUR UPDATED SPR
Gary Oberling 60 $40.70 $42.84 $2.14 $128.40
Jeff Temple 140 $33.20 $36.08 $2.88 $403.20
Cortni Ward(Joe Delich) 40 $18.20 $23.00 $4.80 $192.00
Keith Smith 66 $20.10 $22.82 $2.72 $179.52
Total additional Cost due to updated SRP Table $903.12
3.ADDITIONAL EXPENSES DUE TO SEPARATE CONSTRUCTION PROJECT
Mileage
Jeff 26trips X 50 Miles/Trip x$0.37= $481.00
Total additional expenses $481.00
APPENDIX"B"
STANTEC'S SPECIFIC RATE OF PAY TABLE
PROJECT NUMBER: 27/58A(C030-021)
LOCATION : Sheep Draw Bridge
FIRM NAME: Stantec
NAME OF PREPARER: Jeff Temple PHONE No: (970)482-5922
SCOPE OF WORK DATE: 16-Jul-04
1. SPECIFIC LABOR RATES
EMPLOYEE EMPLOYEE DIRECT SALARY INDIRECT SPECIFIC RATE
NAME CLASSIFICATION COST/HOUR COST(160%) FEE(12%) $/HOUR
Dale Stein Senior Engineer I $39.04 $62.46 $12.18 $113.68
Gary Oberling Engineering Manager $42.84 $68.54 $13.37 $124.75
Jeff Temple Senior Engineer I $36.08 $57.73 $11.26 $105.06
Cortni Ward Engineer II $23.00 $36.80 $7.18 $66.98
Keith Smith Construction Administrator $22.82 $36.51 $7.12 $66.45
MEMORANDUM
WIWD
TO: Clerk to the Board
DC. DATE: September 20, 2004
FROM Frank B. Hempen, Jr., P.E.
COLORADO Diector of Public Works/County Engineer
SUBJECT: Item for Agenda
Please submit the following for the Board's next agenda:
Change Order No. 3 for Weld County Bridge 27/58A over Sheep Draw.
Weld County has contracted with Stantec for design and construction inspection services
for the bridge replacement project for the amount of $169,718.00. Change Order No. 1
increased the contract amount by $7,456.67. The change order included additional
environmental clearance issues not anticipated in the original scope of work. Change
Order No. 2 was approved and allowed Stantec to make changes in staff working on the
project. This change order did not change the contract amount.
Attached is Change Order No. 3 and support documentation. This change order will
officially change the name on the original contract from Sear-Brown to Stantec, Inc. As
stated in Exhibit A, Sear-Brown has changed their name to Stantec during the course of
this contract. Also, this change order will increase the contract amount by $9,032.00 for
additional services that were outside the original scope of work. The additional services
include the following:
• Resetting section corner in State Hwy 34
• Supplementary surveying for landowner's utilities and driveway
• Design landowner's leach field impacted by the project
• Design landowner's private waterline impacted by the project
• Change hourly rate of pay for Stantec's construction staff
The new contract amount will be$186,206.67. The project is funded with a Federal Bridge
Replacement Grant and the current project cost and estimates, including this change order,
are within the project budget. The project is scheduled to be advertised for construction
early October, 2004 with completion in spring of 2005. -