HomeMy WebLinkAbout20051023.tiff CHANGE ORDER NO. 1
CONTRACT FOR ENGINEERING SERVICES FOR WELD COUNTY ROAD 64 34,23 AND 66
OWENS ILLINOIS PLANT OFFSITE ROAD IMPROVEMENTS
Date: March 3,2005
Project: WCR 64 34,23 and 66-Owens-Illinois plant offsite roadway improvements
Owner: Weld County,Colorado
Contractor: Ketterling,Butherus&Norton Engineers,LLC.
The following change is hereby made to the Contract Documents:
Increase the overall contract price by $21,647.30 to account for additional services
performed beyond the original contract scope of work including; additional right-of-way
legal descriptions and exhibits, utility potholing services, printing of plans and special
provisions, hiring a construction testing company, compensation for extensive
irrigation/drainage design, and additional man-hours for plan interpretation throughout
construction of the project
CHANGE TO CONTRACT PRICE:
Original Contract Price: $ 23,450.00
Current Contract Price adjusted by previous Change Order: $ 23,450.00
The Contract Price due to this Change Order will be increased by: $ 21,647.30
The new Contract Price,including this Change Order,will be$ 45,097.30
CHANGE TO CONTRACT TIME:
The Contract Time will be increased by 232 calendar days.
The date for completion of all Work will be July 1,2005 .
RECOMMENDED:
Owner Representative: Date:
Project Manager: giant Date: 3/3/6 S
APPROVALS: n
C Date: /3/0
C13
Owner: _ Date: qs/a.
O '//�/_____________________________________________Date:
/l^/,, 3/23/2005
William H. :e,Chair / /��(/'��`�""�/(
Attest:
Weldcounty Clerk to the Board
(SP[L) 77
By: z4;1(/t;�; � /1C CCi l
P" V eputy Clerk to the Board
MA—Active Projects\Misc Projects\WCR 64 3-4&WCR 23\Design\Contracts\CHANGE ORDER#l.doc 2005-1023
rtJ
i
1
f PUBLIC WORKS DEPARTMENT
1111 H STREET P.O. BOX 758
GREELEY, COLORADO 80632
WEBSITE: WWW.CO.WELD.CO.US
C. PHONE (970) 356-4000, EXT. 3750
FAX: (970) 304-6497
COLORADO
March 3, 2005
Michael C.Ketterling,PE
Ketterling,Butherus&Norton Engineers LLC
820 8th Street
Greeley, Colorado 80631
RE: Owens-Illinois Roadway Improvements,Change Order No. 1
Dear Mr. Ketterling:
We have reviewed your request for additional funds for the above stated project. We are recommending a change order
to be done based on the following items:
County Requested Extras:
Item Original Contract Amount Project Cost Increase
1.ROW/easements(King) $1,600.00 $2,476.00
a.KBN coord.&exh.for Leon - $734.00
2.Potholes—Cob.Boring(6) - $660.00
3.Revise lane widths&striping - $892.00
4.Type County's specs into computer - $648.00
5.Print plans&specs(40 sets) - $1,458.00
6.Const. observation&testing(EEC) *Increase from$5,.000.00* $10,000.00
TOTAL REQUESTED EXTRAS $16,868.00
Additional hours needed for Drainage/Irrigation Design @ %s proposed$9,558.60 = $4,779.30
Additional hours for Const.Management/Interpret.throughout construction = $2,400.00
Reduction of original contract to remove geotechriical investigation =-$2,400.00
Total Increase for Change Order No.1 =$21,647.30
Please sign and return the attached Change Order No. 1 document so we can send it to the Board of County
Commissioners for approval. Please call me if you have any questions or concerns about this.
Sincerely /�/•
Cameron Parrott,P.E.
Project Manager
Pc: WCR 64%, WCR 23,and WCR 66 Project file
M:\-Active ProjectsWisc Projects\WCR 64 3-4&WCR 231Design\Contracts\Change Order Letter KBN.doc
I
I
� I
PUBLIC WORKS DEPARTMENT
1111 H STREET,P.O. BOX 758
GREELEY, COLORADO 80632
WEBSITE: WWW.CO.WELD.CO.US
C. PHONE (970) 356-4000, EXT. 3750
wilpFAX: (970) 304-6497
COLORADO
March 3, 2005
Michael C.Ketterling,PE
Ketterling,Butherus&Norton Engineers LLC
820 8th Street
Greeley, Colorado 80631
RE: Owens-Illinois Roadway Improvements,Change Order No. 1
Dear Mr.Ketterling:
We have reviewed your request for additional funds for the above stated project. We are recommending a change order
to be done based on the following items:
County Requested Extras:
Item Original Contract Amount Project Cost Increase
1.ROW/easements(King) $1,600.00 $2,476.00
a.KBN coord.&exh.for Leon - $734.00
2.Potholes—Colo.Boring(6) - $660.00
3.Revise lane widths&striping - $892.00
4.Type County's specs into computer _ $648.00
5.Print plans&specs(40 sets) - $1,458.00
6.Const. observation&testing(EEC) *Increase from$5,.000.00* $10,000.00
TOTAL REQUESTED EXTRAS $16,868.00
Additional hours needed for Drainage/Irrigation Design @ '/ proposed$9,558.60 = $4,779.30
Additional hours for Const.Management/Interpret.throughout construction = $2,400.00
Reduction of original contract to remove geotechmcal investigation =-$2,400.00
Total Increase for Change Order No.1 =$21,647.30
Please sign and return the attached Change Order No. 1 document so we can send it to the Board of County
Commissioners for approval. Please call me if you have any questions or concerns about this.
Sincerely
41.4%4 77u4.423c--
Cameron Parrott,P.E.
Project Manager
Pc: WCR 64' , WCR 23,and WCR 66 Project file
M:\-Active Projects\Misc Projects\WCR 64 3-4 8 WCR 23\Design\Contracts\Change Order Letter KBN.doc
ENGINEERS
February 24, 2005
Mr. Keith Meyer, PE
Engineering Division Manager
Weld County Public Works
1111 "H" Street
Greeley, CO 80631
Dear Keith:
RE: CHANGE ORDER REQUEST TO ENGINEERING FEE CONTRACT
KBN Project No. 03015-R
You had requested in an earlier project team meeting that we prepare an extra proposal to
our original engineering design contract based upon revisions to our scope of services.
We wanted to provide you with this information sooner, however, we've been waiting for
Colorado Boring to provide us with a bill that we just received today.
Our original design contract was for$23,450. Of this amount, $2,400 was intended for a
geotechnical investigation. This work was not subcontracted because the Public Works
Department determined the typical roadway section to be used with our design. This
reduces the design fee to $21,050. To date, we have billed the County$20,700.45.
We have completed the design work as outlined in our June 23, 2004 proposal and the
project was bid out February 15th.
During the final design stage of this project,we were asked to provide additional and
revised legal descriptions and exhibits(by King Surveyors), pothole existing
underground utilities, revise our drawings to reflect a change in the lane widths, striping,
etc., prepare 40 sets of design plans and specifications (along with addenda drawing
revisions) and coordinate with Earth Engineering Consultants for the construction
observation and testing services. A summary of these requested extras is shown below:
Contract Project Cost Increase
1. R.O.W./easements (King) 1,600 $2,476
a. KBN coord. & exh. for Leon - $ 734
2. Potholes— Colo. Boring (6) - $ 660
3. Revise lane widths & striping - $ 892
4. Type County's specs into computer - $ 648
4. Print plans & specs (40 sets) - $1,458
5. Const. observation&testing(ECC)
(agreement attached for review) - $5 000
TOTAL COUNTY REQUESTED EXTRAS $11,868
Ketterling, Butherus & Norton Engineers, LLC.
820 8th Street / Greeley,Colorado 80631 / tel 970-395-9880 / fax 970-395-9881
Mr. Keith Meyer, PE
February 24, 2005
Page 2
The County will oversee construction observation during the construction of the roadway
improvements. If we are requested to become involved,we assume we may invoice the
Public Works Department at our Standard Hourly Rates.
Finally, in the preparation of our proposal for design services, I had estimated a fee of
$2,200 to design the Winder ditch relocation/siphon improvements adjacent to the new
roadway alignment. I, unfortunately, was way off the mark. Due to the difficulties in
determining how the existing ditch worked, numerous site visits to check existing
structures, various alternative hydraulic analyses, two final designs (first option included
only one siphon with a higher road profile and corresponding earthwork volume;the
second option included two siphons with a lower road profile) we expended much more
time and resources than I had planned.
In total, we exceeded my design engineer manhour estimate by 267 hours. I would ask
that the County consider reimbursing this error in my judgment at my cost of$35.80 per
hour for my staff engineers. This would result in a fee increase request of$9,558.60.
I normally would not consider asking my client for an increase in my contract fee and
would certainly understand if you determine an increase is not warranted in this case.
If you have any questions regarding this proposal letter,please give me a call.
Sincerely,
/( ,
Michael C. Ketterling, PE