HomeMy WebLinkAbout20022787.tiff AGREEMENT
Bridge Rehabilitations
THIS AGREEMENT,made this 7th day of October ,2002 ,by and
between Weld County,Colorado,hereinafter called"Owner" and
Can-Do Concrete Construction,Inc. doing business as(an individual,) or
(a partnership,) or (a corporation)hereinafter called"Contractor".
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned:
1. The Contractor will commence and complete the following:Bridge Rehabilitations described in the Invitation for
Bids,Bid No. B0200191
2. The Contractor will furnish all of the material,supplies,tools,equipment,labor and other services necessary for
the construction and completion of the Project described herein.
3. The Contractor will commence the work required by the Contract Documents within ten(10)calendar days after
the date of the Notice to Proceed and will complete the Bridge Rehabilitations within 180 calendar days unless the
period for completion is extended otherwise by the Contract Documents.
4. The Contractor agrees to perform all of the Work described in the Contract Documents and comply with the terms
therein for the sum of$ 134,030.00,or as shown in the Bid Schedule.
5. The term "Contract Documents"means and includes the following:
(A) Invitation for Bids
(B) Instructions to Bidders
(C) Bid Proposal
(D) Bid Bond
(E) Statement of Qualifications and Subcontractors
(F) Required Project Forms
(G) Agreement
(H) Labor and Materials Payment Bond
(I) Performance Bond
(J) Notice of Award
(K) Notice to Proceed
(L) Change Order
(M) Certificate of Substantial Completion
(N) Lien Waiver
(0) Notice of Acceptance
(P) Specifications prepared or issued by the Weld County Public Works Department.
(Q) Colorado Department of Transportation "Standard Specifications for Road and Bridge
Construction"
(R) Colorado Department of Transportation Standard Plans"M& S Standards"
(S) Addenda:
No. N/A , dated ,20
No. N/A , dated ,20
6. The Owner will pay to the Contractor in the manner and at such times as set forth by the Contract Documents,or
otherwise agreed upon in writing.
Page 19
&wan)/ (.1-end . 2OO2-2787
0,3 CI
7. This Agreement shall be binding upon all parties hereto and their respective heirs, executors, administrators,
successors,and assigns.
8. Contract Appropriations: The Owner hereby states and affirms that the amount of money appropriated for this
Contract is equal to or in excess of the Contract amount. No change order to this Contract requiring additional
compensable work to be performed, which work causes the aggregate amount payable under the Contract to
exceed the amount appropriated for the original Contract shall be issued by the Owner unless the Owner assures
the Contractor, in writing,that lawful appropriations to cover the costs of the additional work has been made or
unless such work is covered under a remedy-granting provision contained in the Contract.
IN WITNESS WHEREOF,the parties hereto have executed,or caused to be executed by their duly authorized officials,this
Agreement in three(3)copies each of which shall be deemed an original on the date first above written.
ORDERED BY: ACCEPTED BY:
THE BOARD OF WELD COUNTY COMMISSIONERS CONTRACTOR
BY 114.. BY /C f�el)
NAME Glenn Vaad NAME Pedro R.Gutierrez
(Please Type)
TITLE Chair TITLE President
Date 10/07/2002 ADDRESS 401 N. 21s'Ave.
Greeley,CO. 80631
(SEAL) (SEAL)
ATTEST: J � L % ATTEST:
c �J
1 r /9
Weld Coun Cler�t�.t �rs.�aa�. ' c�Y� 'N '7 1
i�
By MARY E .SHIELD
BY
Deputy Clerk to the BP (Please Type)
TITLE NOTARY PUBLIC
c4--076".4
Page 20
MEMORANDUM_; ,
WillTO: Clerk to the Board DATE: Oct. 3, 2002
C• FROM: Frank B. Hempen, Jr.,
Director of Public Works/County Engineer
COLORADO
SUBJECT: Item Submitted for Chair's Signature
Please submit the enclosed item for the Board's next agenda:
Agreement with Can-Do Concrete Construction, Inc. for the 2002/2003 Bridge Rehabilitations,
Reference Bid No. B0200191
The appropriate documentation is attached.
Enclosures
pc: Cameron Parrott
M:A W PFIL ES\FrancieAAGENDA.M EM
' fi 644, iidr
�U.- 7—.2JG.i