Esther Gesick
From: Chris Gathman
Sent: Thursday, July 13, 2006 5:07 PM
To: Robb@CassedayCreativeDesigns.com; Linda Hulse
Cc: Drew Scheltinga; Esther Gesick
Subject: PF-1090 continuance
Robb,
I understand that PF-1090 is likely going to be continued. You should probably coordinate with Esther Gesick at
Clerk to the Board on hearing dates. Then send a formal written request for a continuance. Be sure to leave
enough time to address all of Public Works concerns, allow for adequate Public Works review time and allow for
time for Planning Staff to prepare the recommendation to the Board. You do not want to have the Board continue
the case again if at all possible.
Chris
7/14/2006 2006-1964
Page 1 of 2
Esther Gesick
From: Robb R Casseday [robb@cassedaycreativedesigns.com]
Sent: Friday, July 14, 2006 3:50 PM
To: Esther Gesick; Chris Gathman
Cc: brad@keirnes.com; 'Tom Frame'; linda@cassedaycreativedesigns.com
Subject: RE: PF-1090 continuance
Attachments: Continuance Letter to WCBOCCs.doc
Esther:
Please ask for a date of Wednesday, October 4th, 2006. Thank you.
Best Regards,
Robb
Robb R. Casseday, ALA,NCARB
Architect Planner
55 South Elm Avenue, Ste.210
Eaton,CO 80615
(970)454-8740 phone&fax
(970) 381-6022 cell
robb@CassedayCreativeDesigns.com
www.CassedayCreativeDesigns.com
CORRECTNESS: If you have any questions or concerns please contact us. Otherwise at information found on this email and its attachments will be
considered coned.
CONFIDENTIALITY NOTICE: This e-mail is intended solely for the person or entity to which it is addressed and may contain confidential and/or
privileged information. Any review,dissemination,copying,printing or other use of this e-mail by persons or entities other than the addressee is
prohibited. If you have received this e-mail in error,please contact the sender immediately and delete the material from your computer.
From: Esther Gesick [mailto:egesick@co.weld.co.us]
Sent: Friday, July 14, 2006 2:30 PM
To: Chris Gathman
Cc: robb@cassedaycreativedesigns.com
Subject: RE: PF-1090 continuance
Chris and Robb,
The Board is going to need a date specific to continue to...how far out are we talking?
Esther
From: Chris Gathman
Sent: Friday, July 14, 2006 2:12 PM
To: Esther Gesick
Subject: FW: PF-1090 continuance
From: Robb R Casseday [mailto:robb@cassedaycreativedesigns.com]
7/20/2006
Page 2 of 2
Sent: Friday, July 14, 2006 1:58 PM
To: Chris Gathman
Cc: brad@keirnes.com; 'Tom Frame'; linda@cassedaycreativedesigns.com
Subject: RE: PF-1090 continuance
Chris and Esther:
Attached please find our formal request to the Board to Continue the Eagle View PUD (PF-1090) hearing
date. If you have any questions or concerns, please let me know as soon as possible.
Thanks and have a good weekend.
Best Regards,
Robb
Robb R.Casseday,A1A, NCARB
Architect/Planner
55 South Elm Avenue, Ste. 210
Eaton,CO 80615
(970)454-8740 phone&fax
(970)381-6022 cell
robb@a CassedayCreativeDesigns.com
www.CassedayCreativeDesigns.com
CORRECTNESS: ff you have any questions or concerns please contact us. Otherwise at information found on this email and Its
attachments wN be considered correct.
CONFIDENTIALITY NOTICE: This e-mail is intended solely for the person or entity to which it is addressed and may contain confidential
and/or privileged information. Any review,dissemination,copying,printing or other use of this e-mail by persons or entities other than the
addressee is prohibited. If you have received this e-mail in error,please contact the sender immediately and delete the material from your
computer.
From: Chris Gathman [mailto:cgathman@co.weld.co.us]
Sent: Thursday, July 13, 2006 5:07 PM
To: Robb@CassedayCreativeDesigns.com; Linda Hulse
Cc: Drew Scheltinga; Esther Gesick
Subject: PF-1090 continuance
Robb,
I understand that PF-1090 is likely going to be continued. You should probably coordinate with
Esther Gesick at Clerk to the Board on hearing dates. Then send a formal written request for a
continuance. Be sure to leave enough time to address all of Public Works concerns, allow for
adequate Public Works review time and allow for time for Planning Staff to prepare the
recommendation to the Board. You do not want to have the Board continue the case again if at
all possible.
Chris
7/20/2006
Casseday Creative Designs, LLC
55 South Elm Avenue, Suite 210
Eaton, CO 80615
July 20,2006
Weld County Commissioners
915 10th Street
Greeley,CO 80632
Dear Commissioners:
This letter is written to request that the Eagle View PUD Subdivision Final Plat hearing scheduled for
Wednesday,July 26,2006 be continued.
The unexpected need has arisen to conduct additional engineering work to address additional questions
raised by Public Works that require the input and cooperation of CDOT and/or Ogilvy Irrigation and Land
Company,the owners of Seeley Lake and its inlet ditch.
Sincerely,
Robb R.Casseday,AIA
Architect/Planner
CC: Brad Keirnes
Chris Gathman
Esther Gesick
Casseday Creative Designs, LLC
Architecture — Planning — Environmental Compliance — Graphic Design
(970) 454-8740 — (970) 454-8742 fax
enzittl:robb@CeessetlayCreatioc•De,igrrs.com nun. ir,sedrryC retell neDe.i,cn .om
t:� I}sist�1�I3 A!>47:1 _
10/02/2006 09:16 3035723516 DUKE ENERGY PAGE D2/02
IlliDuice
DUKE ENERGY FIELD SERVICES
IEnergy Rittht of way
2324 North 7(h Aven(ic
Fit1d Services Gree'ev, CO 80631
970 356 9700
303 572 3516 tax
October 2. 2006
Casseday Creative Designs, LLC
Attention: Linda Hulse
55 South Elm Avenue, Suite 210
Eaton, CO 80615
Re: Ridgeview/Eagle View Farms
DEFS Pipeline Relocation/Abandonment
Dear Linda:
Duke Energy Field Services, LP has reviewed the drawing you provided indicating the
location of our pipeline to be relocated. As drafted, Operations sec no conflicts with the
understanding the pipeline will require a minimum of 4-feet of cover, no trees within our
20-foot easement, and access in the event of repair or maintenance. The walking trail.
poses no issues as defined within the drawing.
If you have any questions or concerns,please feel free to contact me at (970)378-6351.
Best regards,
Duke Energy Field Services,LP
a:///i ic-ort-7
Lew Hagenlock
Right of Way Manager
LH/lc
EXHIBIT
I,.irnr f'rn:lranlc5, 1.1.P
SS Sohrlr F,1m Soo,. 200
Er ree Crrl utalr Rfie•:S
\ BRA 57S 9154
WAN ra.4:it nc•,cn+»
•
KEIRNES'
September 29, 2006
David Fagerberg
3527 Cindy Place
Greeley, CO 80631
Dear Dave:
This letter serves to acknowledge our mutual understanding that the underdrain serving a
portion of your property east of Weld County Road 35 may be realigned and reinstalled
in conjunction with the development of Eagle View Farms PUD.
The manner of the realignment and reinstallation of the underdrain will be at the
discretion of Eagle View Farms so tong as it provides positive drainage from the manhole
in the northeast corner of the PUD parcel which the underdrain enters that serves your
property to the cast of WCR 35. Please acknowledge your agreement hereunder by
signing below.
Thank you very much.
Sincerely,
Brad Keirnes
Manager
Eagle View Farms, LLC
Signed this 3C7_day of September, 2006, by:
David Fagerberg
EXHIBIT
MEMORANDUM
wilge TO: Board of County Commissioners 10/4/2006
.44
COLORADO FROM: Chris Gathman - Planner II
SUBJECT: Proposed amendments to PF-1090 resolution
1) Condition 1.B should be amended: the date of the referral response shall be changed from
"July 25, 2006" to "September 25, 2006".
2) Condition 1.S should be amended: This pertains to the underdrain easements: this condition
s'hould be amended to read: "There are two existing pipes that drain farm ground located to the
east of County Road 35 (one on the north end of the development and one in the center). The
applicant intends to replace the existing underdrain pipes and reroute them along the north end
of the PUD. This drain system will not be owned and should not be maintained by the
Homeowner's Association. A signed and recorded easement agreement covering the proposed
underdrain shall be submitted to the Departments Public Works of Planning Services."
3) This condition should be added and renumbered as condition 1.T: "The applicant shall
provide a signed and recorded easement agreement with the Ogilvy Irrigating and Land
Company covering the proposed easement located on the western edge of the PUD."
4) Condition S (should read U) — item 11 should read: "The ditch easement between Ridgeview
Farms, LLC and the Ogilvy Irrigating and Land Company shall be shown and dimensioned on
the plat. The recording information in regards to the easement shall be indicated."
5) Condition S (should read U) — Item 14 should be removed. (No site triangles are
required).
SERVICE.TEAMWORK.INTEGRITY.QUALITY
EXH'BIT
to
kcirnes Companies, LLP
55 South Hill Menus Suer 200
Eauoo. Colorado no6!S
Fax assn 5.9254
w.keirn eceem
KEIRNES'
October 2, 2006
Don Wacker, President
Ogilvy Irrigating and Land Company
822 7th Street, Ste 760
Greeley, CO 80631
Re: Eagle View Farms PUD situated on 63 acres southwest of the
intersection of WCR 35 and SH 392 in Weld County, Colorado.
Dear Don:
Please acknowledge your review and finding of no conflicts with the Final Construction Plans
and Final Plat dated September 12, 2006, including the revisions to be made thereto as generally
depicted on Exhibits A (North Ditch Segment-- Easement)and Exhibit B (South Ditch Segment
—Reconfigured Detention Pond)attached hereto, and that ditch activities have been adequately
incorporated into the design of the site for the above referenced development that borders the
Seeley Lake Inlet Ditch, by signing below. This acknowledgement shall also include approval of
the continuing discharge of any groundwater from the relocated underdrain beneath the project
property and to the continued discharge of stormwater from the site via the planned stormwater
detention system into the Seeley Lake Inlet Ditch, as shown on the above referenced plans.
Thank you very much.
Sincerely,
6:15z„.0 /
Brad Reines
Manager
Eagle View Farms, LLC
Ogilvy Irrigating and Land Company hereby acknowledges and approves the above referenced
matters this 3 day of 6Pc is S , 2006, by:
Signed: �e�c/�J
Name: DONALD G LJitC_J<E
Title: fire c /of e,h
EXHIBIT
�4Orb
i---L,77-V OA-J T I
•
Ot
I I 3.:
If
I c Dc
1
I
I
1
; + • r , LOT7
�I I\ 1.753 acres
U 1
\ 1\` \
y
\ • \
I —
\\ d 1
1
LOT 8 EA
GL
\ \ \ �
\1 ` 1.76± acres —
A A.
»- v • V\
N
\ A' \
LOT 9
\\ \ \ 1.75± acres
\
v ,
\ \_- \ \.
V
V.
` v \
V y
LOT 12
1 ,I 1.76± acres
I )
1
I
' A A --
—
r �
II
\\ I
ANN' OUTLOT A
NVA 13.36± acres
06 15' Utility @i o / Od, ..h___\ -�""""�
M�8 Drainage a! 10' Irrigation \ 2 yp 20' Utility and re :
.Sh Vii, Easement N Easement 0 Drainage Easement �d
--;•P an ° LOT 10 °{y v LOT 3
!P1.77₹ acres 1 acres .. '�
LOT 9 -1°' 'v 'Ra. 1h
1.75± acres 'r+' 15 Utility k' dW v 533.13'20'5 1101470 �I
N "y .� Drainage Easement �W ---79.54' Algid,"� a.
W. ICr;
�� 533't 3'20'5 CICC 11111
20' Utility k m—. m ,r d'.' e. I1
I Drainage Easement — y� y LOT 11 68.25' r. 10' Irrigation .8 41, _.I.
+.X a 1.763 acres 9 p' . p
20' Utility $/; ;m ',3 /Easement y
and Drainage q"1 u' e• ,6�
H. 2', Easement 60' Right of Way 59 - 9} 10, 0� LO
.76₹
`�, +o'\-rL� ;3� 10� ^,....„....._ 20' Utility and
��8 1�1v �'�to
..8 00, �,g• Drainage Easement 1 J
b , P C33 15' Utility &
� �+ �hbb5ti ��,p• S*y� . �,�7g'- �,�T"�`� Drainage Easement
LOT 12 2'� to 5. " �ti��QO �yh3
f° \_20 Utility and 1J6₹ acres ice,/
711 ,//t,/ b'S�� 0 J� 4
Q �� 60' Ri ht of
Drainage Easement 78 {y3, /i171i/7 4o• 5� �� ^
20' Utility and mo ? 21717 i �`���.' C:c .2
�;•
Drainage Easement "' I. '3 `�• y i 022 031
+ 71 w� G'° Gam/ Gbi.., 15' Utility &
m �� . , 10' Irrigation Drainage Easement
IA
10' irrigation
'°'- � Easement a u /Easement 023 o
9311,71, - o - LOT 15
372 51 °
N823529 E_ Z45— 1.J5₹ acres , _ o�
7ti
N8735 29 E Y65 20 ��C Jg t° 20' Utility and '
20'-Utility & - — tY \,t°• Drainage Easement .7 a
0 " Drainage 15' Utility h� , . reo
Easement Drainage Easement
o - I OUTLOT C 10' 2ti i LOT 16
L28.00' dia. ` ]( . 1.76₹ acres '00
landscape island d3 to 0/
\ OUTLOT A mow;. LOT 13 LOT 14 t° S•ec./ 10' Irrigation o NI
13.36₹ acres o'.,. 1.75₹ acres 1.713 acres ., Easement t,, N
20' Utility and _ (1p• �'�� 30' 3t
Drainage Easements
\ LIit;
; Wi ° o u, � I gib* t• . ,"' and EasemeDrainant �ti0/ 20 Utility and J 'Sr O ✓✓ y
'\ Drainage Easement tiJ^ I rt.T \ in
20' Utility and o� 15' Utilityasem & i o ,n
.� ^ Drainage Easement ta- o 20' Utility kf - Drainage p
0 Drainage Easement Easement 4 LOT 17 nl
C)0,
,o_ ,r° 176₹ acres al
0
OG,
L A ` - ' lIto' I I I
.I 552465/ 5832' --- - 129' o ^io 20' Uti ty4 ondr�✓„ t 8847. ��IQy
W 1 I2, N
388
_- _
OOi N Drainage Easement ryl� �
P
}.+ ' 2990— NIA
LOT 18 10' Irrigation �Up I
1.74₹ acres Easement b ti W
TLOT A b � lQ \
\ 3.363 acres /U 'r
50 031
N Q4 58
Cr NOF43'31 O/I/II1`, -
120.31' 'VI,O 56-r2.5 7468. . 015
in
3 019
20' Utility R ..i061-15- t o LOT 19
Drainage Easement NI1I11
�W�+{' -1 g i1jjst'//' 1.653 acres ho' 15' Utility t
\ r 1�//' ,.✓� „hp Drainage Easement
30 I
m LOT 20
\ at
r3 1.76₹ acres
\ a? .ho
Z. 20' Utility and '� 10•I
�r^ Drainage Easement �y9
Jr Ditch Easement \ ,L°i \ 20' Utility &
Drainage Easement
179.31
_—
--- -- _, 47582'
• __-.-. { !� -... .. _ _ _ -584"37�5�-E ]'4ita^ „..(---76-1.74,
v N89'37'58"w 1353.05'
Corner I
,R—SR
Revisions to Proposed
Resolution of Approval
October 4,2006
Revisions/Corrections:
Para 2.f. WCR 35 requires a left hand turn lane be constructed as requested by Weld County Department
of Public Works. An improvements agreement has been submitted to and approved by Public Works which
addresses the safe design of the turn lane and the proposed cost necessary for construction of the turn lane
improvement to WCR 35 both of which will be completed by the applicant.
Para I.B. The applicant shall address the concerns and comments of the Department of Public Works,as
stated in referral responses dated September 22 and 25,2006. Written evidence of such shall be submitted
to the Weld County Department of Planning Services. Any and all conditions in the referral responses
relating to the Ogilvy Ditch have been addressed and are deemed to be satisfied by the agreement between
the applicant and the ditch company dated October 2, 2006(a copy of the letter is made a part of this
resolution). Any and all conditions in the referral responses relating to underdrainage of the Fagerberg
property onto and across the applicant's property have been addressed and are deemed to be satisfied by the
letter submitted by the applicant to and approved by Fagerberg dated September 29,2006(a copy of the
letter is made a part of this resolution). Any and all conditions in the referral responses relating to the use
of an exclusive easement granted to Duke Energy have been addressed and are deemed to be satisfied by
the letter provided by Duke Energy dated October 2,2006 (a copy of the letter is made a part of this
resolution). Any required modifications to the Final Plat and Construction Drawings consistent with the
above correspondence shall be approved by the Department of Public Works prior to the recording of the
final plat. Public Works shall notify the Department of Planning Services of such approval prior to
recording of the plat. Easements for the proposed underdrain and the additional agreed upon easement for
the Ogilvy Ditch shall be signed and recorded and submitted to Public Works. Such easements shall be
shown on the Final Plat and Construction Drawings as necessary.
4.A. "Eaton"shall be substituted for"Ault".
Additional Conditions to Resolution:
New Para I.C. The north line of lot 7 and the west line of lots 7, 8, 9, and 12 shall be fenced with five(5)
foot solid fencing in satisfaction of comments in the September 25,2006 Public Works memo concerning
accessibility to the Ogilvy Ditch.
Deletions to Resolution: