HomeMy WebLinkAbout20073261.tiff laTETRA TECH 1900 S.Sunset Street,Suite 1-F Longmont CO 80501
Tel:303.772.5282 Fax 303.772-7039
•
MEMORANDUM
To: David Bauer, Weld County Public Works
From: Becky Eustice
Subject: Filing Plan for draft Improvements Agreement
Date: June 14, 2007
The phasing of the Waterfront at Foster Lake will occur from the northwest to the south,with the
development of those parcels along I-25 being last. It is anticipated generally as follows (please
see the attached map).
Filing 1 —
Those lots located between WCR7 and Foster Lake, and located north of the
northernmost access to WCR 7. This filing includes the on-site infrastructure and the
• following off-sites:
• Overlot Grading for these Lots
• Sanitary Sewer South to the Liberty Gulch Trunk Line
• Waterline Looping to the Line in WCR 7
Filing 2—
Those lots located south of Filing 1 and extending to the relocated Weld County Road 28,
on the west side of the existing Outlet#3. This filing includes the on-site infrastructure
and the following off-sites:
• Grading of this area, including the breach path
• Relocation of WCR28 (including utilities, and structures)in a three lane section
• Reconstruction of the breach path location
• Grading of the breach path to the St. Vrain River
• Construction of WCR 7 between the high school and the northernmost boundary
Filing 3 (3A and 3B)
Those lots located directly south of Foster Reservoir and north of WCR 28, and a small
pocket of lots on the south side of WCR 28. This filing includes the on-site infrastructure
and the following off-sites:
• Possible improvements to SH66 and WCR7 (based on the traffic study)
• • Reconstruction of the spillway on Foster Reservoir
• Grading of this area and the spillway path to the intersection of the breach path which
leads to the St. Vrain River
1
2007-3261
Filing 4-
• Those lots located directly south of WCR 28 between the breach path and the western-
most boundary to approximately the extension of WCR 26.5. This filing includes the on-
site infrastructure and the following off-sites:
• Completion of the grading south of WCR 28 between the breach path and the western
property boundary.
• Construction on WCR 26.5 between the western property line and WCR 7.
• Completion of a paved section of roadway between WCR 7/WCR 26.5 and the
existing pavement at WCR 25 /WCR 5.5
Filing 5
Those lots located along our western boundary south of WCR 26.5. This filing includes
the on-site infrastructure only.
Filing 6
Those lots directly south of Filing 4 and west of the breach path. This filing includes the
on-site infrastructure and the following off-sites:
• Improvements to the St. Vrain River adjacent to Filing 6 and Filing 9
Filing 7
Those lots located along I-25 and north of WCR 28. This filing includes the on-site
infrastructure only.
• Filing 8
Those lots located along I-25 and directly south of WCR 28. This filing includes the on-
site infrastructure only as well as the completion of the grading between I-25 and the
breachpath for the southern portion of the property.
Filing 9
Those locates located between Filing 8 and the St. Vrain River. This filing includes the
on-site infrastructure only.
Filing 10
This filing includes the commercial, multi-family, and community center located on the
southeast corner of WCR 28 and WCR 7. This filing includes the on-site infrastructure
only.
•
2
«• / To
c
a � {
\ \ \ \
) /
k \ 2 (
j / c 0 � (
to LL
a \
§ a) ) C
/ c 8-
§ 3
2 / 2 . (
7 CO \ wc re
E / O
7
• ) { ) 13 0
f / { c $ 0 \
- a : 2 ) { ) k
CO c / eL $ ] § Ti k E $ 7 / 2
t 0 C \ O ) ) i � � \
0 E .2 �� � / k § c To
0 -
f 0 . 2, E V.T.
) � \
- \® f k c co k «
§ § / ] t . f )
a > — -e-r. w0
12 § $ # 2 G t [) § a
f Wi / .0 ) 402 / E
CO / r
C▪O co w N « co N
Cr Cf Cr CC CC
§ § k k 0
. al
C a §
il /
EXHIBIT AA
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 1
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading(incl.Temp Seed&Mulch, Eroision Control, 213,869 CY $1.50 $320,803.50
Inlet/Outlet Protection)
Street grading(inci in Site Grading)
Street base 50,000 SY $2.00 $100,000.00
Street paving 50,000 SY $15.00 $750,000.00
Curbs,gutters,and culverts 1,300 LF $12.00 $15,600.00
Sidewalk 7,100 SY $20.00 $142,000.00
Storm sewer facilities 5,208 LF $45.00 $234,360.00
Retention ponds(incl in Site Grading)
Ditch Improvements
Subsurface drainage
Sanitary sewers See Separate Agreement with St.Vrain San Dist
• Trunk and forced lines See Separate Agreement with St.Vrain San Dist
Mains-Water 8" See Separate Agreement with Longs Peak Water
Laterals(house connected) See Separate Agreement with St.Vrain San Dist
On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak Water
Fire hydrants See Separate Agreement with Longs Peak Water
Survey and street monuments and boxes 1ILS I $15,000.001 $15,000.00
Street lighting Provided by United Power
Street Names 37 EA $200.00 $7,400.00
Fencing requirements
Landscaping
Park improvements
Road culvert 3 EA $5,000.00 $15,000.00
Grass lined swale
Telephone Provided by K2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak Water
SUB-TOTAL: I I I $1,600,163.50
Engineering and Supervision Costs $160,016.35
(Testing, inspection, as-built plans and work in addition to preliminary and final plat; supervision of actual
construction by contractors)
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $1,760,179.85
• The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent.
Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 1 of 40
By:
Applicant
•
Applicant
Date: ,20 .
Title
(If corporation,to be signed by President and attested to by Secretary,together with corporate seal.)
•
Page 2 of 40
EXHIBIT AA
Name of Subdivision
• or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 2
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading(incl.Temp Seed 8 Mulch,Eroision Control, 460,050 CY $1.50 $690,075.00
Inlet/Outlet Protection)
Street grading find in Site Grading)
Street base 40,000 SY $2.00 $80,000.00
Street paving 40,000 SY $15.00 $600,000.00
Curbs,gutters,and culverts 13,000 LF $12.00 $156,000.00
Sidewalk 6,700 SY $20.00 $134,000.00
Storm sewer facilities 6,200 LF $45.00 $279,000.00
Retention ponds(incl in Site Grading)
Ditch Improvements
Subsurface drainage
Sanitary sewers See Separate Agreement with St.Vrain San Dist
Trunk and forced lines See Separate Agreement with St.Vrain San Dist
Mains-Water 8" See Separate Agreement with Longs Peak Water
Laterals(house connected) See Separate Agreement with St.Vrain San Dist
• On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak Water
Fire hydrants See Separate Agreement with Longs Peak Water
Survey and street monuments and boxes 1JLS I $20,000.001 $20,000.00
Street lighting Provided by United Power
Street Names 26 EA $200.00 $5,200.00
Fencing requirements
Landscaping
Park improvements
Road culvert 3 EA $5,000.00 $15,000.00
Grass lined swale 6,870 LF $25.00 $171,750.00
Telephone Provided by K2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak Water
SUB-TOTAL: I I I $2,151,025.00
Engineering and Supervision Costs $215,102.50
(Testing,inspection,as-built plans and work in addition to preliminary and final plat;supervision of actual
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $2,366,127.50
The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent.
• Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 3 of 40
By:
Applicant
•
Applicant
Date: , 20
Title
(If corporation, to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 4 of 40
EXHIBIT AA
Name of Subdivision
• or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 3
Location: See Vicinity Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading(incl.Temp Seed&Mulch, Eroision Control, 340,000 CY $1.50 $510,000.00
Inlet/Outlet Protection)
Street grading(incl in Site Grading)
Street base 137,000 SY $2.00 $274,000.00
Street paving 137,000 SY $15.00 $2,055,000.00
Curbs,gutters,and culverts 18,921 LF $12.00 $227,052.00
Sidewalk 16,778 SY $20.00 $335,560.00
Storm sewer facilities 8,330 LF $45.00 $374,850.00
Retention ponds (incl in Site Grading)
Ditch Improvements
Subsurface drainage
Sanitary sewers See Separate Agreement with St.Vrain San Dist
Trunk and forced lines See Separate Agreement with St.Vrain San Dist
Mains-Water 8" See Separate Agreement with Longs Peak Water
Laterals(house connected) See Separate Agreement with St.Vrain San Dist
• On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak Water
Fire hydrants See Separate Agreement with Longs Peak Water
Survey and street monuments and boxes 1f Is I $20,000.001 $20,000.00
Street lighting Provided by United Power
Street Names 30 EA $200.00 $6,000.00
Fencing requirements
Landscaping
Park improvements
Road culvert 1 EA $5,000.00 $5,000.00
Grass lined swale 2,000 LF $25.00 $50,000.00
Telephone Provided by K2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak Water
SUB-TOTAL: I $3,857,462.00
Engineering and Supervision Costs $385,746.20
(Testing, inspection,as-built plans and work in addition to preliminary and final plat; supervision of actual
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $4,243,208.20
The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent.
• Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 5 of 40
By:
Applicant
•
Applicant
Date: , 20
Title
(If corporation,to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 6 of 40
EXHIBIT AA
Name of Subdivision
• or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 4
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading find.Temp Seed&Mulch,Eroision Control, 490,000 CY $1.50 $735,000.00
Inlet/Outlet Protection)
Street grading(incl in Site Grading)
Street base 23,000 SY $2.00 $46,000.00
Street paving 23,000 SY $15.00 $345,000.00
Curbs,gutters,and culverts 17,848 LF $12.00 $214,176.00
Sidewalk 19,120 SY $20.00 $382,400.00
Storm sewer facilities 7,057 LF $45.00 $317,565.00
Retention ponds(incl in Site Grading)
Ditch Improvements 416 LF $25.00 $10,400.00
Subsurface drainage
Sanitary sewers See Separate Agreement with St.Vrain San Dist
Trunk and forced lines See Separate Agreement with St.Vrain San Dist
Mains-Water 8" See Separate Agreement with Longs Peak Water
Laterals(house connected) See Separate Agreement with St.Vrain San Dist
• On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak Water
Fire hydrants See Separate Agreement with Longs Peak Water
Survey and street monuments and boxes 1ILS I $20,000.001 $20,000.00
Street lighting Provided by United Power
Street Names 51 EA $200.00 $10,200.00
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone Provided by K2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak Water
SUB-TOTAL: I I 1 $2,080,741.00
Engineering and Supervision Costs $208,074.10
(Testing, inspection,as-built plans and work in addition to preliminary and final plat; supervision of actual
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $2,288,815.10
The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent.
• Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 7 of 40
By:
Applicant
•
Applicant
Date: , 20
Title
(If corporation, to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 8 of 40
EXHIBIT AA
Name of Subdivision
• or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 5
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading(incl.Temp Seed&Mulch, Eroision Control, 380,000 CY $1.50 $570,000.00
Inlet/Outlet Protection)
Street grading(incl in Site Grading)
Street base 22,000 SY $2.00 $44,000.00
Street paving 22,000 SY $15.00 $330,000.00
Curbs, gutters,and culverts 17,842 LF $12.00 $214,104.00
Sidewalk 11,000 SY $20.00 $220,000.00
Storm sewer facilities 9,507 LF $45.00 $427,815.00
Retention ponds(inci in Site Grading)
Ditch Improvements
Subsurface drainage
Sanitary sewers See Separate Agreement with St.Vrain San Dist
Trunk and forced lines See Separate Agreement with St.Vrain San Dist
Mains-Water 8" See Separate Agreement with Longs Peak Water
Laterals(house connected) See Separate Agreement with St.Vrain San Dist
• On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak Water
Fire hydrants See Separate Agreement with Longs Peak Water
Survey and street monuments and boxes 1lLS I $20,000.001 $20,000.00
Street lighting Provided by United Power
Street Names 45 EA $200.00 $9,000.00
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone Provided by K2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak Water
SUB-TOTAL: I I I $1,834,919.00
Engineering and Supervision Costs $183,491.90
(Testing, inspection,as-built plans and work in addition to preliminary and final plat;supervision of actual
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $2,018,410.90
The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent.
• Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 9 of 40
By:
Applicant
•
Applicant
Date: ,20
Title
(If corporation, to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 10 of 40
EXHIBIT AA
Name of Subdivision
• or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 6
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading(incl.Temp Seed&Mulch,Eroision Control, 1,198,620 CY $1.50 $1,797,930.00
Inlet/Outlet Protection)
Street grading(incl in Site Grading)
Street base 8,000 SY $2.06 $16,000.00
Street paving 8,000 SY $15.00 $120,000.00
Curbs,gutters,and culverts 14,000 LF $12.00 $168,000.00
Sidewalk 13,000 SY $20.00 $260,000.00
Storm sewer facilities 6,500 LF $45.00 $292,500.00
Retention ponds(incl in Site Grading)
Ditch Improvements
Subsurface drainage
Sanitary sewers See Separate Agreement with St.Vrain San Dist
Trunk and forced lines See Separate Agreement with St.Vrain San Dist
Mains-Water 8" See Separate Agreement with Longs Peak Water
Laterals(house connected) See Separate Agreement with St.Vrain San Dist
• On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak Water
Fire hydrants See Separate Agreement with Longs Peak Water
Survey and street monuments and boxes 1lLS I $20,000.00 $20,000.00
Street righting Provided by United Power
Street Names 24 EA $200.00 $4,800.00
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone Provided by K2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak Water
SUB-TOTAL: I I 1 $2,679,230.0
Engineering and Supervision Costs $267,923.00
(Testing, inspection,as-built plans and work in addition to preliminary and final plat;supervision of actual
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $2,947,153.00
The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent.
• Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 11 of 40
By:
Applicant
•
Applicant
Date: ,20
Title
(If corporation,to be signed by President and attested to by Secretary, together with corporate seal.)
•
•
Page 12 of 40
EXHIBIT AA
Name of Subdivision
• or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 7
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading(incl.Temp Seed&Mulch,Eroision Control, 250,000 CY $1.50 $375,000.00
Inlet/Outlet Protection)
Street grading(incl in Site Grading)
Street base 11,400 SY $2.00 $22,800.00
Street paving 11,400 SY $15.00 $171,000.00
Curbs,gutters,and culverts 9,700 LF $12.00 $116,400.00
Sidewalk 12,000 SY $20.00 $240,000.00
Storm sewer facilities 4,500 LF $45.00 $202,500.00
Retention ponds(ind in Site Grading)
Ditch Improvements
Subsurface drainage
Sanitary sewers See Separate Agreement with St.Vrain San Dist
Trunk and forced lines See Separate Agreement with St.Vrain San Dist
Mains-Water 8" See Separate Agreement with Longs Peak Water
Laterals(house connected) See Separate Agreement with St.Vrain San Dist
• On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak Water
Fire hydrants See Separate Agreement with Longs Peak Water
Survey and street monuments and boxes 1ILS I$20,000.00 $20,000.00
Street lighting Provided by United Power
Street Names 17 EA $200.00 $3,400.00
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone Provided by K2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak Water
SUB-TOTAL: I I I $1,151,100.00
Engineering and Supervision Costs $115,110.00
(Testing,inspection,as-built plans and work in addition to preliminary and final plat; supervision of actual
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $1,266,210.00
The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent.
• Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 13 of 40
By:
Applicant
•
Applicant
Date: ,20 .
Title
(If corporation,to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 14 of 40
EXHIBIT AA
Name of Subdivision
• or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 8
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading(incl.Temp Seed 8 Mulch, Eroision Control, 275,000 CY $1.50 $412,500.00
Inlet/Outlet Protection)
Street grading(incl in Site Grading)
Street base 14,000 SY $2.00 $28,000.00
Street paving 14,000 SY $15.00 $210,000.00
Curbs, gutters,and culverts 12,000 LF $12.00 $144,000.00
Sidewalk 13,000 SY $20.00 $260,000.00
Storm sewer facilities 4,400 LF $45.00 $198,000.00
Retention ponds find in Site Grading)
Ditch Improvements
Subsurface drainage
Sanitary sewers See Separate Agreement with St.Vrain San Dist
Trunk and forced lines See Separate Agreement with St.Vrain San Dist
Mains-Water 8" See Separate Agreement with Longs Peak Water
Laterals(house connected) See Separate Agreement with St.Vrain San Dist
•
On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak Water
Fire hydrants See Separate Agreement with Longs Peak Water
Survey and street monuments and boxes 1JLS J $20,000.001 $20,000.00
Street lighting Provided by United Power
Street Names 25 EA $200.00 $5,000.00
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone Provided by K2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak Water
SUB-TOTAL: I I $1,277,500.00
Engineering and Supervision Costs $127,750.00
(Testing,inspection,as-built plans and work in addition to preliminary and final plat;supervision of actual
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $1,405,250.00
The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent
• Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 15 of 40
By:
Applicant
•
Applicant
Date: ,20 .
Title
(If corporation,to be signed by President and attested to by Secretary, together with corporate seal.)
•
•
Page 16 of 40
EXHIBIT AA
Name of Subdivision
• or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 9
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading(incl.Temp Seed&Mulch, Eroision Control, 815,000 CY $1.50 $1,222,500.00
Inlet/Outlet Protection)
Street grading(inG in Site Grading)
Street base 13,000 SY $2.00 $26,000.00
Street paving 13,000 SY $15.00 $195,000.00
Curbs,gutters,and culverts 11,200 LF $12.00 $134,400.00
Sidewalk 12,000 SY $20.00 $240,000.00
Storm sewer facilities 5,600 LF $45.00 $252,000.00
Retention ponds(ind in Site Grading)
Ditch Improvements
Subsurface drainage
Sanitary sewers See Separate Agreement with St. Vrain San
Trunk and forced lines See Separate Agreement with St. Vrain San
Mains-Water 8" See Separate Agreement with Longs Peak
• Laterals(house connected) See Separate Agreement with St.Vrain San
On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak
Fire hydrants See Separate Agreement with Longs Peak
Survey and street monuments and boxes 1 I LS (Illiff=it#I $20,000.00
Street lighting Provided by United Power
Street Names 20 EA $200.00 $4,000.00
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone Provided by K2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak
SUB-TOTAL: I I I $2,093,900.00
Engineering and Supervision Costs $209,390.00
(Testing, inspection, as-built plans and work in addition to preliminary and final plat; supervision of
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $2,303,290.00
• The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent.
Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 17 of 40
By:
Applicant
•
Applicant
Date: , 20
Title
(If corporation,to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 18 of 40
EXHIBIT AA
Name of Subdivision
• or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 10
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements. (Leave spaces blank where they do not apply)
Improvements Quantity Units Unit Costs Estimated
Construction Cost
Site grading(incl.Temp Seed 8 Mulch,Eroision Control, 155,000 CY $1.50 $232,500.00
Inlet/Outlet Protection)
Street grading and in Site Grading)
Street base 24,000 SF $2.00 $48,000.00
Street paving 24,000 SF $15.00 $360,000.00
Curbs,gutters,and culverts 6,238 LF $12.00 $74,856.00
Sidewalk 3,500 LF $20.00 $70,000.00
Storm sewer facilities
Retention ponds(incl in Site Grading)
Ditch Improvements
Subsurface drainage
Sanitary sewers See Separate Agreement with St.Vrain San
Trunk and forced lines See Separate Agreement with St. Vrain San
Mains-Water 8" See Separate Agreement with Longs Peak
• Laterals(house connected) See Separate Agreement with St.Vrain San
On-site sewage facilities
On-site water supply and storage
Water Mains(includes bore) See Separate Agreement with Longs Peak
Fire hydrants See Separate Agreement with Longs Peak
Survey and street monuments and boxes I
Street lighting Provided by United Power
Street Names 9 EA $200.00 $1,800.00
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone Provided by 1(2 Communications
Gas Provided by Xcel Energy
Electric Provided by United Power
Water transfer See Separate Agreement with Longs Peak
SUB-TOTAL: I I I $787,156.00
Engineering and Supervision Costs $78,715.60
(Testing, inspection, as-built plans and work in addition to preliminary and final plat; supervision of
TOTAL ESTIMATED COST OF IMPROVEMENTS AND SUPERVISION $865,871.60
• The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County,or its duly authorized agent.
Said improvements shall be completed according to the construction schedule set out in Exhibit AB.
Page 19 of 40
By:
Applicant
•
Applicant
Date: , 20
Title
(If corporation,to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 20 of 40
EXHIBIT AB
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 1
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within 1 year from the date of approval of the final plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July,2008,Filing 1 Shall be
Street paving Complete in July,2009
Curbs, gutters,and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
•
Page 21 of 40
The County,at its option,and upon the request of the Applicant, may grant an extension of time for
completion for any particular improvements shown above,upon a showing by the Applicant that the above
schedule cannot be met.
•
By:
Applicant
Applicant
Date: , 20
Title
(If corporation,to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 22 of 40
EXHIBIT AB
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 2
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within 1 year from the date of approval of the final plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July, 2009, Filing 2 Shall be
Street paving Complete in July,2010
Curbs, gutters, and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
•
Page 23 of 40
The County,at its option,and upon the request of the Applicant, may grant an extension of time for
completion for any particular improvements shown above, upon a showing by the Applicant that the above
schedule cannot be met.
•
By:
Applicant
Applicant
Date: ,20
Title
(If corporation,to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 24 of 40
EXHIBIT AB
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 3
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within 1 year from the date of approval of the final plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July,2010,Filing 3 Shall be
Street paving Complete in July, 2011
Curbs, gutters,and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
i
Page 25 of 40
The County,at its option,and upon the request of the Applicant, may grant an extension of time for
completion for any particular improvements shown above,upon a showing by the Applicant that the above
schedule cannot be met.
•
By:
Applicant
Applicant
Date: ,20
Title
(If corporation,to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 26 of 40
EXHIBIT AB
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 4
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within 1 year from the date of approval of the£mal plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July,2011, Filing 4 Shall be
Street paving Complete in July,2012
Curbs, gutters,and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
•
Page 27 of 40
The County,at its option,and upon the request of the Applicant, may grant an extension of time for
completion for any particular improvements shown above,upon a showing by the Applicant that the above
schedule cannot be met.
•
By:
Applicant
Applicant
Date: ,20
Title
(If corporation,to be signed by President and attested to by Secretary, together with corporate seal.)
•
•
Page 28 of 40
EXHIBIT AB
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 5
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within 1 year from the date of approval of the final plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July,2012,Filing 5 Shall be
Street paving Complete in July,2013
Curbs,gutters, and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
•
Page 29 of 40
The County,at its option,and upon the request of the Applicant,may grant an extension of time for
completion for any particular improvements shown above,upon a showing by the Applicant that the above
schedule cannot be met.
•
By:
Applicant
Applicant
Date: , 20
Title
(If corporation,to be signed by President and attested to by Secretary, together with corporate seal.)
•
•
Page 30 of 40
EXHIBIT AB
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 6
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within 1 year from the date of approval of the final plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July, 2013,Filing 6 Shall be
Street paving Complete in July,2014
Curbs,gutters,and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
•
Page 31 of 40
The County,at its option, and upon the request of the Applicant, may grant an extension of time for
completion for any particular improvements shown above, upon a showing by the Applicant that the above
schedule cannot be met.
111
By:
Applicant
Applicant
Date: ,20
Title
(If corporation, to be signed by President and attested to by Secretary,together with corporate seal.)
411
Page 32 of 40
EXHIBIT AB
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 7
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within 1 year from the date of approval of the final plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July, 2014,Filing 7 Shall be
Street paving Complete in July,2015
Curbs,gutters,and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
•
Page 33 of 40
The County,at its option,and upon the request of the Applicant, may grant an extension of time for
completion for any particular improvements shown above, upon a showing by the Applicant that the above
schedule cannot be met.
•
By:
Applicant
Applicant
Date: , 20
Title
(If corporation, to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 34 of 40
EXHIBIT AB
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 8
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within 1 year from the date of approval of the final plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July, 2015,Filing 8 Shall be
Street paving Complete in July,2016
Curbs, gutters,and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
Page 35 of 40
The County, at its option,and upon the request of the Applicant, may grant an extension of time for
completion for any particular improvements shown above, upon a showing by the Applicant that the above
schedule cannot be met.
•
By:
Applicant
Applicant
Date: ,20
Title
(If corporation,to be signed by President and attested to by Secretary, together with corporate seal.)
•
•
Page 36 of 40
•
EXHIBIT AB
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 9
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within I year from the date of approval of the final plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July, 2016, Filing 9 Shall be
Street paving Complete in July, 2017
Curbs, gutters,and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
•
Page 37 of 40
The County,at its option, and upon the request of the Applicant,may grant an extension of time for
completion for any particular improvements shown above, upon a showing by the Applicant that the above
schedule cannot be met.
•
By:
Applicant
Applicant
Date: ,20
Title
(If corporation,to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 38 of 40
EXHIBIT a
• Name of Subdivision
or Planned Unit Development: Waterfront at Foster Lake
Filing: Filing 10
Location: See Phasing Map
Intending to be legally bound,the undersigned Applicant hereby agrees to provide throughout this Subdivision
or Planned Unit Development the following improvements.
All improvements shall be completed within 1 year from the date of approval of the final plat.Construction of
the improvements listed in Exhibit AA shall be completed as follows:
(Leave spaces blank where they do not apply.)
Improvements Time for Completion
Site grading Assuming Final Plat Approval in
Street base July,2017,Filing 10 Shall be
Street paving Complete in July,2018
Curbs, gutters,and culverts
Sidewalk
Storm sewer facilities
Retention ponds
• Ditch improvements
Subsurface drainage
Sanitary sewers
Trunk and forced lines
Mains
Laterals(house connected)
On-site sewage facilities
On-site water supply and storage
Water mains
Fire hydrants
Survey and street monuments and boxes
Street lighting
Street name signs
Fencing requirements
Landscaping
Park improvements
Road culvert
Grass lined swale
Telephone
Gas
Electric
Water Transfer
•
Page 39 of 40
The County,at its option,and upon the request of the Applicant, may grant an extension of time for
completion for any particular improvements shown above, upon a showing by the Applicant that the above
schedule cannot be met.
• By:
Applicant
Applicant
Date: , 20
Title
(If corporation, to be signed by President and attested to by Secretary,together with corporate seal.)
•
•
Page 40 of 40
WELD COUNTY ROAD ACCESS INFORMATION SHEET
•
Weld County Public Works Department Date: June 14, 2007
1111 H Street, P.O. Box 758, Greeley, CO 80632
Phone: (970)356-4000, Ext. 3750 Fax: (970)304-6497
1. Applicant Name: HF Holdings,LLC do Darwin Horan(attn: Linda Sweetman-King)
Address: 4 Inverness Court East#300,Englewood, CO 80112
Phone: 303-468-6700
Authorized Agent: Julie Cozad, Land Planning Manager,Tetra Tech
Address: 1900 S.Sunset St., Suite 1-F, Longmont, CO 80501
Phone: 303-772-5282
2. Address or location of access: See plat map
3. Legal: S2 of Section 27,T3N,R68W,the N2/NW4,the E2/SW4 and the E2 of Section 34,T3N, R68W,the
NW4/NE4 of Section 3,T3N, R68W of the 6th P.M.,Weld County,Colorado
Weld County Road#7 Side of Road: East Distance from nearest intersection: .5 mile south of
intersection of WCR 7 and SH 66,east of and adjacent to WCR 7,west of 1-25
Is there an existing access to the property? Yes See attached map for proposed access points
1 4. Proposed Use: Mixed Use PUD,Commercial/Residential
5. Site Sketch: Please refer to attached plat due to numerous access points.
Legend for Access Description: A'rii
AGR= Agricultural
RES = Residential
Oil&Gas
O&G= Oil&
D.R. = Ditch Road
= House
• n = Shed
A = Existing Access
A = Proposed Access
r
OFFICE USE ONLY:
Road ADT Date Accidents Date
Road ADT Date Accidents Date
Drainage Requirement Culvert Size Length
pecial Conditions
Installation authorized ❑ Information Insufficient 411 Reviewed By: Title: