(:rand Junction Drexel, Barren & Co. has reviewed the attached change order request from
Growling Bear Construction Inc. for an additional manhole. We have
compared the unit price quoted to other estimates we recently received and it
vii I3 W. 4th Street is fair and consistent for the installation of a manhole. Don't hesitate to call
(iiceIe�. Colorful() 51163.4 with any questions.
970-35 I-0645
970-35l-Illi65 Pox
Drexel,Barrell& Co.
David W. Peek, P.E.
yeaoa9
2007-3325
/ -vt) P(0
Growling Bear Construction Inc. PROPOSED CHANGE ORDER
No. 00001
2330 4th Ave Phone: 970-353-6964
Greeley, Colorado 80631 Fax: 970-353-6974
TITLE: Add manhole DATE: 10/12/2007
PROJECT:Weld County south parking lot JOB: 2719
TO: Attn: PAT PERSICHINO CONTRACT NO:2719-1000
WELD COUNTY
915 10TH Street
Greeley, CO 80631
Phone: 356-4000
RE: To: From: Number:
DESCRIPTION OF PROPOSAL
Provide new manhole at existing 12" RCP per revised plans dated 10/8/07 from Drexel Barrel',
Item Description Stock# Quantity Units Unit Price Tax Rate Tax Amount Net Amount
00001 Provide new manhole 1.000 LS $2,620.00 0.00% $0.00 $2,620.00
00002 Profit and overhead(12%) 1.000 LS $314.00 0.00% $0.00 $314.00
Unit Cost: $2,934.00
Unit Tax: $0.00
Lump Sum: $0.00
Lump Tax: $0.00
Total: $2,934.00
APP'RO r L /
J C�1
Btt, By:
Curtis Naibauer of E • 1 mil
Date: 10/12/2007 Date: OCT 2 2 2007