HomeMy WebLinkAbout20071798.tiff CHANGE OWNER © RCI Project#0615CO ORDER ARCHITECT CONTRACTOR ❑ ALA DOCUMENT G70/ FIELD ❑ OTHER ❑ PROJECT: Weld County North Jail Complex Phase 3 CHANGE ORDER NUMBER: 05 2110 0 Street Greeley,CO 80631 DATE: 5/29/2007 TO CONTRACTOR: ROCHE CONSTRUCTORS,INC. ARCHITECT'S PROJECT NO: Post Office Box 1727 Greeley,CO 80632 CONTRACT DATE: 9/22/2006 CONTRACT FOR: Construction of new building The Contract is changed as follows: COR#9- Winter condition costs through 5/21/07; RCI had a$100,000 allowance in contract for $127,123.00 winter condition costs that will be utilized in this change order;This change order does not include extended general condition costs. ($100,000.00) $27,123.00 Not valid until signed by Owner, Architect, and Contractor The original(Contract Sum)(" ar teed Maxim. ^• Price)was $10,650,017.00 Net change by previously-authorized Change Orders $102,991.00 The(Contract Sum)(Gu ^ranteed"" ._. Price)prior to this Change Order was $10,753,008.00 The(Contract Sum)(G ecd Maxim -- o�cc)will be by this Change Order in the amount of $27,123.00 The new(Contract Sum)( )including this Change Order will be $10,780,131.00 The Contract Time will be unchanged. The date of Substantial Completion as of the date of this Change Order thereof is November 3,2007. NOTE: This summary does not reflect changes in the Contract Sum,Contract Time,or Guaranteed Maximum Price which have been authorized by Construction Change Directive. Bley Associates Roche Constructors,Inc. Weld County,Colorado ARCHITECT CONTRACTOR OWNER P.O. Box 1727 Greeley,CO 80632 By � William H. Jerke, Chair Pro—Tem (.Dgte/ O Date 5/25/2007 Date 06/27/2007 AIA DOCUMENT G701 • CHANGE ORDER • 1987 EDITION • AIM) • ©1987 • THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE.,NW.,WASHINGTON.D.C. 20006 G701-I987 044- dq-p9 2007.1798 ROCHE CONSTRUCTORS, INC. SUMMARY SHEET Weld County Jail North Complex Phase 3 Greeley,CO RCI Project #0615CO RCI's COR# 9 Date: May 21,2007 Description of Change: Winter Condition Costs though 5-21-07 Company Amoun Duran Excavating $ 36,197 Keifer Concrete $ 30,279 Roche Constructors Inc. $ 60,364 Sub-Total $ 126,840 Roche Constructors Breakdown: Material Sub/Equip Labor Sub-Totals $ $ $ 0 Taxes (0%mat'I;50.00%labor burden) 0 0 0 Sub-Total - RCI Total $ - Summary: Subcontractor Totals $ 126,840 Mark-Up on Sub Work (10%) $ N/A RCI Work $ 0 Mark-Upon RCI Work (10%) $ 0 Sub-Total $ 126,840 Payment & Performance Bond (.8%) $ 215 General Liability Insurance (.256%) $ 69 Total: Total $ 127,123 This price is good for seven (7) days. Time extension required for this work: 0 days. e (06 /l Approved by Date • C®2 ©c9°) tan excavating Inc. January 24, 2007 Roche Constructors 361 71S`Ave Greeley Colorado 80634 Re: Weld County Jail Phase III Snow Removal Attn: Ryan Strub Dear Mr. Strub The follow is a cost to remove snow for the above project. 01/02/2007 Loader 7 Hours 150.00 = 1,050.00 Skid Loader 2 Hours 95.00 = 190.00 Labor 2 Hours 25.00 = 50.00 Total 1,290.00 Awa `k. 1/3/2007 Excavator K-220 1 Hour 125.00 = 125.00 Loader 2 Hours 150.00 = 300.00 Skid Loader 2 Hours 95.00 = 190.00 wf Total 615.00 a 1/5/2007 Loader 1 Hour 150.00 = 150.00 RC! Total 150.00 o- 1/8/2007 .IAN 2 9 2007 Excavator K-220 1 Hour 125.00 = 125.00LY Loader 2 Hours 150.00 = 300.00 Truck 3.5 Hours 62.00 = 217.00 - Labor 3.5 Hours 25.00= 87.50 Total 729.50 er-, ^JAN 3 1 ?PUT 418 N.9th Avenue • Greeley, Colorado 80631 (970) 351-0192 1/9/2007 Excavator K-220 1 Hour 125.00= 125.00 Loader 2 Hours 150.00= 300.00 Skid Loader 3 Hours 95.00 = 285.00 Truck 3.5 Hours 62.00= 217.00 Labor 8 Hours 25.00= 200.00 Total 1,127.00 (40..A1 3 1/10/2007 Excavator K-220 1 Hour 125.00 = 125.00 Skid Loader 2 Hours 95.00 = 190.00 Labor 3 Hours 25.00 = 75.00 LA/ Total 390.00 1/16/2007 Loader 1 Hour 150.00 = 150.00 ,,.u/ Total 150.00 Subtotal 4,451.50 Markup 667.73 Grand Total 5,119.23 Sinter Ernest E. Duran C/ President IAN 2 9 2��� Duran Excavating Ay T1 1's st y. i= •..r PROJECT LOGS 3 excavating ,� - ^. 41e. t t t V::'SW' '. f: a ,. `vr-..w_r., ` i91''::1 lit?..?, •k" k?i d ,.�. '. , ,..yf JOB NUMBER DATE IN CHARGE TEMPERATURE ._.. GENERAL WEATHER CONDITIONS .2 / BAM/ NOON a AM EMPLOYEES AND CLASSIFICATION FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP! PHASE!CATA CLASS HRS. EQUIP It STARTIFINISH \-\b<o \C$ 1 yt 3-- r -c5 0 9-#- LIG Darn-cc) O r =;P, -+mom l o .-.Y• c7PreTht,.�''1Oc� ate_ �m ' 2) -ocl C) . --A-Li') 200--Pf { ^t .c :._i-c., L� �•! ,,� !- ;- ?- Xn-Cod) ? 10 ;^t1 LU . FBACK CHARGES UST MATERIAL LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED \ r-Z I •r `-c),-cc";•-d T p . r'` DESCRIPTION: 7_,s7,,,..in sr, o iIt) �! d. �• / y ' iF y., L% 3. ` /o 4er /So sba 544 95 EQUIPMENT UNIT! HOURS LABOR OTHER :::_ c - - . -- c,F P‘-f CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE 3 NAMES OF OTHER INSPECTORS,REPRESENTATIVES OF OWNER.A CH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME Per 51.::II cit.; z-1-as ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS ': CONCRETE FLATWORK TRAFFIC CONTROL 1'.ELECTRICAL OTHER LANDSCAPING - OTHER �Y _. WI]INWI 2 flair h Che \ Greeley,Colorado ° Las Vegas,N eanugare,Inc ` s 9 ,'77'.' evade :Westminster,Colorado .,. ADDITIONAL .�..�.,..:2 .,�., ._., � � , ,WORK AUTHORIZATION (Daily) Bill red to: ate: Weld County/Roche Constructors,Inc. 111-2-07 I Name:WELD JAIL PHASE Ill - No.: 0615 Specifically describe Fr • Remove snow building Pad AWA 018 Duran Excavating. - Cost Code - Shaded area for office use only Employee's name Reg. Rate O.T. O.T. Total PT&1 Total Hrs. Hrs. Rate Raw Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total Total j _ . , Material Subtotal ~ Cost Code Tools or Equip. NO. Rate Rental Period Total Loader //WLS Skid Loader 7 Arc Tools&Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW /� `( SEE ATTACHED AWA's from Duran ! Subcontractor Subtotal \' SUBTOTAL RCI Rep Calendar day extension OVERHEAD (_%) ❑ No ❑ Yes of day(s) SUBTOTAL Owner/Sub Rep PROFIT(__%) TOTAL r��r t� c ti ? 9 1 -/ ' y� ctr�r�(9)0)356-3611 ru-v,(9]0)656 3610 Dcnvcr Metro 3D])5343)16 361 7Y Avenu_ &;G341 V_0.Co- 1) ( O612; Greeley,Colorado 9Nct om , i1 F '4 •�.,rr• ' s`s+F� i unn ws. r '� PROJECT LOGS Z IL {��ps ' inc. • t - JOB NUMBER DATE IN CHARGE TEMPERATURE - GENERAL WEATHER CONDITIONS WED• 2 8AM NOON 4AM 32. \\ \ © .•LRV .I .•�U 13° yon Sur,nV EM•L.YEESAN• CLASSIPIC•TI•N FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP/ PHASE#CATA CLASS HRS. EQUIP It START/FINISH .. u • cc\,Cr. C4 ---).-',-)--4-, • I-Li ..•r. tt. BACK CHARGES 1. UST MATERIAL,LABOR&EQUIPMENT L NAME OF COMPANY BEING BACK CHARGED I R �G�t_ --r. .nti rry/- 1.;. DESCRIPTION: /11'. ' $° �' .cc Z i r.rf� t{/Z-L Off' ,. L - 7 ,,._ �- _.,/( •y1 EQUIPMENT UNIT t HOURS LABOR OTHER - - , '‘ . -,y1 S. - 1() Z. .••� .Q. y/tPi ( L'-1) H)'.^^.CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE NAMES OF OTHER INSPECTORS.REPRESENTATIVES OF OWNER,ARCH/ENGR•• DE VI ;W' PROJECT TYPE OF INSP. . .I '.NI TIME err -- SU:C• A • S •NJ•: SRE ASPHALT SIGNAGE.STRIPING r CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER .-_ ... .. . _ _ LSIJp1001 ItRoche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado "'S Constructors Inc. s l�$�. >` ''" 1� 4.44,14:P, ADDITIONAL WORK AUTHORIZATION (Daily) .R r ll Date: Job Job: Weld County/Roche Constructors,Inc. 1-3-07 Name:WELD JAIL PHASE III No.: 0615 pecifically describe -Remove snow building Pad.Staging area. uncover and recover footer excavation line 14.3& 14.7 south of T and line 22 from L.5 to R+1- AWA 021 Duran Excavating. • Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. _ Total PT&I --- - Total Hrs. Hrs. Rate Raw Lloyd McEwen Fabian Con Rodrico Ocompo - - - - -Labor subtotal . Cost Code Material Req. Quan. Unit Sub Tax -- -otal �. Total t. y... Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Loader L-43 2HR Skid Loader SL-50 - IHR _..... EXCAVATOR EX-40 1HR Tools&Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED AWA's from Duran (Sr' Subcontractor Subtotal (S SUBTOTAL RCI Rep - OVERHEAD (_%) Calendar day extension 0 No SUBTOTAL 0 Yes_of day(s) cite. - Owner/Sub Rep PROFIT I %) TOTAL Ay _ Wilco(970'.3563611 :I<(970)356-3619 Center Me Ito(303)534-3716 361 71 Avenue(60634? P.O.3a" 1727(306)?) Greeley,Colorado rnnv rocheconstruc[ars.cam 3:1‘ '- 1( "^ uran PROJECT LOGS wtµ xcavat(ny ^ JOB NUMBER DATE IN CHARGE TEMPERATURE - GENERAL WEATHER CONDITIONS q .\ 8AM NOON 4AM \ • l iNt 2 -2 - b _ EMPLOYEES AND CLASSIFICATION FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIPS PHASES CATA CLASS HRS. EQUIPS START/FINISH hL` �c. _ BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED \"\bck\ \ C (YA'C . DESCRIPTION: ^��f/^4 - 41_, ,457.477"tij 1. ij -yL Lk EQUIPMENT UNITS HOURS LABOR OTHER / • CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON T OB DATE a NAMES OF OTHER INSPECTORS.REPRESENTATIVES OF O .NQB ORg.VISITING PROJTT TYPE OF INSP. TIME Aar Wide/ ASPHALT SIGNAGE.STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING r OTHER LO3o-1001 Roc le - Greeley,Colorado Las Vegas,Nevada Westminster,Colo do• ' :'W Conatructor4,Inc. Fa,F � .� q ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors 1/5/07 Name:WELD JAIL PHASE III Specifically describe . ..,, additional work: Duran snow removal for Friday, ate: AWA 032 Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rote Raw . .,_ ^ .. 1r I , y i ` t t . - > ., P.iGi t a e ,u r• '. ' Labor subtotal - Cost Code Material Req. Quan. Unit Sub Tax Total _ i Lt.. \-�mT 't W' Y $li i 1.244144.4 -. . Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools S.Equip.Subtotal r: Invoice No. Subcontractor Amount SEE ATTACHED Project logs from Duran Exc. ALL PRICING SUBJECT TO REVIEW Subcontractor Subtotal SUBTOTAL R R p OVERHEAD( %) Calendar day extension El No SUBTOTAL ❑ Yes_of day(s) Owner/Sub Rep ' PROFIT(__%) _.TOTAL ,J. ••' f)` Cf:, (970)350-3611 Fax 970);56-3619 De, r i 0.20(303)533716 36171'A.er tea'86634) P 0.BOY 1727!806V Greeley,ColorddC wyntirpcheconoructQrs.con ` ' a _ AltRoche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado `it Constructors,Inc. �C ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors, Inc. 12-7-06 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Cover over excavated area and footing excavation along line L.5 and 1 (winter protection) AWA 009 Duran Excavating. Shaded area for office use only Cost Code Employee's name Reg. Rote O.T. O.T. Total PTBJ Total Hrs. Hrs. Rate Raw .4;t1.1 x + 5xs 1 h�gn4,3> v,.. w• 4 . fie i 51 y' Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total Total i , Material Subtotal COST Code Tools or Equip. NO. Rate Rental Period Total! Tools S. Equip.Subtotal - f 4 Invoice No. " ;r Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED LOAD TICKETS-AND D LOGS 7 /) f!/_O rr Subcontractor Subtotal ( 4r ( : Tn SUBTOTAL RCI Rep OVERHEAD ( %( Calenar do 0 Yes of dayls) SUBTOTAL Owner/Sub Rep PROFIT( %) TOTAL z t. 1,ep at' X Ofrre(970)356-3611 Fax(970)356-3619 Denver Metro(303)531-3716 361 71"Avenue(80634) P.O.Bo'1727(80632) Greeley,Colorado www.rocheconstructors.com r. l �1 �. 4 area rc ' ' PROJECT LOGS = • NMI animating JOB NUMBER DATE IN CHARGE TEMPERATURE 3.., Yr\ON. 8AM NOON :AM GENERAL WEATHERCONDRTONS 3Z \ Ca b t* So° .tea ,.► EM•LWEES AN.C •SSIFIC•TI:■ - - FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP/ PHASE/CATA CLASS HRS. EQUIP START/FINISH ► ✓ . l .fy r AS S cPRIAU &Wit 4 2kcr if, 0 Al 6C4. 2atici-i . L '/ / 'nilL -RMRlbt> L4, , '(!C( en L BACK CHARGES UST MATERIAL LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED I R T\\r DESCRIPTION: / +z /, Um Y 2 i 1 EQUIPMENT UNIT: HOURS LABOR �.nA R lc\-\-3 'X OTHER b,c• ua\ofz r-k-43 I, 3_,'Ln TYkD 11).„ /C-__H" Tc2.6 . 3S U %N - =c'L Kr . CHECK HERE IF REGULAR RESIDENT INSPECT R WAS ON OB THIS DATE 0 P NAMES OF OTHER INSPECTORS. REPRESE I S O WNER.ARCH/ENGR OR DE V SmNG E� TYPE OF INSP. TIME ASPHALT SIG:NAGE,STRIPING CONCRETE STRUCTURES SURVEYORS .a CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER Lci 30-1W1 v:; -.� � I) Y, 441 . ,'N .c+.i. uran tt'z 'zd, '`' C IIr. PROJECT LOGS i- ti:cawtin9 ' TEMPERATURE GENERAL WEATHER CONDITIONS 7uL..S. -•i BAM NOON 4AM ). \ G\ .� 1, 6 y CY EM•L•VEES •N• C •SSIFICATI•N FULL NAME HRS. PHASE 8 CATA CLASS HRS. EQUIP i PHASES CATA CLASS HRS. EQUIP i START/FINISH Akgii%le _,el 1ocVaq- o 1-�, L- 2 -Can -a -'ls EX- non-_ Sr `' "zoo-(oo o '1'1, k43-0- T.cxsZstr)h -3oN g awa4q o t,- , St.-5 a-abp-Coc) n `'r Sk-9 lob-3ad FI*_:;=A.) cPaa`z : 'moo-mac o '1 EX-HO 'oo-b0 n '''), E*14106-330., 1 OD-33Q Rccc w, Ck b 8 COoo- c L J C-� L. --- "l S — ,_vio- /3 loo-3?,n l._ G� q 3 Doog-01 7DI 3 Tit-2f, Rrn-Ito° jo\1U Rx,t2A6 5.2._ e O Qq 0. 10&'''55() BACK CHARGES I/`21 UST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED ROC_kl= DESCRIPTION: D 1/yte7le._ t-C-J 6:ft. .(//�{ /, _ i /mac . lG/ / Z %-( . e +.i� , . # ,i,fil 1./� l7�Pi1�4�/!t��nIL> /-'t7.4� —6� ' Y (/ lkvdi' V--0/-1 / Po••- ✓L -r,/t/u.L c-I/��J-`��/ . EQUIPMENT UNIT s HOURS TABOR OTHER g`121-4U he-gal1 SK10 t-a c ER Sl,s 3 1.0c.4, ,E .' ,. I.- U3 z • 8 Toi-kN otiR1C^(.{n CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE a NAMES OF OTHER INSPECTORS,REPRESENT VES F OWNER.ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME SU=C. -A ••S •NJ•= SITE ASPHALT SIGNAGE,STRIPING - CONCRETE STRUCTURES SURVEYORS . , CONCRETE FLATWORK TRAFFIC CONTROL • .. ELECTRICAL OTHER LANDSCAPING OTHER LGI 30-1 001 . Rothe P�"✓ (,y Greeley,Colorado Las Vegas,Nevada Wesrminster,Colorado Constructors,Inc, ,�,q, ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Jobtfrr' I Job to: Weld County/Roche Constructors 1/9/07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe additional work: Duran snow removal for Tuesday, 1/9/07.AWA 033 Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw• Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total .t34! ! F jr' r..-- Material Subtotal ' Cost Code Tools or Equip. NO. Rate Rental Period Total • Tools&Equip.Subtotal Invoice No. Subcontractor Amount SEE ATTACHED Project logs from Duran Exc. ALL PRICING SUBJECT TO REVIEW (% Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD(_%( Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT(__%( :9--)± ,l r(q °mere(974. 356-3611 Fax(9701356-3619 Denver Mctro(303)534-3716 36171`Avenue(E0634) PO.Bow 1727(80632) Gretney,f7 oc • ''.4 �'—uRotsCOM �` ^'_' -+3.t� a Cam." B., „ CT- ��� PROJECT LOGS ` tna �a .6 ��xaavating r,. I.. . _. ,. ... CONDITIONS . .. .... JOB NUMBER `. 'DATE IN CHARGE TEMPERATURE GENERAL WEATHER C ONDNDITIONS V.)G'D r aAM NOON 4 A ?�� \\\ .\r-1 .,ARP`/N_F4x I& Lk ' -i rvsV EMPLOYEES AND CLASSIFICATION FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH \-0 I%)r, 7 t - 2 )SOD-Con O V-7 L-LI Alab.gey 9 I Fk-I-R -T TcYc -4. i'3-t\-- KI 2 a1C0.gc\ C �Z 5L-51 2-:_co-(oS'--s --)<ym_D.3d :. 771= i I F'!_, I'_l- s • . 100G 1 - 1— <J PRGCTII"G 2 -rn-GS ./- -05 _ 1n0-L-I `" FP ,,.� c Q..- P: a �Ic)O-C7,o O '/7 E:Ic:'-3 ,26 -35 n X1.5 rx3c 'loo-LIoh p 0C -C :-:_-) 9 __cyD-{.0 I~ -'7 — fix)-2U S — ,13')-LIDO 5a BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT .' NAME OF COMPANY BEING BACK CHARGED F DESCRIPTION: 9 i p J v , s. EQUIPMENT UNIT# HOURS LABOR ^ OTHER R •-:,.-E, A )14 N P ..):-.2-.iE Llc-7._ CXcAl )P--:5 i f-u. . I CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE a• NAMES OF OTHER INSPECTORS.REPRESENTATIVES OF OWNER.ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME FA— St- ::.:1\1 SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER d. - LGI]O-ICUI t%Rohe i Constructors,IncBil Greeley,Colorado Las Vegas,Nevada Westminster,Colorado ADDITIONAL WORK AUTHORIZATION (Daily) I Date: to: Weld County/Roche Constructors,Inc. 1-9-07 Job Job Name:WELD JAIL PHASE III No.: 0615 Specifically describe Remove snow from footings along line 14.3,heat subgrade with propane weed burner to remove shallow frost for backfill AWA 039 Duran Exc. . _ Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT8.I Total Hrs. Hrs. Rate Raw Jarrod Johnson 7 - - $2 tom^w y. John Rodriquez 8.5 $25. _ wxr �Y_, ' �P C.I. C a n Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total Total - ..._. K ..: .. Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Skid Loader Sk-51 $95.00 2 Excavator EX-43 $110 1 Tools 8,Equip.Subtotal ISII Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT(_%( TOTAL N , .;ti Cfrr2)970)356-3611 rax(970)356-3619 0 r rcr!c,n(303)534 3716 351 71 Avenue;80634) PC Bo:1727(30632) Greeley,Colorddn 4w.mv.rorit=constructors.corn .t J M3'13,i„Y {, GY 'PROJECT LOGS • MINI xoavating _ JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS 8 A NOON 4AM A- IAM EMPLOYEES AND CLASSIFICATION FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP R PHASES CATA CLASS HRS. EQUIPS START/FINISH i-Jr l. ? »-?a 0 t L- 7 -r.D a S L--43 ti c o--sop A���Pw L\ L2t-cmoo -t D, -A n05�x� BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED (� DESCRIPTION: _ 1 / "Dvict. 5SN_ EQUIPMENT UNIT ` HOURS LABOR OTHER CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE 2 NAMES OF OTHER INSPECTORS.REPRESENTATIVES OF OWNER.ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LOP 30-1001 QTR It�Q�, ,e Greeley,Colorado Las Vegas,Nevada Westminster,Colorado constructon,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 1-16-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Remove snow pad AWA 041 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Firs. Hrs. Rate Raw , ;f _"4---, - - Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total Total t Material Subtotal _ ':.4.1: ,.. . Cost Code Tools or Equip. NO. Rate Rental Period Total Loader 1 hour Tools&Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal nU,l SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT(_�( TOTAL OKcc(9]0)356-7611 Fax(9]0)356 3619 Denver nK^.ro(303)53x ]16 361 n-av,nue(6063x) v.O.BBog 1727!6063_') Greeley,Colorado wr,r,.rrcneco stvcrors.corn C)2 ooq Itan\ Iexcavating Inc. February 12, 2007 Roche Constructors 361 71St Ave Greeley Colorado 80634 Re: Weld County Jail Phase III Extra Cost on Frost Removal Attn: Ryan Strub Dear Mr. Strub The following is a cost breakdown on extra cost we incurred to load and haul off frozen soil, in addition DEI had to load from stockpile backfill material. 1-18-2007 Used Excavator at stockpile area to move snow and remove frost from pile. Loader was used to stockpile frozen material on site ready for haul off. Excavator K-220 2 hr x 125.00 = 250.00 Loader 6 hr x 110.00= 660.00 s Sub Total 910.00 a'""` 1-19-2007 Loader was used to stockpile frozen material on site and load truck to haul frozen soil to county yard. Loader 8 hr x 110.00 = 880.00 Truck 3.5 hr x 58.00 = 203.00 �N �t SZ Sub Total 1,083.00 1-22-2007 Load and haul off frozen material, also removed snow from work area. Loader 5.5 hr x 110.00 = 605.00 Truck 4.5 hr x 58.00 = 261.00 Supervision 5.5 hr x 45.00 = 248.00 „1 Sub Total 1,114.00 p k 418 N.9th Avenue• Greeley, Colorado 80631 (970)351-0192 1-25-2007 Stock piled frozen material on site. Loader 8.5 hr x 110.00 = 935.00 A� y (DO Sub Total 935.00 1-26-2007 Load frozen material on site and hauled to county yard. Loader 7.5 hr x 110.00 = 825.00 Truck 7.5 hr x 58.00 = 435.00 rr Gs Sub Total 1,260.00 �r " 1-29-2007 Stock pile frozen material on site. Loader 8 hr x 110.00 = 880.00 G Sub Total 880.00 Pr's' 2-1-2007 Load frozen material on site and hauled to county yard. Loader 4.5 hr x 110.00 = 495.00 Truck 4.5 hr x 58.00 = 261.00 n '1 Sub Total 756.00 Qi Total 6,938.00 Markup 1,041.00 Grand Total $7,979.00 Sincceerdy C e . uran President Duran Excavating Ii! \ ran PROJECT LOGS ' ®xcavating lac. JOB NUMBER I DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS -MAR 8AM NOON I aAM ��� \\�v\"�1.\\ 41 • V GAGS ?N0° I ' um LAW\11D EMPLOYEES AND.CLASSIFICATION- FULL NAME HRS. PHASE 8 CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH 1`.X LYV ).n MC 'K."'_NI R `��..),-n-C-,S a 2 E)(LA ) oo-Go O Cc C-k-1b -?0O- et ICac--, I: 7,-,A1,\' 'cm`s, R 7-2 nr7)-GS L 2 -- 9, ncy-F L7 fl L-143 1 nn-31.54D 7c.2 r i C_'?is 4 = /'k^-(= ) �. 2 - -.7, •Y' 47,.) 0 2 Lf.:.--1 qieY')—irr7 --4:-_F %-,,-. O_: --' ., 4 7on-CS L 7 »,x,. C-05 C 1 — floc` BACK CHARGES LIST MATERIAL LABOR 8 EQUIPMENT • NAME OF COMPANY BEING BACK CHARGED �' JC). \ C /�I i n; :c - DESCRIPTION: am. c / l rst" AS ad w irit L 41-4, lc~4A,-1 C6.1 bM --o ‘-' 12,41-i Snit4 WS C.-4 ILL Qc.,4-/hi bre .4,a -I TO, ,C vu.c., < •S ft- .. c✓ O1.- j•F i .4% t5 7714,..4 nA^,, 2 19vett I:. .9i. _ Si0GL AY :.-7 /- >->A Jti /.) •..T 4 Fc , J EQUIPMENNT UNIT= HOURS LABOR OTHER i; •:m e A'-t-3 a /(..,47_.)X-7-:' /-=fF k"-;.-/�i1t) ? 'Kin. . CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE Id NAMES OF OTHER INSPECTORS. REPRESENTATIVES OF OWN ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP TIME P,RrSgaRl ) ASPHALT SIGNAGE•STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATNORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING 1 OTHER LGI]a.T Ow ,[4,`,,\•) ROChe Greeley,Colorado Las Vegas, Nevada Westminster, Colorado L ,ki Constructors.Inc ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors, Inc. 1-18-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate footer line 22 and partial 21.2 frost 1.5ft thick stock pile frozen material AWA 051 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rote O.T. O.T. Total PT&1 Total Hrs. Hrs. Rate Raw L$205.00Labor subtotal S2 Cost Code Material Req. Quan. Unit I Sub Tax Total Total Material Subtotal 7- Cost Code Tools or Equip. NO. Rate Rental Period Total Loader 1 hour Tools 8 Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal Ici\t ' SUBTOTAL RCI Rep OVERHEAD ( %( Calendar day extension 1:1 No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %( TOTAL A , Office(970)356-3611 Fax(970)356-30199 Denver Metro(303)534-3716 361 71"avenue(90634) P.O.Box 1727(80632) Greeley,Colorado VAVVJ rocheconstmctors.tom i f.-) i ,'s; Roche Greeley, Colorado Las Vegas, Nevada Westminster, Colorado L (",M. Constructors.Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors.Inc. 1-19-07 Name:WELD JAIL PHASE Ill No.: 0615 Specifically describe Excavate tooter line 21.2 frost 1.5ft thick stock pile frozen material and haul off to county pit AWA 052 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw k i 1 Labor subtotal 52a5m Cost Code Material Req. I Quan. Unit Sub Tax Total Total t ,r-.e ".-- ^. .4. -"III 6 es. rov .`x Material Subtotal i :ti- Cost Code Tools or Equip. NO. Rate Rental Period Total Loader 1 hour Tools&Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN JSubcontractor Subtotal SUBTOTAL RCI Rep- tar_ OVERHEAD ( %( Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s} Owner/Sub Rep PROFIT( %( TOTAL q� ! R µ� r • G Yi 3: y ✓ YL Y x^ta Office(970)356-3611 Fix(970)356-3619 Denver Metro(303)534-3716 361 7P'avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rocneconsimctors.com I � .\iSran\ fr/c- PROJECT LOGS - \IIIIIIIIIIIIzeavatinc. Inc. JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS fppm 8AM NOON dAM 2 Oil ka ,U '1)1Ekc\ 9.6 Stioin'? EM•L•Y a.AN'CLASSIFICATI•N "s: ^ FULL NAME HRS. PHASE 8 CATA CLASS HRS. EQUIP#1 PHASE#CATA CLASS HRS. EQUIP I START/FINISH `5- rr., ' \� ."\ X0.9 X11 -> -; = �. T L'r -I- BACK CHARGES LIST MATERIAL,LABOR 8 EQUIPMENT NAME OF COMPANY BEING BACK CHARGED 1°'\-c cL // DESCRIPTION: // / •"/ .�. J !% c.z- ice/, ear c X- ç ' -:v J -. t %,(2/,. i/ !2 /�<1 "CJ.< 7.A-1 ktr2/Z) EQUIPMENT UNIT= HOURS LABOR OTHER r ‘ ), a4/7.-c- --_ "fir Z 8 Oz-. /rr ,<--EA 3. 7 d -2154l) C11q! / 1,'t _ CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE UA NAMES OF OTHER INSPECTORS. REPRESENTATIVES OF OWNER.ARCH/ENGR�OJ/R�DEVIVISIITING PROJECT TYPE OF INSP. TIME SUBCONTRACTORS ON JOB SITE 9 ..",,:::714.' ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LG.30-1001 I� PROJECT LOGS excavating inc. JOB NUMBER I DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS MO N- SAM I NOON I 4AM 7, t 27\C 1 ,• •Lt lb .... 06 CLODL Le FOG' EMPLOYEES AND CLASSIFICA11O• FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP X PHASE#CATA CLASS HRS. EQUIP It START/FINISH L \r o Vc1c-1=',,3FN S z= -roc> L -1O0 - 17 ; :1-F7-.�r-: -,TD 1\, .-f,N1 'aci-S -2-..V`). --c° 0 y5 1-1=13 27 .) o / 2 -far) 4z3O 7- -.1 Q,tP..\bl)FZ -CC -.1..X)n-a , o cS gn51 -ice-1z,% Rt_ ) <5 , rx--cre-O TI). •`/.S T.,6 %00772 BACK CHARGES LIST MATERIAL LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED • .."_ DESCRIPTION: ? - _ ;_ ^' �� 1-O S c7'LP ��� ;rr �!: .���irFlcrGl OAL K - %i/ a ���i� �•y 6-zk P LV I.14-2-100-99 SKtI- ..3 ..1)7.17,- S !�(j//,,, r/7.// .?1^,l'!: T'� _• 4/rn1 //.l'� .?.-s!//leif c, •. i: ,�. ./1'zic_/ -( U�®„ 9-c 4+ ,a(x)-(O°(J �' EQUIPMENT UNIT a HOURS LABOR - OTHER rN7 <j• :C /-Li c=-5 - C: c/-C S,S ,-- - P ,I.CK 7Z.-!.': yS CHECK HERE IF REGULAR RESIDENT INSPEC R WAS ON THE JOB THIS DATE M NAMES OF OTHER INSPECTORS. REPRESE IVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME \AI PFrt SHQgiN SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LGI 30.1001 \ IP 1 J ¢ 'G' Roche Greeley, Colorado Las Vegas, Nevada Westminster, Colorado •_1:5‘.)' :: Constructors.Inc ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 1-22-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate footer line 21.2 frost 1.5ft thick stock pile frozen material and haul off to county pit remove snow from pad AWA 056 Duran Exc. Shaded area for office use only Cost Coae Employee's name Reg. Rate 0. O.T. Total PT8.1 Total Hrs. Hrs. Rate Raw Labor subtotal $20540 Cost Code Material Req. Quan. Unit Sub Tax I Total Total t lty`7-. Material Subtotal s:y#x.,,; Cost Code Tools or Equip. NO. Rate Rental Period Total Loader I hour Tools&Equip.Subtotal -- Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN � Subcontractor Subtotal L. \� / SUBTOTAL RCI Rep "`��� OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL A vz _ ... 5,`,' Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71°Avenue(80634) P.O.Be.1727(80632) Greeley,Colorado MAN rocheconstructors.com Yx 'Duran '� PROJECT LOGS xeavating Inc. JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS T`A1uC)NS, 8AM I NOON 4AM Z� EM•L•YEES AN• CLASSIFIC•TI•N FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP X PHASEX CATA CLASS HRS. EQUIP X START/FINISH „ur/(rpm \.\r y9� Mc _ wF tl - ,S 7:-.7, 0-(00 n t-), y� 1-i'3O FAR\AN CAUZ ` S ^•�c>O-GZ> 0 - S E.-'�3 /C2-6 -2-1136 R nc RI:CC CNcPst.D. ` .S -17A-OO-4-n L-- ( , , r-y`o BACK CHARGES LIST MATERIAL LABOR E.EQUIPMENT NAME OF COMPANY BEING BACK CHARGED Mme'..). DESCRIPTION: r - / X i,7te Zzner ,�nc(r/;13 25: 7 d ✓ O EQUIPMENT UNIT* HOURS LABOR OTHER (-:)(lAii4/7. y-i/3 Ric. hM0LEJZ 1.-y3 S,5 t c RApa lc) CrgmPo CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE NAMES OF OTHER INSPECTORS.REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME Q4t St-;7-R;N SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LSI 30-1001 F_ Cons avuc tors Inc che Greeley, Colorado Las Vegas, Nevada Westminster, Colorado ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors.Inc. 1-25-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate tooter line line X from 15 to A.0,electric room and partial mech room footings first floor frost 1.5ft thick stock pile frozen material and haul off to county pit AWA 060 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rote O.T. O.T. Total PT&1 Total Hrs. Hrs. Rate Raw I Labor subtotal $205-CO Cost Code Material Req. Quan. Unit Sub Tax Total Total Material Subtotal - Cost Code Tools or Equip. NO. Rate Rental Period Total Loader I hour Tools & Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN C:7SUBTOTAL Subcontractor Subtotal RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of daylsl Owner/Sub Rep PROFIT( %) TOTAL gal Office(970)356-3611 Far(9]0)356-3619 Denver Metro(303)539-3]16 361]l°avenue(80634) P.D.Box 1727(80632) Greeley,Colorado Imnv.rochecons[ructors.com ti 0(16 I®arae P� PROJECT LOGS _ IEEE Inc. JOB NUMBER DATE I IN CHARGE I TEMPERATURE GENERAL WEATHER CONDITIONS FR 8 A I NOON I aAM 3Z3 \\ e_ \0 Lc c -V I kV\ qi° '�S° Rr v\V-i) EM•L•VEES AN. CLASSIFIC•TI•N FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH \-X\J-0 \\- C11\friF U ,Sc 2D-a/..)--(4) 0 a S r-t/3 - yr1 -D,O Fee,ga\nt e kuz .5 77(..)..)-(a-) n -,S I_x•t4'3 (' n Z -)no 1-nn RtCaRnn DCA 2 fln-C? k iS — e--to I- — --inn-44- BACK CHARGES LIST MATERIAL LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED RncNF DESCRIPTION: >� / •l -G "/2 /- V/r -J 8/ e7 "=-' . 93'/X 2` 'wka'/) - l / ' '- 9S2 u r UIPMENT UNIT x HOURS BOR OTHER ,cXrrL't;7G,6. /n 7 7. 5 Iv- erca ,C-1-R 9, 5 l7/,,r7P 7RUO< 7 <-2l *-75 • 7, 5 R-�/_},C•e nzwm�b CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE d NAMES OF OTHER INSPECTORS.REPRES TIVES OF OWNER.ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP TIME PaT ciy'ctzi N ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER to'30-400i 11 A5'. Roche Greeley, Colorado Las Vegas, Nevada Westminster,Colorado L`\ N,d Consiruclors.Ino ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 1-26-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate tooter line west of line A.0 from V.5 to 7+/-,frost I.5ft thick stock pile frozen material and haul off to county pit AWA 065 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total _ Hrs. Hrs. Rate Raw I I Labor subtotal Moo Cost Code Material Req. Quan. Unit Sub Tax Total Total 1 lrY 'i'YJ':t₹Arr L a lt_ Material Subtotal ,v: Cost Code Tools or Equip. NO. Rate Rental Period Total Tools& Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN - Subcontractor Subtotal OV SUBTOTAL RCIRep OVERHEAD I %l Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT I %) TOTAL .. s i-,..:,:r4e "Office(970)356-3611 Fay(920)356-3619 Denver Metro(303)534-3716 361 71°Avenue(80634) v.O.Bog 1727(80632) Greeley,Colorado www.rocheconstructors.com 1 '{ Mtt.YC { "t & i) Y ,j ,•w.r�_f sF .> _ .:til ;'^/ hr . v �'� -F uran�.. ...Midi ' 'Zl:K,T-{.a� L'y,' \j12xcavati\ ;PROJECT LOGS JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS • N`, -L 8 A NOON CAM z-2-, \\ \ L•• u ti (,° -Ce1a c!A V\� EM•L•YEESANI CLASSIFICATI•N FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP* PHASE*CATA CLASS HRS. EQUIP* START/FINISH 1-,AN-1O (C �VJF 'j `, ').�-G`D 1-.../ P-te\rn or P'n1Pc) ✓! 2_'.015-4-1) L 7[an X30 t BACK CHP GES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED \\(e- --- DESCRIPTION: / �� a (/�...s 7tAl j am+(/a3-_'.; �T,/ -11 4-'9"/ , / W:, 41.:1--f/ .r ) `!4.C.'z%s j-I r I /,C'•as/Y, ,mss is , I o Src-k ;,; ! /Lf <.7 O.; 1 4 fCbW / /O H..Cc, t. C-47-L✓ EQUIPMENT UNIT; HOURS LABOR OTHER 7 L v . .J /Tx- 3 • CHECK HERE IF REGULAR RESIDENT INSPECT WAS ON THE JOB THIS DATE 03 NAMES OF OTHER INSPECTORS.REPRESEN S OF 0 ER.ARCH/ENGR{� OR�D�E�VISITING PROJECT - TYPE OF INSP TIME i T"i i l. �TY'F SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE.STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK I TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER I L4 1001 ' E'/ :!Roche Greeley,Colorado Las Vegas, Nevada Westminster, Colorado :E \:� Constructors.Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors.Inc. 1-29-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate footer for cells from 2 to I and A.0 to H frost I.5ft thick stock pile frozen material and haul oft to county pit AWA 067 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&1 Total Hrs. Hrs. Rate Raw Labor subtotal $2054:9 Cost Code Material Req. Quan. Unit Sub Tax Total Total v i '�7�C I. f m "j• __ Material Subtotal -41*, Cost Code Tools or Equip. NO. Rate Rental Period Total Tools 8 Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN iii)._\,, Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL 0 Yes of dayis) Owner/Sub Rep PROFIT( %) TOTAL r r m.. t ti- i egir, office(970)356-3611 Fax(970)356-3619 Denser Metro(303)534-3716 361 7P`Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rochecontuctors.com �• - - i5. t,.r r 7 �',.0 rim vC ♦ s,fr e`z�, h Yran 5f '---\\ e -•PROJECT LOGS xcavating 1� JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS -1'L4J9` / 8 AM NOON 0 AM -2,Z-a, 1\ 6-1 \-c057-M NARIA1 \° a.s° CI-INA L? EMPLOYEES ANIVLABSIFICATION FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIPS START/FINISH hU;-r, rc- (_=, , ,:NI t . '--A--;-4-,e L, 1�-3.BC) 3 sc : . 12 60--W A R'': ', " �sG 0 .2:2.-‘,-,-(--C) 0 -Ne)3 r•-: ! ' 3 c:'ym-<--n L� i" - 17190- ) - - t', ^c,c_ -..-, (); ^ ..,c(, ? _ �.`-.--t- ^. I-- , ..- 1200 -33') F-::;- :-c..--`-e ( - s =-'D`- ' ) "CD.45 il<2b 11.06-3 BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED -L •-r DESCRIPTION: ,/- /Cj// 6 I n / �, c' rg// (.c_IC c�/ g.r n4„, L ,L ', 71 _ 1c,�� W .L-'r'LL -L ,�-rr�" "yyJ. e�4 7&--Z� /11d7,12, vi \_7L^ \ 4 .7 .-- EQUIPMENT UNIT J HOURS LABOR OTHER / -/c-- n roA. j/-'-,/3 3 �flfiOe-2 4. -Ud Y'rj /1,-.:i,^,v-t',zc< T- G L/, S iz..-, -..; ,,,, pr 4 peAt.c7 CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE mc/L IJn_de/4/ NAMES OF OTHER INSPECTORS. REPRESENTATIVES OF OWNER.ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE.STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LGI 30-1001 / 3 '' Greeley, Colorado Las Vegas, Nevada Westminster Colorado �. Roche y 9 's _. �., constructors.ins ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-1-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate footer for cells from 1 to 5.7 and A.0 to H frost I.5ft thick stock pile frozen material and haul off to county pit AWA 074 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O. O.T. Total PTE.( Total Hrs. Hrs. Rate Row Labor subtotal $7115.00 Cost Code Material Req. Quan. Unit Sub Tax Total Total I Material Subtotal :- Cost Code Tools or Equip. NO. Rate Rental Period Total 1 Tools& Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal c),,v,....„ SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of doy(s) Owner/Sub Rep PROFIT( %) TOTAL r y ,- Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)539-3716 361 71't Avenue(80634) P Box 1727(80632) Greeley,Colorado www.rocheconstructors.com 'C.T1,7t 1 , • CoR -aR` IIuran\ Excava Inc. arch 30, 200/ Roche Constructors 361 71S`Ave Greeley Colorado 80634 Re: Weld County Jail Phase III Extra Cost on Snow Attn: Ryan Strub Dear Mr. Strub The following is a breakdown on the remaining cost to load and haul off frozen material from footing areas and removal of snow from job site. 02-5-2007 Excavate load and haul frozen soils also installed 1 load of crusher fines Crusher Fines 1 is x 77.00 = 77.00 Excavator 9 hrs x 125.00 = 1,125.00 Loader 9 hrs x 110.00 = 990.00 n,,,,A 1-l Truck 8 hrs x 58.00 = 464.00 Labor 9 hrs x 25.00 = 225.00 Sub Total 2,881.00 02-06-2007 Excavate load and haul frozen soils also removed snow. Excavator Snow Removal 2.5 hrs x 125.00 = 313.00 Off Road Truck Snow Removal 2.5 hrs x 95.00 = 238.00 Labor Snow Removal 2 hrs x 25.00 = 63.00 n,,,..),-. "�� Excavator Removed frozen material 5 hrs x 58.00 = 625.00 Truck haul off frozen soils 4 hrs x 25.00 = 232.00 Sub Total 1,470.00 418 N.9th Avenue • Greeley, Colorado 80631 (970)351-0192 02-07-2007 Excavate load and haul frozen soils, also remove snow and placel load of crusher fines. Crusher Fines 1 is x 83.00 = 83.00 Truck 1 hr x 58.00 = 58.00 Excavator 3 hrs x 125.00 = 325.00 Off Road Truck 3 hrs x 95.00 = 285.00 R,,,,� -t, 8� Labor Snow Removal 3 hrs x 25.00 = 63.00 Sub Total 864.00 2-8-2007 Excavate load and haul frozen soils, also install 1 loads of crusher fines. Crusher Fines 1 is x 78.00 = 78.00 Truck 1 hr x 58.00 = 58.00 Excavator 6 hrs x 125.00 = 750.00 aver. « a' Off Road Truck 6 hrs x 95.00 = 570.00 Labor 6 hrs x 25.00 = 150.00 Sub Total 1,606.00 02-09-2007 Excavate load and haul frozen soils, also install 4 loads of crusher fines. Crusher Fines 1 is x 298.00 = 298.00 Truck 2 hrs x 58.00 = 116.00 Excavator 2 hrs x 125.00 = 250.00 Off Road Truck 2 hrs x 95.00 = 190.00 `' - '° Ha Labor 2 hrs x 25.00 = 50.00 Sub Total 904.00 02-12-2007 Excavate load and haul frozen soils, also install 1 load of crusher fines. Crusher Fines 1 is x 79.00 = 79.00 =IQ Truck 1 hr x 58.00 = 58.00 Excavator 5 hrs x 125.00 = 625.00 °*'"a, Skid Steer 5 hrs x 95.00 = 475.00 Labor 3 hrs x 25.00 = 75.00 Sub Total 1,312.00 02-13-07 Excavate load and haul frozen soils. Excavator 3 hrs x 125.00 = 375.00 Loader 3 hrs x 110.00 = 330.00 Labor 3 hrs x 25.00 = 75.00 f '"-'4 4-S Sub Total 780.00 02-14-07 Excavate load and haul frozen soils. Excavator 8 hrs x 125.00 = 1,000.00 Loader 8 hrs x 110.00 = 880.00 ,.,,.,.- +'es`\ Off Road Truck 8 hrs x 125.00 = 760.00 Labor 8 hrs x 760.00 = 200.00 Sub Total 2,840.00 02-15-2007 Excavate load and haul frozen soils, also removed snow from area. Excavator 9 hrs x 125.00 = 1,125.00 Loader 9 hrs x 110.00 = 990.00 Skid Steer Snow Removal 1 hr x 95.00 = 95.00 ns--'" a t s Backhoe 1 hr x 95.00 = 95.00 Sub Total 2,305.00 2-16-2007 Excavate load and haul frozen soils. Excavator 5 hrs x 125.00 = 625.00 Off Toad Truck 5 hrs x 95.00 = 475.00 a\,n 4 91 Sub Total 1,100.00 2-19-2007 Excavate load and haul frozen soils. Excavator 3 hrs x 125.00 = 375.00 Labor 3 hrs x 25.00 = 75.00 q.,Ja+ -4 10 1 Sub Total 450.00 2-21-2007 Excavate load and haul frozen soils. Excavator 5 hrs x 125.00 = 625.00 Off road Truck 5 hrs x 25.00 = 475.00 pw> u ‘0,-) Sub Total 1,100.00 2-26-2007 Excavate load and haul frozen soils, also remove snow from behind retaining wall. Backhoe 5 hrs x 95.00 = 475.00 Loader 5 hrs x 110.00 = 550.00 Skid Steer Snow Removal 5 hrs x 95.00 = 475.00 Off Road Truck 5 hrs x 25.00 = 475.00 Labor 20 hrs x 45.00 = 500.00 Sub Total 2,475.00 Total 20,086.00 Markup 3,013.00 Grand Total $ 23,099.00 Sincerely Ernest E. Duran President Duran Excavating • • '®titan PROJECT LOGS • ®xeavating Inc. • • JOB NUMBER DATE I IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS MO N. - 8AM NOON 4AM 3Z3 '?.\�A O1 aR v i• 1 Z° LLD SU. V EM'L•YEES AN• CLASSIFICATION FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH \NV:Sq.7) wv,c,=W= H . •--).:_0(:)-cn L —13O--4—k , -)R-pl7 > \it\tip.`,)72_ -Pcri a1no>\ 0 r --ion--4,--g, c`,9,»J.11 i•-.R_ sCA, -' > 2f/ =2 ocn-(2:0 O q L—!It 1 C.,O-02O • C—a�\CAN c-1 Z r -2:2-15O- CD O at E..-S6-47_,- SO ?. tcc`Iwb Cc-C1,.G - 2.-≥ 07- 'DC I 7(Yl-u F',_ CD R ' —tY)— (<,� T'n ' ,S Tx2� 4srYr/-1 BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED q.3CtZF DESCRIPTION: Ic ort.cie/ ,.-47./ e.LC.J l20.CJr, /[.Ail {i '1Q1-(.C.. 7."-. �fC; / /YJt ulO 1. / r• rytG EQUIPMENT UNIT# HOURS LABOR OTHER 61.6 rGke C-.);'-I it, G9 7"291' ti 2 9 Ron i ,—Avuoj J'i, ,,,c.04 CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE ` NAMES OF OTHER INSPECTORS. REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP TIME PAT SN1--R1N SUBCONTRACTORS ON JOB SITE • . ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATNORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LGI 30'Ip01 r 3 ] ritk 1 6 m f gyp ' 4. � 4, 35, �Buckien ° , 1 ; � , .;Enterprises . v. , -,-� ,, e .�. I 804 NORTH 25th_ AVENUE ORDER It 33903 P O.# 323-26046-20 a' '�;- ee - GREELEY,COLORADO 80631 � _. ORDERED: 512007 {_ Phone(970)353-0720 ,- ACCOUNT R: DURAN E -+ Denver(303)823-8259 f � 'l j - TAKEN by:Mike ORDERED by (driver) - '.DURAN EXCAVATING, INC. - LOCATION: Jail 418 NORTH 9TH AVENUE • ,` `-GREELEY, CO 80631 - ss nc EQUIPMENT GRAVEL OTHER Si '.F. ITEM NO. ITEM DESCRIPTION - TRUCK -t CODE DATE UNIT EXTENDED . 'j' ( START SLOP DOWN NET GROSS TARE NET COST $AMOUNT t yea r . TIME TIME L TIME HOURS POUNDS POUNDS TONS EACH eFzm°, Wr GCCS /V 4 & !// Red PU t71A5�p7 72'.tb 53'300 ?.1000 14.60 50.00 $5.2E $7665 . { C :OB # 3 if :2__±,_) PHASE # ' n q PHA, E # `i RILE N.LP.F. NI,S R 0 _—a-__ HDID RE—. EIL ACCT # . E:tt@PLIE 1T # BY����=wl a TERMS: (Gravel-Delivery) Sudden Enterprises and employees assumes no liability for any damage to personal property when customer requests and directs truck I4.6G beyond curb line.Signed receipt of gravel admowtedges ownership and owner S76.65 attests hauling of same is a separate negotiated transaction between seller and avner. (Equipment Rental)Any alterations in the hours totaled on this invoice must be 14.60 Tons Delivered 0 50.00 /Ton WOO approved by Sudden Enterprises.One half hour lunch and any down time will be adjusted when verified. All invoices are due the 10th of the following month.By end of month,unpaid accounts are placed onICOD m De!Marr Charge Is 20.00 SALES TAX 40.00 and a 1 14%finance charge,which is an annual rate of 18%will be applied. Idle accounts,$1.00 rebilling /7 T T RDER 57645 charge and all reasonable attorney fees and court cost for collection If necessary. Paget oil 4-- Drivers signature r,--......Customers Signature BILING COPY RO!C�i Greeley,Colorado Las Vegas, Nevada Westminster,Colorado " Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: I Job Job to: Weld County/Roche Constructors,Inc. 2-5-07 f, Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate footer for cells from I to 5.7 along line A and A.0 frost I.5ft thick stock pile frozen material and haul off to county pit AWA 076 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT8.I Total Hrs. Hrs. Rate Raw L w Y Aviv, r a �ry ' }, SRC^^„terc.+�. Labor subtotal ....,,",_4,6 v Rx Cost Code Material Req. Quan. Unit Sub Tax Total Total �fi+ dir1t ' i 't.,'"/"-f,,-.:.; 1'1.1'.' t�y3 � RTMgT 9i+1K l 0lit: C,`a x -jr. Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools& Equip.Subtotal w° Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN tiliz___ Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL '1.(:''.14.1,'...,1,g Y office(970)356-3611 Fax(970)356-3619 Denver Iaetro(303)534 A 3716 361 "Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado rnve,.rocheconstructors.com Ors ` 1 ,cwt � 'Zv=whK Nam Erman ®xcavatin . PROJECT LOGS incJOB NUMBER 1 DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS T- `\��� 8AM NOON 4AM 2? 2- C n +A Z - r l 6 ,n0 EM•L•YEESAN. CLASSIFICA7I•N FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH 1,A2=. )7 yi, �. i Z10D-PICt o t �*ISd 2.7-00- (a 0 0 `-a C)e 43 -`l i yam . Z2�-&� L ,.4cS -- C. a�; ...1\ aV-�z 9 Z _2<-)- 6D L. 5/, " _2..t. , 0 >X F -x-13 -Tho-u 62or*_\r_o ne m2c) 31 % - tt l..e ../c — - tZea-60 I, 5 — 7ec ', / / `ii, no-cn I- / ),c- ----_... 1^oLc`5 PRQ _t•>--b eA )-a73-Cf. Z5 4 V-1-1,,1 Z\ DD ctrl TO "( ,S I'k•Z1 oo-t1� c'-.3-7r-.'.)c-,Z._ C;:j..,v:: ra\ `7 -,..5_ v;> lJ '5 „r4r+'J ana). -6'Ccm 1.. �t r,-.1 _24 z r_x)-6o 1ti\>, `A, -a?on,-CS 7t) ---C -k-246 7i)6-Lna BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED Ta.O' Li r;, DESCRIPTION: ? ,Q - / ,� l G.�/m-t�l�rl(���) {-in.�I Le .l GCf/ fjC� � � Ari "l" / (,4171--"r ./et) /17°77,4°4-- .C /' .re X //♦ Ji ♦•T �zEQUIPMENT (� UNIT# HOURS LABOR OTHER S�0I) Ce_•(�Uo t E CX,e_�� -2.NS c-.t-; )k,c) - \\.":',S.).L'CQ-.i( Y.___ T'C'- z,S _ . . A--. .'v >? <� Ii,AD F,t.� a,1"1SSCC\ CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE IS; NAMES OF OTHER INSPECTORS.REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME P�Z.�\:::,.:(Z.',).) SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING I OTHER LSI 00-'00' "olti troche _ - Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-6-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate footer 5.3 and 5.7 from A.0 to G+/- frost 1.5ft thick stock pile frozen material and haul off to county pit also remove snow from north side of bank north of line 1 for backfill operations and installation of gravel. AWA 077 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw titit ,? ,�s 8 a ^t4 4t n 9w iat 1: w ' a4J�y 11 r 11 .a `r e .�ftY,xFs a{',..d � �wee.,(rv; g'€�f a, Labor subtotal „� +•4 r, ^"�a•Tui: Cost Code Material Req. Quan. Unit Sub Tax Total Total jQ4.. ���1 ItiiJ f} 1 !I d 4 Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools& Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL rJ ' Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361]t"avenue(80634) P.O.Pox 1727(80632) Greeley,Colorado wrnv.rocheconshuRors.com PROJECT LOGS >';P xcNillir;\ d JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS WtL{-��. 8AM NOON I 4AM -7.-1 • LARR4 :III 2,I-r° L-tO eloc, EM•L•YEESAN• C •SSIFICNI rN FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH L.R F hp 0 1�'\AFC\ - 9 aAno-qc1 O `p L'r-?n "):750--,-ID Z---) (:u -O0- 430 Rnciakr0 C e_e,r,,c,n q zAno-q9 1- � 27 so-Lin . 1n6- y'C? N ,ca S x w.,, 7 inn-q�► -7.0 ,3 t z7 2Zt-(0,5 tk-11 107'' --I/\0- 4/36 if-ei- _ CCzC�� C\_ )-1_50-k0 --7.. S 17.1,C:',_ --I * -a o �n T X � TV2.h Oo0- y3o BACK CHARGES - LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED I R L `c. DESCRIPTION: / X�eM'LLJUe ao'Z74, Q-[A) / .GJ'?? J../ : . — ' ;��iC f 6/Yt27 /0,-. - �// 1 !{ / p / �' J-_rr. lilr, 2„K_ �'.. :,._- ;;7 .%../ -te 3 J�T -TACT `. 8222 -7.e _. i i �areCi. u"t a /(7.l✓,t_• �7 T.La , ` V\J EQUIPMENT UNIT# HOURS LABOR OTHER T-\ - z, ,_ -.c,.. -3'_ 3 \-\R.uLTRi.,cr<- Tic-r7 3 a ROD\R(co c:__*-cn CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE 9 NAMES OF OTHER INSPECTORS.REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME P QT $UC:R'.t\1 SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LGI 30-1001 n n Sir+ ; �,y h in< t r¢ y •. n � • 6 Bucklen �.% 4� c't �1>�� � #; Enterprises 'r v 804 NORTH 25th AVENUE ORDER# 33911 1 P 0# 323_9001 y- K a_ 1.7"1"„ . GREELEY,COLORADO 80631 ORDERED: 217/2007 Phone(970)353-0720 ACCOUNT#: DURAN E Denver(303)623-8259 - TAKEN by:Robin ORDERED by aonn T� DURAN EXCAVATING, INC. LOCATION: )AIL 418 NORTH 9Th AVENUE 0 STREET GREELEY, CO 80631 • EQUIPMENT GRAVEL OTHER ITEM NO. ITEM DESCRIPTION TRUCK DATE UNIT EXTENDED CODE COST $AMOUNT START STOP DOWN NET GROSS TARE NET TIME TIME L TIME HOURS POUNDS POUNDS TONS EACH GCCB -tlusned Con. 5ase PU 02437,07 7:56 55480 24300( 15.74 40.00 yy3,2= 32.53 IOB # 1 PHASE # 9017 J ?nd PHASE # V.I.T.F _N. .P.F. 41,S, R 0 M f_ • TOLD F ET. 3/L ACCT # :QUIRNENT # • ,1PPROVEg [3Y �ltyJ TERMS: (Gravel-Delivery) Sudden Enterprises and employees assumes no liability ror any damage to personal property when customer requests and directs truck 13/4 SE2.63 beyond curb line.Signed receipt of gravel acknowledges ownership and owner attests hauling of same is a separate negotiated transaction between seller and owner. Tons Delivered Iron (Equipment Rental)Any alterations in the hours totaled on this invoice must be 15.143 t(�,pp S8S10 approved by Bucklen Enterprises.One half hour lunch and any down time will be adjusted when verified. n, 9SALES TAX MlCOD Delivery Chs a is 50.00 1040 All invoices are due the 10th of the following month.By end of month,unpaid accounts are placed on COD and a 1 'A%finance charge,which is an annual rate of 18%will be applied. /TO ORDER SE'td] Idle accounts,$1.00 rebating charge and all reasonable attorney fees and court cost for collection if necessary. C Page 1 of 1 �- Drivers Signature Customers Signature RILING COPY Roche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-7-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate footer 5.3 and 5.7 from A.0 to G+/- frost 1.5ft thick stock pile frozen material and haul off to county pit also remove snow from north side of bank north of line 1 for backfill operations and installation of gravel. AWA 082 Duran Exc. - Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw y 4. Eci, ,vk �, i,q , .- 53,: Labor subtotal 4Yta:A.)F t�> M Cost Code Material Req. Quan. Unit Sub Tax Total t Total s^ ,cam ( " 'i' w it gc _1 5 Material Subtotal +; ' . w', Yx w Cost Code Tools or Equip. NO. Rate Rental Period Total Tools& Equip.Subtotal °t Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of dayls) Owner/Sub Rep PROFIT( %) TOTAL der"t{ 1 r r 4 c 6 F¢5 Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71"Avenue(80634) F.O.Box 1727(80632) Greeley,Colorado www.rocheconstructors.com r IIIII � PROJECT LOGS = excavating Inc. JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS II-VAS. c.--z_— 6 A NOON 4AM 3z3 a1 g10 4.A R‘A Sk.iN\ 1; 46 ctn.-I. Ili\ Fd EM•L•YEESAN. CLASSIFICPLI•N FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP it START/FINISH FAi AN CRAz 7.1O-ko 0 -saf r-k-3R 24 no-q4 0 2 r--k- -7nn-y—o IJ1Cr7C.. ...S ARREct`+! ' z--is() - RO TZ 7 -1-1<-2.1 2tOp cH I 16 Xi a6 -7nra-U30 7---(-N,7 ARRc-r-OAitO 2'100-4,0 I,. " 2ato 1n L '< — 1c]`)-1-{-aL7 F\3OPA n OC(mr\P0 '"4/ i 1SO-4o L I — --)CXo-4t --FERIAP IQ» �E q R 2.-150-I-10 - 26 D-2b L 3 `ova-‘I1'.0 BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED 1"oL-.N1- DESCRIPTION: J - / /7,71 i r2>c!7 `: '' r— /7 7 EQUIPMENT v 7 UNIT# HOURS LABOR OTHER \-q.;,_,.. l.. TRLA_A i K--).i Cc, h '.1>�, -'R!J.CIfN ric- D Co 4 hn�a�r a\ewe,/o PItttY,Nidsx, J,l hIA CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE NAMES OF OTHER INSPECTORS,REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME PAT sH 41AN SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LG130-1001 t • yF` Enterprises. -: 1 • F �ti+ -� x 804 NORTH 25th AVENUE ORDER# 33933 '. P,O.# 323-9001 GREELEX COLORADO 80631 3, ORDERED: 2/8/2007 Phone(970)353-0720 ACCOUNT it: DURAN E I Denver(303) 623-8259 TAKEN by:Robin ORDERED by DURAN EXCAVATING, INC. - LOCATION: JAIL 418 NORTH 9TH AVENUE - 0 ST GREELEY, CO 80631 EQUIPMENT GRAVEL OTHER ITEM NO. ITEM DESCRIPTION TRCUCK DATE UNIT EXTENDED ODE START STOP DOWN NET GROSS TARE NET COST $AMOUNT TIME TIME L TIME HOURS POUNDS POUNDS TONS EACH GC 'Ciusned Con. Base pU 02,08,D7 8:38 63903 24000 14 - O. $5.25 $78.48 /-tj / ICS # 1 PHASE# 512a 2nd PHASE"#` _ . .Lf. N.1.F.F{ y, 3.R,p H)1D RE' .. ,ACCT . FDIPTgF.i1T# . AEP YCVED Bat '- TERMS: (Gravel-Delivery) Bucklen Enterprises and employees assumes no liability for - -],7 any damage to personal property when customer requests and directs truck / 1495 beyond curb line.Signed receipt of gravel acknowledges ownership and owner 578.48 attests hauling of same is a separate negotiated transaction between seller and owner. (Equipment Rental)Any alterations in the hours totaled on this invoice must be ]q95 Tons Delivered® =0.00 /Ton SC.00 approved by Sudden Enterprises.One half hour lunch and any down time will be adjusted when yenned. in All invoices are due the 10th of the following month.By end of month,unpaid accounts are placed on ICOD m Delivery Charge 1^e S0.00 SALES TAX 50.00 and a 1½%finance charge,which is anannual rate of 18%will be applied. Idle accounts,51.00 rebillin char n l TOTAL ORDER VS 4'a 9 99' all ea able attorney fees and court cost for collection If necessary. Page 1 of 1 t- % Dnvers Signature ,` Customers Signature BILING COPY • AltRoche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-8-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe remove frozen material from side of bank north of line I for backfill operations and installation of gravel. AWA 084 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw kwaa x 4* 'v1 �k Y it 4 z Igt. + 4..,s J Labor subtotal 4,45,5 Cost Code Material Req. Quan. Unit Sub Tax Total Total ' sue, t 5 '.441:114-4,,...;),..1)741- 4114 -4 ' ' tip . Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(sl Owner/Sub Rep PROFIT( %) TOTAL 44o-x w. cte �4. 3 yT. Office(970)356-3611 Fax(9]0J 356-3619 Denver Metro(303)534-3716 361]1"Avenue(80634) P.O.Bax 1727(80632) Greeley,Colorado wvvccr0Checonshuctars.tom "pG PROJECT LOGS '=xcauranvating Inc. fte JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS V'R1, Z 8 AM NOON 4 AM ' keatt. ., n 12.° C LOCA.0LY EMPLOYEES AND CLASSIFICATIO FULL NAME HRS. PHASE 8.CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH 4.aRF- rize) MAQ\ME249 2-150-�10 l_ --- — --2.-)-c>o--ID o '--a C-4D 1(Y\- 43O FRRIP.DI CRua_ 2_10O--qq 0 tx -2:73R � -140O -3 C ioo—Li3O ---.-z-400-65 C - J N'c \ 5 ARRT-mlOcLX 2100- ct T , T1ic27 22_c0-LS To,-7 -1 r,- i-I-D1b Rnfla.\cc , OcKwo 21(-)(5--°1 t- 2-tc-b 14Q 1- -IOC) -y30 FFsm PA.t�r) [ Elm A -xi 50-'•-iD t-- 2.7_06-Gs 1- /y 1001130 BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED F,OCI,F DESCRIPTION: ", 1 /,� yy,!3P/ .Qi/r'!�-L/Gr.•Y„P.G 1 Cr /�'✓/ / --`_ CPYL 9 L-4#7,...11 ci F �i 4. -„_at: n l c-, 44 ..n, • /,/Aaz 3&ns R L 5:9d c. c / EQUIPMENT UNIT# HOURS LABOR OTHER EXC. P )N,OS)-- P' --IS 2 H NJ L-c?LICk. T.27 2. Du nw P 7- R u,c K T -2h LI- L CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE 1.11 P AT NAMES OF OTHER INSPECTORS,REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME PR-t- cgs-sin) SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER - - .._.. LG130-1001 F �! �s tM1i' !4- {lo . kb mt i n� i PX il ! 4'1. n, ,:lF y 1 . .rIt s N '1' vYki: `"n ,co- ,:- 1,4,,,,:22.4-A.'ra;. St: �� .i 3 - Bucklen cs h ;r , / it , ,. j - Enterprises , *. ,. x m �E � 804 NORTH 25th AVENUE ."--4F-4, ORDER k 33964/ P.0.4 323-9001 .5g q"'tj I GREELEY,,COLORADO 80631 - - '^�,44r ORDERED:.2/12/2007 Phone(970)353-0720 ' -._ACCOUNT if: DURAN E . IDenver(303)623-8259 -: - 1 TAKEN by:Robin ORDERED by a`"' DURAN EXCAVATING, INC. LOCATION: Jail *• 419 NORTH 97H AVENUE '# GREELEY, CO 80631 - :-.._;..•...,,.....•,..-.yam-..."-,. �..... . ., i 4' EQUIPMENT 147,;37...-..n. An" GRAVEL .,. OTHER : ITEM NO. ITEM DESCRIPTION A01( DATE ` ' '- UNIT EXTENDED START STOP L DOWN NET GROSS TARE NET COST $AMOUNT TIME TIME TIME HOURS POUNDS POUNDS TONS EACH GCCB Cllisfled Con. Base PU 0209A7 7'57 ` - 50800 :24000 13.40 10.00 15.25 170.35 GC .. Crushed Con. Ease PU 02C9rC17 8:23 ; +;. 54000 24000 15.00 10.00 15.25 /78.75 GCE • Crushed Con. Base PU 0209,07 8:49 53100 2WOC 11,55 10.00 15.25 676.38 el a GCCB Crushed Con. Base PU 02109.V7 W25 51800 24000 .13.90 10,00 15.25 $72.97 JOB # 'a3 PHASE# `FfOo t til ' 3/411i1W j 041‘2,,,5_ 2id PHASED ,; ft B.IJ.E ,Nk Fi, A.• i h, 5 R,O _•M � � HO.D RET til, u GIL ACCT # ;r ENIPMFNT # .., r _ ._ , r AP,ROVE) BY Ii TERMS: (Gravel-Delivery) Sudden Enterprises and employees assumes no liability for any damage to personal property when customer requests and directs truck 36.85 1298.45 beyond curb line.Signed receipt of gravel acknowledges ownership and owner attests hauling of same is a separate negotiated transaction between seller and owner. (Equipment Rental)Any alterations in the hours totaled on this invoice must be 56.13 Tons Delivered® 50.00 /Ton 10.00 approved by Sudden Enterprises.One half hour lunch and any down time will be adjusted when verified. SALES TAX 10.00 All invoices are due the 10th of the following month.By end of month,unpaid accounts are placed om De1N ery Charge IS t0.00 n COD and a 1%%finance charge,which is an annual rate of 18%will be applied. TOTAL ORDER 1298 45 Idle accounts,$1.00 rebllling charge and all reasonable attorney fees and court cost for collection if necessary. Page 1 011 Drivers Signature Customers Signature BILING COPY alRoche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. . ADDITIONAL WORK AUTHORIZATION (Daily) Bill . Date: Job Job to: Weld County/Roche Constructors,Inc. 2-9-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe remove frozen material from side of bank north of line 1 for backfill operations and installation of gravel.Also crushed concrete at north end of footings for north cells in Pod 8 AWA 088 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT8,1 Total Hrs. Hrs. Rate Raw k ° yy 4-1:,4;64:;r:m� ,H- Grp. m. "gg a Labor subtotals; Cost Code Material Req. Quan. Unit Sub Tax Total Total - m�i C. 4 ex{,� �. h 44 qf . "t6 " YM E 9i Material Subtotal •a .y Cost Code Tools or Equip. NO. Rate Rental Period {p Total Tools&Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL O Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL # ..rOffice(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71"Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado maay.racheconstructors.com °I((:) LLm� . ran PROJECT LOGS Ill MM.. , xeavating Ine. JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS /MONK 8 A NOON 4AM AA 32.3 )\ R•t1\'gi' • 31 k el r _ASU -EMPLQYEESANO CLASSIFIGATIOa _ _ ;»:; .• ; FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH 1,k01-'r) Mc-a\hi -1\I /6I owl-O\ 0 5 E -93 27 x-65 t ' -7(r-L13� Tr>\\,n1 ar)R,l; M---z - aoot-ol O -$5 SL-5`.. z ?L21-CAS O -<I U-1:2 "7(d W CViroz-s (RtzilmAV, eka:i-©1 L f3 — 7 z(z)-h5 7.0 rk27 7co-q31 \-.nRFN7(-) MaR'tNU ?too-G,5 0 al F-k-4 7u-d-y 1-. c:,or vnIASt. cos �c.-,:-;s �� 7S)c -L)%0 0 L-t-/A :Lc-(1S 4U L-L/6 i0:3-U3i .e-.vc,_‘.) eRu\z "O 215()-un b (y i in-6S a u'i: &3? -76()-1/X) Voa Rlcp cx.c=4.cc ch ✓a Z ?4)--1- ( t ' — ? - 'lri-I'c5 k iy — 7aa-c-/3�J ? L-vvc R-y�t�_a> WW ‘- 7 7._ =:,-)--z--(o L �S — 2 13)--:-,S L 4 - •7a-J-i-i d (LL-C-t§kCy's( 9/ c\fl J- \ -TX-) Th-`lb 7-OJ-C.,S l D "rS T- -2 . 7Z10 ) l',D 4112 1-1:f, Z-?5c.) -I-10 TO ./t ik�, BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT • NAME OF COMPANY BEING BACK CHARGED RC-C.-\3‘.[C: Ck ry" `_O\ DESCRIPTION: �J C�.1�-#i917� ,- '7,/E7•L c47? �1 .7 r-,'"f../. /1!I-, .r9 l ' c'�� L72 -/ ! .,-% 6: / . -Yrl!,>?1,/ Jam!' --A./40_, ://,c,-2 : , .,-• (Y A-%, cc_ i!y, / /j., . / Lc.-,o C. ,:isg.• ; c0 ...c- .i F EQUIPMENT UNIT# HOURS LABOR OTHER A/c w// -6L 5 .I:7,//74cT�i ->.k • J VM.P/tt --C-An V-.. C--i — 3 , c---y/j I'rtr"i/ i(42-) CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE al NAMES OF OTHER INSPECTORS,REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP TIME J SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE.STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LSI]0-1001 t� n " E",1$x, ,'I11^R r+" • :▪ xha s� ,. '� , , x7. r r rk ,. r: _; a • e Noryi� ,t w`teT-t: ` '' 441• J- ccse5' Bucklen ,k 't� 1 ter ,;, Enterprises • f kx * ' w• . 804 NORTH 25th AVENUE - '"'�ORDER# j j97 S.fx -;:P 0# 3 ��..� ._.�=- l�� GREELEY,COLORADO 80631 3Z3-9DU1 J;. ;: ORDERED: 2/12/2007 t+'_ i '.4 w y„ Phone(970)353-0720 ACCOUNT# DURAN E rt IDenver(303) 623-8259 TAKEN by:Robin 'ORDERED by DURAN EXCAVATING, INC. - .,LOCATION: Jail t . 418 NORTH 9TH AVENUE �''0 street - : GREELEY, CO 80631 • '-- EQUIPMENT • -• GRAVEL :-s OTHER , „ ITEM NO. ITEM DESCRIPTION CODE DATE c^ UNIT EXTENDED START STOP DOWN NET GROSS TARE NET ' " COST $AMOUNT TIME TIME L TIME HOURS POUNDS POUNDS TONS EACH GCCB C6lshedCon. Base PU 02/12A37 10:35 ::' 54140 21000 13.07 -W00 :5. 179.11 tJIB fir Arr> 4 , PHASE $ - 90 01 /bed PHASE `�" i M S R 0 k r - M .... DC� ET. S i G t. CC-#' C `-` • flill f NT # &i ."_d Re it'PROVED BY . it TERMS: (Gravel-Delivery) Budden Enterprises and employees assumes no liability for 1 any damage to personal property when customer requests and directs truck 13.07 - ' • 179.11 beyond curb line.Signed receipt of gravel acknowledges ownership and owner attests hauling of same is a separate negotiated transaction between seller and owner. Tons Delivered® i.l: • (Equipment Rental)Any alterations in the hours totaled on this invoice must be LID? 10,00 /Ton SO. T approved by Sudden Enterprises.One half hour lunch and any down time will • be adjusted when verified. miners=0alhary Charge 4. $po SALES TAX 30.00 All invoices are due the 10th of the following month.By end of month,unpaid accounts are placed on COD and a 1 Y%finance charge,which"an annual rate of 18%will be applied. n TOTAL ORDER 579.11 Idle accounts,$1.00 rebilling c rggeand reasonable a�tomey fees and court cost for collection if necessary. Page 1 o11 , �,-`—'�-7`-/`_--7,tI Drivers Signature Customers Signature BILING COPY N� Roche +Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-12-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe remove mud along north side of pod 8 for backfill operations and installation of gravel. AWA 090 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw T.fib` `y ` 6 u,ra r` i --I x x 5 � t. S° q *Pt1`d p4,3-`121sEitirelritjad.:ja; xt�M{y '1a' 1 t Labor subtotal Sw Cost Code Material Req. Quan. Unit Sub Tax Total Total 4 l ;_ ,t� wti Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal IPr, . Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL ° t ,. IV':# . „": Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71"Avenue(80634) P.O.Box 1727(80532) Greeley,Colorado wwm.recheconstructors com Ta i V NIM,::::\ 45OOV Oi4$) PROJECT LOGS®xca JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS TUTS, 41AM NOON 4AM ZZ_ -2-. \3 r a \A _;e ZU C o . S EM'LIYEES • . CLASSIFICAlI4■ FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH \,,lo4n linCe\w5) 2— -« 0 ',•• E 43 ztor- -C�() o -3 EX)-13 "1 c o- 93 ‘.�,a iza mc.„9: .F—/ q 2?cx>-(0S O q, EX-4.0 -r c e- Lill FIPO(l J FAL SAS vfl q/ ?..? ")-1-4C) O ,S kuc, ZzoO-CoS b � L- G —ioo — 420 Fcacilan4 Clain. �I -2:-)SD-1-1.0 O 2. Ck-38 ' loo-C25 o `5 ex-3s -inn_ god ZFv - L PC )RICO cLP \co Al 2?S)-k0 k — ')..ADO-(aS t_ ''zy -10n - y36 •N Ic1>o ws a ,Eno on 49 'l').OO-( S T 0, Al Tk-i6 100 - tRA, P L.Ix F1R0.L-cr)c\i A1 : zzoa-,S 1.. .,4 — 100- Y3o caZ%. i,on1 VE_a-ao I 22 o- 4,s O 9 =''h•-?' 100• Y30 FCRH .Mcy', Dr:.- c -1 z-7Sn-14o C `'. --- '".:,..)o-(0S fl - noo- t13n \i_. U P•.P.\{ '.)..co--6 S -f.D, TK--o -1 n° BACK CHARGES LIST MATERIAL,LABOR E.EQUIPMENT NAME OF COMPANY BEING BACK CHARGED� A� //f - /" DESCRIPTION: �IC 6 CI1 4?i/''`,`�7t/kir .dj,!�C, �4/YL/9--/t .7-ce 3 ' S EQUIPMENT UNIT it HOURS LABOR OTHER 5X4-4_07 FA-V3 3 Ace4cick -4 3 3 Aa,0/ C.cct47PD CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE NAMES OF OTHER INSPECTORS.REPRESENTATIVES OF OWNER.ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME PAT sHERIN SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATNORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER WI 30-1001 - S A tche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors, Inc. 2-13-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Excavate footers lines 3 to 5 frozen (frost 1'-6"to 2'-0" haul off frozen material blankets north side of line 1 on backfill. AWA 092 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Firs. Rate Raw ,; 41. f S#ftybw 4 . 1 5. 'h• i2.4,t 4 t s ' ._µi ^- Labor subtotal ;. O' Cost Code Material Req. Quan. Unit Sub Tax Total Total T ° 7T�x `„ 1 los 4g Material Subtotal r' Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL „4, Office(970)356-3611 Far(970)356-3619 Denver Metro(303)531-3716 361 71"Avenue(80634) P.0.Bo/1727(80632) Greeley,Colorado www.rochecanstructars.corn Nilltrim 1= A O f y PROJECT LOGS excavating Inc. JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS WEl)• 8AM NOON 4AM 2 W\ . ..V ik 70 C 0 EM•UYEES ANA CLASSIFIC•TUN FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH V 3'-/c) Mc-r-Wl'--tJ A �'a00-GAO 0EX-42) 1OD-336 Ntc r cAS t c c& `w)• ?-7-Y3-( ''') - -1421 10n- )--4.Cl Cr AtJ ? InthuF) ? -t--5 ! -100-33O r PR1 AN! CRtp. G VP‘c_F,Z tO IQ WL ArAjco OcA.r�T Co VP�;,-tAk) ' HPS. BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED R z^(4 DESCRIPTION: —�'. 1, / b,i4IOr, . 1� � �,.< San/3 '! C7 —‘ It s''o y s.ic L. e ( j '/ EQUIPMENT UNIT# HOURS LABOR OTHER /=XIrY.�1. ' Lei—'=,13 g =K _GE, /7 ' - ..' . G 7 C1 7 7 f.,: IYiaczAi/%EL CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE " NAMES OF OTHER INSPECTORS.REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP _ ,l L!C n,) F TIME Nr� �i(i / SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER Lei 30-1001 icAt Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors, Inc. 2-14-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Continue Excavate footers lines 3 to 5 frozen (frost 1'-6" to 2'-0" haul off frozen material blankets north side of line 1 on backfill. AWA 094 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rote O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw *-7' iwf3 6 '1iala n i; I M�4y 3z. L x Labor subtotal `r s"= Cost Code Material Req. Quan. Unit Sub Tax Total Total 5 1. t.. .. , L Material Subtotal fir f w' Cost Code Tools or Equip. NO. Rate Rental Period Total Tools& Equip.Subtotal `-" 55 1fh' Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %( Calendar day extension 0 No SUBTOTAL 0 Yes of day(s) Owner/Sub Rep PROFIT( %( TOTAL +ux a Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-371G 361 71'Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rccheconstructors corn \II Dann _. '� ©16 PROJECT LOGS raxcavating Inc, JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS 7-t-,‘,,,?..-1, ` :AM NOON 4AM 3z3 -2\,\s\Di I,IaRa4ou9:\ 'A ° -Zo ur,.v EM•L•YEESANI CLASSIFICATION FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS FIRS. EQUIP# START/FINISH , "ai, ,C�v. ' . 2'.• _ r L _ �-- ,• i 71-- '�. - 0 L 3 -•---- 2'LDo- it, • 7 _•- C -, oa -> •- 1 -C6o pD 1. 1 • - - +�, .. �q (0o. a o _ 13 22 o-°S L - 100- • 1C' r F., --►, . t...:.-cc ' . I r. - ta-os -ccc „2 10 - �� P 1/ c•.r- F -7 1 -.'q' — Z .s►—Co L `4 — 1 oc)- H c RIICa ;'=r ' r:.• 2', -A! \ — BACK CHARGES `\ LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED ROCsAE DESCRIPTION: ;l �Lc,� / �,[ 'rr t r��/ fee 4,94 rr��/o,c �- t �(lQ//r an c-e. Sk2 a -A ?. I? 4. ,yid 1 "sr iz Z'n //lam 5tiR "eft, i .Crr A7 /41 ii t€ fry /( t, S 7th, � r,D 3 C �l i '-/ i Li / ✓' ii+ /�L l7 ,.mac.--J21 . ,` -�, J /'..r, 'C_C�.>� /r?i i/' ,,. A`%!.‘c—f.-17. ,glfn EQUIPMENT UNIT# HOURS LABOR OTHER r\P.1/4. s sL-Sl 1 Lf XAPOk Silk-5A ktila14k ic-k1/4<1/4.1.,1/41:e~_IA -'L=!3 q % 'f.i f7 3-4,4 CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE ISA NAMES OF OTHER INSPECTORS. REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP TIME Paz %IAERIN SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LGI]0.IWl - r c '' M® Roche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-15-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Continue Excavate footers lines 3 to 5 and H to 14.3 frozen (frost 1'-6"to 2'-0") haul off frozen material blankets north side of line 1 and haul out snow!. AWA 095 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw **71:44;84.4 xir F.iii, rRgg2"..` --: s 8 1 4 i5+T�Y A.. + F . SY AEk.. , Labor subtotal - �. Cost Code Material Req. Quan. Unit Sub Tax Total Total ,' -.;..A. k h '' V 7 ��yyf 5�1S,Jt A uS d Y Material Subtotal ",ii Alit. Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal 1. uh Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL } 7 _ Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)S34-3716 361 7Y'Avenue(80634) P 0.Box 1727(80632) Greeley,Colorado vo w.rocheconstructors.com 4 C4.9 ./I / �/ / ji/ / I ®uran /h-,y _ - k Fr1', '� PROJECT LOGS 0 xcavating Inc. JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS -F RA. Z. 8AM NOON IAM Z \�),b \ LAaRk �UaAN ,I° 440 W1NC3� nV\�i I D EMPLOYEES AND CLASSIFICA(ION FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP/0 PHASE#CATA CLASS HRS. EQUIP# START/FINISH L\n'D MC C--w6M "d43 t?-80-Co0 0 ''/ Ek-4? 72on-Gs I- /3 — 1pp- 33n L N C*REzc) MectiVEL e '�kkoo-2D L - — 22 ct CAS L — 'le0�a PkoctuPa cc wa�a .£ Z1sU-Ikn C5 L-41, Z2ee-6S O 1. L, 100.3 z oo -r m6 a�IP,N c Diaz .�� ?D \ nSO- '-� FYI,$ '� -ZO L. —• l0O-'-)2,n Rac Rtcn c = PrrPo I tis -4:o L. Z-%- . L f„-'k�.� aR�rt-y on "tthn-(„t> TT), JS 'TY.71 ?7 j- S t.. ✓3 -- 100-.2,?,() P Aar , r_Frir-ii:notO -,-)so -I-1() L 4 7-zoo-cos L u`. 1Uo-"?,3(l TCk Czoc`,R\E�/\c7 / 7-Inn-60 L 5 - -z.-,nn-Gs L 3 - 7W- 33r raRsrie nu t�>C=_r-,r-.tc-, Z�SLR- uo L 3,( -- zzoo-r,5 I.. - I 760-`330 c'_r�1-tL.nJTy rttlr-,n') a '115,10-y0 L. v, _- z�ao-<9 -7;30E)-7� I-. 700-N;5, BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED P.OC:�C DESCRIPTION:p //n�/./ �-"7 d Warn .!v O /Y�?d 7d O'.Z� /7 TO Z. "2-Lf{/3"/A 42//c.xlr!/L . 9iYr-z2.'P a Mei&,vYit .-re/ c'7't f'r/a,rr. � ba 1O7.4"/ ..2 t ,-nc a't' , ,. :�,L e.r' . )4-c"/ 'fv e_ L EQUIPMENT UNIT# HOURS LABOR OTHER LcxK-?, /AToR G-x-U3 5 /-/A(JA rRjck -7-g-27 5 5 3ofki Ro RI(,I,IZ Z FEADVAe/,tk)(Aplo..o)0 CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE UO NAMES OF OTHER INSPECTORS,REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME Rcr SPFRIN SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LGI 30-100i _Roche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-16-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Continue Excavate footers frozen(frost t'-6"to 2'-0") haul off frozen material blankets north side of line 1 and haul out snow!. AWA 099 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw c YV. r 't n ° 'OM r>,.. Labor subtotal Mt Cost Code Material Req. Quan. Unit Sub Tax Total Total .4411,4 41., 'a��a`B!'r�'~^s s$ u it �� Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal 1 `11 '„.y t Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(sl Owner/Sub Rep PROFIT( %) TOTAL .x `' n'z drrr` rW 4C6yy.. 5 ; Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)5343716 361 A`Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado mvw.rochecanstructors.mm rpta eSvT,'r4 SA 1L • 'ruran l a 1On �•� PROJECT LOGS _ xcavating Inc. JOB NUMBER DATE IN CHARGE TEMPERATURE YO.N- GENERAL WEATHER CONDITIONS BAM NOON 4AM v a C\ . & Rfl I *C\\ -n� C) g V\ EMPLOYEES AND CLASSIFICM 1OU FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH L\TiR CRc E vAr L i 1 2t nD-(r{') b --3 kej4 ZZDDI6S L ` -(.O -1 D,')-L2,1) ,SiiiVtl4 , z-2.Qo-(0s L.--6 -ton-utp Nlc a RF�1'NVIV -ti 'ZZJU-row, T.o.- TK2i I CO-4_3(-) G_ -- .. y r.c,cCir>t)cD -. "Z 1 -4O I-.. "r - -).:.OD-6s L. - S - -1;)o-I-1 yl f.`_,-y 7)r( DEL(cC 9 2l,�-CAS O '-C 8,4-0 too-�S k t--- — 7 . FER14F1r1ftoE1.hPbC5'� 2.�A-4 L14'0 D z�.-�xr�S k �-S - 1.ya-14-)C3 Fc\R i F,I‘I cRu-z --Cr 275n-q t-, C) - r Eke ,-." o-(-z c z--2=; F.x-u() 1OO-q SL h1:z, 2iSo-4(l tc II.S rk-? X0-4 3c7 BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED Jl^ L\ . DESCRIPTION: 1 S X47 _ hr Olt 5: 7 .6/7C-7? - aZial()-7 , 0 f �• EQUIPMENT UNIT# HOURS LABOR L v � OTHER /� a .ys 3 ._ / 3 /JA/4-/011e/G/.IFL CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE.a NAMES OF OTHER INSPECTORS,REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME PAT SHE-a\N SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LGI 30-1001 Roche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. _ 2-19-07 Name:WELD JAIL PHASE Ill No.: 0615 Specifically describe Continue Excavate footers at Vestibule 100 frozen (frost 1'-6"to 7-0") haul off frozen material (3hrs 4/-) AWA 101 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw E � - . r_a•:A/,,a1 ,rte • y _ i 55 • Y ?.� Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax T.t.l Total s s` . Material Subtotal . Cost Code Tools or Equip. NO. Rate Rental Period Total Tools& Equip.Subtotal r l Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RC!Rep OVERHEAD( %) Calendar doy extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL 7,=v, a� 4� ti �� Office(970)356.3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71`t Avenue(60634) P.O.Box 1727(80632) Greeley,Colorado www.rocheconstructors.corn 'luran ilk)l "A�� PROJECT LOGS '®xeavating Inc. C r i I C!;?"a, JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS Wen, Z. 8AM NOON 4AM a VZ_A\o I.RA-u ci& c l 2-\ '--t5° - LA'Ar,tl EMPLOYEES AND.CLASSIFICATION • FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP# START/FINISH A/1,-1 I77 ,LE AI 1— 2),n -G,t 6 ? ??no-6S t-_ H - "10011 :1(144 du '- r,a K=u z -Gt 2=0,t- S L 1 CO-L-1 N'c.:..4 c F , 1,:CC ?"2 Cry-CcD .�, ':- --.. zzoc>-6S l -- -1 o0-u^il) PI -z,• '> pt: >vul73 Z? D7-CoS h r16-Lk -,_;_, - -[10 uP< z.zno-GS _ 0 b:-14C) 2? ON- S L L . 1 — 7 On-1430 F•cf; '_=-;i. '/ l7,C/?:47"? z' nO-GS L. `i ©-1-1 C&�Ki' rI 131Cnr?S ?? -C.,C-) (') 9 Sk51 7 n()-yid Oi_, .; m , ,r. Zzoo-Gs ' 1ne-r-Pe Ni --- =,... 166,7,' -7_4mot¢ ??,y-GS 0 '-4 I'-3S BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED RocHE DESCRIPTION: ..� CS >,r�/�/n .. i-- /'V 3 j--402-77 S. 7 awl _.., -7 ./a2 ,.../ ' Ce., -. x, air,9 t'. -2. ice_- / / r✓ Q T OO EQUIPMENT UNIT# HOURS LABOR OTHER A -��r7C/A AX y3 .5 /4 !f y4/ X T=:-.27 5 CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE la NAMES OF OTHER INSPECTORS,REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP. TIME PAT SdFR\r'l SUBCONTRACTORS ON JOB SITE _ ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LGF 30.1001 RktRoche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Dote: Job Job to: Weld County/Roche Constructors,Inc. 2-21-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Continue Excavate footers rooms 138 to 6-101 haul off frozen material (3hrs+/-) AWA 104 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Firs. Rate Raw I • 'IYE f Labor subtotal :zT Cost Code Material Req. ` Quan. Unit Sub Tax Total Total a�.Fc iJ 4,Qf' � Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal . i ' Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL _. gpol ';`r .£ L •A• Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)5111-3716 361 71'Avenue(80634) P.O.fox 1727(80632) Greeley,Colorado wvu.ro[heconstnutors.c0m i_iran �� �P ,s 1®xeavating PROJECT LOGS Inc. JOB NUMBER DATE IN CHARGE TEMPERATURE GENERAL WEATHER CONDITIONS NI:MN. 8AM NOON 4AM 32. 2\-x.\0 1\P,QR( 01R4\\ G° by EM•L.YEESAN• CLASSIFIC•THN FULL NAME HRS. PHASE&CATA CLASS HRS. EQUIP# PHASE#CATA CLASS HRS. EQUIP if START/FINISH l.b\'di o 'cn -wFN Q ZJOo-@ot c> g Ec4 7150-1-lib 0 4 tk-43 -ion- W a_Or1^,I 9,,ric uE-Z 4 --.tCnO-GG 0 LLfl floc?-COS 0 ' -I L-x-17 Zoo-'-136 NIIr,..,,-,,e-SF•FCF.,v,,,;-Th' fbo-GS o /el SL-SO Ioo-I-430 ic'i'-_::.< F CFSt1\I7-.1n S 2!m-q9 k — 2150-L.0 4- )1 — -too-l-t3o n': o.i o 3tcd , )-,)-.00-6 o Ja y- ���S !_ -t - 100 1k F c<h c vc-, t E FC',D 9 ,1)...,'U3 I-- 2 7-oo G5 I- �{ - -7 00-430 "7 == ':r Om-c 9 2 !oo-99 a ck-52, 22 m-e5 c .� S JCS- ,S - �vo-�!?� 17_7 ..��.�r S '0I 2 t 0o--1ct TO Ai( MI1 "Zl.00-GS Tr) -4 neil --/ DO-430 nL (ca'j SS 2.\0O-,°1 _ct •T1--b a aob-65 -12 S Mt, BACK CHARGES LIST MATERIAL,LABOR&EQUIPMENT NAME OF COMPANY BEING BACK CHARGED YNOCL vc: 1', 1 ' 1(3� !;'� DESCRIPTION: 7 j4 �, � r ti / / ' ,� _ /C '/cze: i ./ Old • ellI,Y-"� //1/,C.<_e..4C�l-l-fJ l. - 7�' 5izzzG- ��v,:7:G fj� 71/.. Z..--- ,,, ,/ Tr— --,c2 !=X-y3 <Pie Ae/Ta h 6 3 4 5 /.oAC)5 EQUIPMENT UNIT# HOURS LABOR OTHER --_-(n__6„.@6- 81/-35 5 s<It? A0ar_IZ 5/-S2 5 ;:')RC`rc'.. /-�7 5 i-iya: 71'i< C,,,, 7-X- 7 -s 'V/-JQ-4."z5 -S4/, CHECK HERE IF REGULAR RESIDENT INSPECTOR WAS ON THE JOB THIS DATE E NAMES OF OTHER INSPECTORS,REPRESENTATIVES OF OWNER,ARCH/ENGR OR DE VISITING PROJECT TYPE OF INSP TIME PAT S41 PN SUBCONTRACTORS ON JOB SITE ASPHALT SIGNAGE,STRIPING CONCRETE STRUCTURES SURVEYORS CONCRETE FLATWORK TRAFFIC CONTROL ELECTRICAL OTHER LANDSCAPING OTHER LGI 30-1001 R `1 91o1Vt..he Greeley,G,lorado Las Vegas,Nevada Westminster,Colorado '� Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-26-07 Nome:WELD JAIL PHASE III No.: 0615 Specifically describe Remove snow north of line L.5 (snow was stacked against shoring) . shoring was removed last weekend but snow needed to be removed to allow for backfill on L.5 AWA 105 Duran Exc. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I I Total Hrs. Hrs. Rate Raw ECTI '", w.. .y WitSkte . a're.' . 3"s i >- 4. Labor subtotal t: ! Cost Code Material Req. Quan. Unit Sub Tax Total Total Slitgrifiid �i 3� xq ?' e: Y mpg¢ > i 3 $a +naMT 5'0'8 ":1 >' -1.-' ' Material Subtotal r Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal lIttirr" Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED PROJECT LOG FROM DURAN Subcontractor Subtotal SUBTOTAL RCI Rep OVERHEAD( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL A. . 4 7,, Office(9%0)356-3611 Fax(970)356-3619 Denver Metro(303)539-3%36 361%1"avenue(80639) P.O.Box 1727(80632) Greeley,Colorado wwwch.roeconsTru<rors corn r t 05/15/2007 10: 23 9704828658 KIEFER CONCRETE PAGE 02 NINA # VIt Tf ✓GLC I.iVI 12 12.18.06 630 11 12.26.06 1195 11 12.26.06 1530 11 12.27.06 1400 11 12.27.06 790 17 01.02.07 230 19 12.28.06 1320 20 01.03.07 456 22 01.04.07 686 24 01.05.07 2314.5 37 01.08.07 585 40 01.11.07 1312.5 42 01.15.07 1027.5 43 01.16.07 757.5 46 01.18.07 333 49 01.19.07 1769.64 50 01.20.07 1753.5 53 01.22.07 1266 57 01.23.07 583 59 01.24.07 270 64 01.26.07 60 66 01.30.07 250 71 01.31.07 1480 75 02.01.07 250 80 02.05.07 427.5 81 02.06.07 905 86 02.07.07 170 87 02.09.07 212 89 02.12.07 65 96 02.13.07 191 97 02.15.07 760 98 02.16.07 350 102 02.20.07 745 110 02.22.07 396 111 02.26.07 220 112 02.28.07 240_ 117 03.09.07 255 118 03.12.07 204 124 03.23.07 1003 125 03.26.07 535 126 03.27.07 102 127 03.28.07 102 128 04.02.07 340 129 04.03.07 748 130 04.09.07 161.5 total 30,279.14 /, v0,14:1bsr" - lat%% Roche \vi G►sik iVy r Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors.Inc. 12-12-06 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Cover footing subgrade line 1 and L.5 evening of 12-11-06 and remove cover morning of 12-12-06 AWA 011 Kiefer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT8.1 Total Hrs. Hrs. Rate Raw l h'.t tl Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total Total Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools& Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW CnoP — anw,,C, ✓ t'7 - Subcontractor Subtotal SUBTOTAL V RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL vile ct Plae(9](1)356-3611 Fnx(970)355-361n 'T•nvcr Metro(303)531-3716 361 71"Avenue(80634) P 0 80,1727(80632) Greeley,Colorado we.r.rocheconstructars com f � -s" b a4 �k rIY r ,a-2✓; r • ^�' a •r� -0{ r . 'iii,,,:t.',,-„, F 13 �.C1 r �9 -a f x r "SK .V t Sr �y "".,1 NFi na r as A -- r' ,₹m t " �r"s ; 9 P''' n n a 1 i n a a M w1, .: o f j At't{ag�Ia o` a`�i t h i r v. .. y.tix * F x , z y r t 2 u s S ! 1 d ,:f•r r a sw.E y c.3 Au r5. F63' � _,�i'M`n 'iti" t^fi^" lsk L%"k. ,k 'l'-- e fiiP""F}L '5113 T '',91t,',,-;:`,[4,', ' ACY 9 c ,F o • r r� ' 9 1�'t�'�''. ,� tii �Y 'Y '� '4'.y. 'd d �{f 1�mM Lt141� � r�? "F�49` +� J/ •kr r 1 hq� F rd"^- ) �L a ff,rCj 4 w s ar OIL R'I r 1- .11;,;b:,1_gR��1, a ,�'F "Ssev. �.. .I TJ/�'A7 � Q1-- t".„11.,..•..• � .'F FG kneh"r �".S . y,@,'�*:11+J� T'r.M s .f 7.,k _/ /vn: (AA k t y h } FK.R N' v` nl g �y _.O/ ! # TRP+5 4,Ge•ef l ,4 sti a '�'l' o A ,2C r' , 2 — Ia (O I ,f ✓'tj... Q-tstC�p ar # �.. {�f4.1 Fn ,A .*IE 2r - P' m MII"x aFi Oil t r` tq a� � s �`}}Jafi `S�t.%n"'dJw4�p'jh• &get/non, 0 5Y Q 1110 'Y r �� y((; J Ab"r;:1 '41i4 r+r '� ,i.' 4 Atli 'y MIFi 6p'if xx r: 5 r lT ,'Se▪ F{r � '+c e r € G Y S t� as i p ° „PA-Ai.", � F 'yr 7 '+`t+ s��-t4k- e .tA enee > • q�.`a5 , r'- • }�pt ti. "C` n :3. re �'1 felnrn r1 6 ��"A t 4k '�`i 'kC'^ uY'�1f 'r 9,�{ 's R t(-.; - f.`�( r 6T' 0 9�"' E , •49, I tagski y� �Y ` ` � t ,t •• !,•,• { s. ciN r 44 ° Y y a nir y k• '0?),";;,-r- C '':;;',,'"-4',,' v • { �y,�$t d ! i Epp )," _ p s°� i N RFY !`a•r � ttA r119„•{ Y y ' pN x 1 rG}•E y}}} y ,Y4.',.‘;,'" M 3510-' Oil$ A CoiQthe Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Co.:a Inc. ADDITIONAL WORK AUTHORIZATION (Dally) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 12-I8-06 Name:WELD JAIL PHASE III No.: 0615 Specificolly describe Cover footing FORMS AND REMR lire I and L.5 and remove cover morning 12-12-06 thru I 2-15-06 AWA 012 Kiefer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate 0.T, O.T. Total PT&I Total Hrs. Hrs. Rafe Row Travis 7 L dr t I s �T . J - J J 1 �.Y 's t ; Greg 3 35 -t ; r N • George 3 1-/5 h tO"J 5:E C! Ryan _ __. ...... OuµE __j S 1 S 1 bar subtatal LAM) 2/i- 3o 75:Cost Code Material Req. Quan. Unit Sub • Tax Total T0101 rt s T . �1. Material Subtotal Wj:y'•:,;;�' Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ".:, Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW See attached list from Kiefer 12-11-06 thru 12-15- 06 kik( Subcontractor Subtotal 30 SUBTOTAL4/7 30 00 RCI Rep OVERHEAD(_%) Calendar day exten4on ❑ No SUBTOTAL ❑ Yes of dayls) Owner/Sub Rep PROFIT %) ET 39tid 3132lN00 elad3I>l 8998LRPR/S Flo .7.T /Par//T/TP �r� r ,, v*yi iIi_ F "iy f% '5Y* + '3 rd':::: F^ `'., ""' t¢A: -M I'Y / �1 .7-QJ�' (L¢GFt. y �4 �Y F•.lPq�t ,..,..\,!-:,;.,-..Y.-$:;,...-„.;, w " ya�; 1 1^�` *fie e au j � �- 'v r� �v,.. na iP�lUh'F. f;rx 9 x 4; 7( , 1,, + ,y ::1-'9:::.4):::,,IF • • < et 1,214• y 4 iv k -lit '' �¢ y1'I Y.aik Tart a . / ,,�...I,_ BJ. C '!"`6i tete7 —) w/L�/ y y t � A 'N% 4 :,₹a ,,; ', l-G 4 rF' 7 '^ , _ .s,-i'L• Pe+xq'Mr mf" , /; {, /- "wt.. "S°Jr"`:rtwt,� 1 — lox - 41"f S kc'7 r✓ +Y,i `tFS {4 '` ¢ , "L ; P m -1M� ° # Grp „A,Jp•• , ' 'v44�Y , .N4asef`�N i F x if f v x ' 1'+ti 4 p� -5-j.4,4•9'-'t.',7 i. t », .4.4....•,./s15„.. r is el + y tit/is - j _ a4 "Al a6�`5 �� 4 z � _4..4-�x+r dt„,,..,,,. �� i'MA� r' ""rk, �"` ' .3,x+ a + t s a .".1,Pr' 4R? 1,0'14', t l ; 4 i uF A a ^�,tpX' n xy'� 7"�}q A'+ ,ax�b" 'a'���, xa ,, '..t ,7:(4, .�,' f ..y (?, r '' / p_v_y O P1},141' „��'? + �'+`jC?$to- 1 = Y,O1-,' ,, e C ,u�g;,r-�f:.a�, re4w,'srfr'rit F� eta s e �;. a d a ,"1, i �iji x rte yy + f fi a +?I'll n ., C, P x7771"""" k("4p k •)kf ! : � d f }� l 4--M1 t� A � y . X11; Lc 12r2d/Zan, 11:24 y/a4d2dbb8 KIEFER CONCRETE PAGE 03 0 ®��Roche Greeley,Colorado Lae Vegas,Nevada Westminster,Catered* d`BCi Gonxlfuetor',Int. ADDITIONAL WORK AUTHORIZATION (Dally) BIB I Dale: Job I Job to: Weld County f Roche Constructors,Inc. ! 12 12 06 Name:WELD JAIL PHASE III Nob.: 0615 Specifically describe )2- L2EAnovly SN�w olCO AWAS Kiefer Concrete. Shaded area for office use o , Cost Code Employee's name Rag. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rote Row .Rttaq F-1 9 35 '4r.a: , ' 4,1 31 Lu ny q 3o , ), �••i: .30 4' 1w 6� "h'll ,,ibi�l d vh :•'. z TO NEIL 9 .1-•;•.•.1.`7r, 27O Ern 30 'rIv s ant, ,; �4,) labor subtotal ., Cost Code Material Req. Ouan. Unit Sub Tax Total Total Ik) 4. �I n f •i AI, ray • Material Subtotal Cost Code I Tools or Equip. Na. Rote Rental Period Total Z Nos Skel Lo<at 35 10 • Tools$Equip.Subtotal ra • Invoice No. Subcontractor T Amount ALL PRICING SUBJECT TO REVIEW Subcontractor Subtotal SUBTOTAL " /lqr RC(Rep OVERHEAD h%) Calendar clay extension No SUBTOTAL o Yes of days) Owner/Sub Rep PROFIT I_%) TOTAL ' Y f' . .(111:1 ;I•`np. p.l rAr•ur:.0071) i (, L..n 1:..7, ,IM1... I bvyn 12/28/200b 11:23 9704828658 KIEFER CONCRETE PAGE 04 a04Li Greeley,Colorado La Vegas,Nevada Westminster,Colorado Lenottuclon,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) B111Date: Job Job to: Weld County/Roche Constructors,Inc. , ip-72"96 Nome:WELO JAIL PHASE SI No.: 0615 Specifically describe IZ,—Zb AWA°KIefer Concrete. Shaded area far a - - use onl Cost Code Employee's name Reg. Rate O.T. 0.T. Total PT&I Total Hrs. Hrs. Rate Raw DoN 9 45 Yos 40� =F•o4bG 9 45 ''tJstY' �""..�W` tll ',': n• r T2),..t } 9 3 5 4' S � ry I r „ 315 DUANE q / !? �hr it qtly {^I"J iid HQS Labor subtotal Cost Code Material Req. Ouan. Unit Sub I Tax Total Total ra 'x� 1I it ,i irri � yl Material Subtotal i Cost Code Tools or Equip. NO. Rote Rental Period Total Tools&Equip.Subtotal11 Invoice NO. Subcontroclor Amount ALL PRICING SUBJECT TO REVIEW Subcontractor Subtotal S 1530 SUBTOTAL RCI Rep OVERHEAD( %l Calendar day extension ❑ No SUBTOTAL Q VAS ofday(s) Owner/Sub Rep . PROFIT I •R) • TOTAL �•.lit/Ill 1-I _ ...n• t 111!1!. 1 1i: I[.I,1.' 1 -i .1.YJr.I. � 1) r0JI(�,;1...,L"111 . r•i6:Y.f'' .�I rnna. uhf r.r,ImgW:cnin .• Roche pow q,*6tcs rcL, n /o tilt 1 Greeley,Colorado Las Vegas.Nevada Westminster,Colorado aonelruelen,Inc. I l 2A2 "-ADDIDONAL WORK AUTHORIZATION (Dpgy) Bill Dale: Job Job to: Weld County/Roche Constructors,Inc. 14+2.46 I Nome:WELD JAIL PHASE HI No.: 0615 Specifically describealc CEANQV �JNJW AWA efer Concrete. _ Shaded area for office use only Cost Code Employee's name Reg. Role O.T. O.T. Total PT&I Total �-- Hrs. Hrs. Role Row P4ay fv 1> .F :� , � `Tx,. 9 35r� I is Y q3olout. a _Nate_.� 9 So Hekse_l 9 3O M ,r wit 4I 4;4 '' �'.I& ';. Vo Lobor subtotal '•. - 1125 Cost Code Material Req. Ouan. unit Sub Tax Total Total et ,4v e t�. r..Y,, "PA, Y "t Material Subtotal „ .:•, :,a Cost Code I Tools or Equip. NO. Rate Rental Period Total Z Nog c_xl tr.Loa4 fr_ 35 10 roofs&Equip.Subtotal ' '. Invoice No. Subcontractor - " "• '" Amount ALL PRICING SUBJECT TO REVIEW Subcontractor Subtotal) SUBTOTALS 119•1110 RCIRep Calendar day extension _ OVERHEAD(_%) 0 No El SUBTOTAL Yes of dews) Owner/Sub Rep PROFIT(�_°L) TOTAL TT 7ClktI 7l AlNrl^1 ?IZa7T,I QCQQ7QAQIC CA:7T lfQ7/1T/TQ 12/2b/2Uab 11:22 9/U4828658 KIEFER CONCRETE PAGE 05 3s,4 q qt aonstreRoche Greeley,Coloreds, Las Vegas,Nevada Westminster,Colorado �ar..ln�. ADDITIONAL WORK AUTHORIZATION (Dally) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 141}2-12.96' Name,WELD JAIL PHASE III No.: 0615 Specifically describe (2-Z-7 RE.rw.tE 5b.do.y O!!n____ AWAY Kiefer Concrete. Shaded area for office use only_ Cost Code, Employee's name Reg. Rate O.T. 1 O.T. Total NVI Total Hrs. Hrs. Rate Row DON, (� /5 t; L 3-70IM __re KM b 3o �1 '� a l SO ; PA Z 35 In v'4� I �tzri it ! Ir. I'i V4,vt': '7 0 �ASoN 2 35 I%;tomq�' If:, .. n .•. u.• ',.qr.. . Labor subtotal ;`•'i r, "Cr: Cost Coda Material Req. Owen. Unit Sub Tax Total total J Material Subtotal 1.,,,;;Tit Cost Code Tools or Equip. NO. Rate Rental Period Total Celia-r. 4 Ax, 600 Skiff toA.L,e - e 3S ZIO Tools 8 Equip.Subtolol • invoice No. Subcontractor Amount /la, ALL PRICING SUBJECT TO REVIEW Subcontractor Subtotal SUBTOTAL 4 114 a O Ca- RCA Rep OVERHEAD( %I Calendar day extension ❑ Na SUBTOTAL Ei Yes-.of day(s) Owner/Sub Rep PROFIT L�%l TOTAI. • :• n-011 :.L 111 I (a;p I. 11 IJ h"i.4 A.lilt•}: -I •i 1,. 11.; •' A _ r"iIa:t'. ' :: • 'i I'r :.. .;(',u..„ rr 'Iry,41 ,s• ia•n:: hr.rr:nn:arc..rn r. 12/28/2006 11:23 9704828658 KIEFER CONCRETE PAGE 06 -C RQCt'1G Greeley,Colorado Lae Vegas,Nevada Westminster,ColoradoConoVunore,ha. ADDITIONAL WORK AUTHORIZATION (Doily) BiN Date: Job Job to. Weld County/Roche Constructors,Inc. 12 1206 Name:WELD JAIL PHASE PI _ No.: 0615 Specifically describe17. 17_ ITRIC AWA S Kiefer Concrete. Shaded area for office use only r Cost Code Employee's name Reg. Rate O.T. 0.1. total PT&I Total Hrs. Hrs. Rate Row launt4 z 2C .J`• tv 30 7 u S:: ,:r i� .t•I L ' �, :tr; 130 � ', 30 sc,t_ 6 3o I °''l ` "''13r; `� a I� ,FA I�r irt;{ 180 Likwo-1 b 30 Labor subtotal 1,7:1;:y-7\'I ISO Cost Code Material Req. Quoit. Unit Sub lox Total Totol d. ;t,g, y..'PIA,: : }7‘.:14;,,t k.;" I ^� '1 Material Subtotal `'`.,:i`ty;';•i Cost Code Tools or Equip. NO, Rote Rental Period Total Tools& Equip,Subtotal •>t&,;'^'I Invoice No. Subcontractor l Amount 74D ALL PRICING SUBJECT TO REVIEW f Subcontractor Subtotal >, SUBTOTAI, _ 1 I0 RCI Rep — Calendar day extension OVERHEAD( 9:1 ❑ No El Owner/Sub Rep Yes—of doylst SUBTOTAL PA opir TOTAL ni ., -.e vecp:gbigl i.n Dr. :m:uli='j JRN-t?3-2007(WE0) 1E: 01 RnrHE P. 006/005 k22 uene �Int y Greeley,Colorado Lae Veggie,Nevada W/mrdnwa.r,Colorado ADDITIONAL WORK AUTHORIZATION (Dally) • Dole: lob Job lo: Weld County/Roche Constructors,Inc. 12-28.06 Name:WELD JAI,PHASE Ill No.: 0615 SPcdka$y deserbe • Remove;now born looting forms along gridfnne 1.5. remove row horn over rebor slockplles.recover tooting concrete after pour AWA 01? Keller Concrete. Shaded area for office vse only Cosi Code Employea's name Reg, Role O.T. 0.T. Total PT&1 Total Hrs. Hn. Rate Raw ROW 35,00 tkr` t .'� am 4Q.00 Dab �`- John .. 26¢.00 � -- .. . i Ryan Z0 00 ■ " i GupPy 45 O ! -T� 4-: Sus 7n.T. I oN 3' o0 � Iw wswYwriwr Lobes subtotal 2_?, Cost Code Malarial Req. Quan. Unit Sub Tax Total Total 1 . ' A� F Maledal Subtotal Cost Code Tools or Equip. NO. Rote Rental Period Total • Tools&Equip.Subtotal • = --- • Invoice No. Subeoneractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Sublotol SUBTOTAL. 230.0 RC Rep - OVERHEAD I—°°i Calendar day extension in No SUBTOTAL ❑ vas__of daypl Clymer/Sub Rep . . PROFIT b %1 ga "nit-f.1 I7]YIAPVI )U flTV ofoo7onnic CI. •7T inno ;it ern 0,414 (. ki 4 utLe Thiant_ti, C.'R 079,17 ,,. i; G7,,G o fin' f O2) `` H edrill / et e-----t ik (fry ft) ost _5w d µ) JLt..a e ft e/ Ti All .-' Ji 2007(WE0) 1d: 00 ROf•HE P. 002/00S %%' ROche ?Af _„iv .cabredo Las Vegas,Nevada Westminster,caos.de IADDMONAL WORK AUTHORIZATION (Daily) 111 Dole: Job Job to: Weld County/Roche Constructors.Inc. 1-2-07 Nome:WELD JAIL PHASE Ill No.: 0415 SpectficolN describe Remove snow Porn tooting along gddino L.5 and remove snow from over mbar stockpies as well as fooling Fno 1 a7& I d3 from Line L toT+/• AWA 017 Keller Concrete. Shaded area for office use only Cost Code Employee's name Rag. Rate O.T. O.T. Total P LI Total Hrs. Hrs. Rote Raw John :i0.0 , 31.44 -ansr 'tlD —van a g0.00" ":'�exs✓xn!!t .I '.. 120 Hen's 1 4it •maw! , 0 Jason • d 3.1.12 '..'.—:;1; Ire._4 W. , _ _.r•, Iva Labor subtotal l• 13zo COSI Code Matedol Rai, Ouan. Unit Sub_ Tax Total • Total c. luiMairaii::._.. MaPedal Sublolol Cost Code Tools or Equip. NO. Rate Rental Period Total • • • Toils 3,Egvip.5ub101CA — Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer SubconvectorSubtotal SUBTOTAL 1t 3�� RCI Rep OVERHEAD(—.—.°S) Colander day oxlordon ❑ No SUBTOTAL ❑ Yes_olday(sl Owner/Sub Rep PROFIT(_9y • L0 3DVd 313HONOO N3d3IN 8S98Z8b0L6 6P :ZT L00Z/LT/T0 Gifts r g 4 lJ 'tr-vaQ C ' Dell Er r°�� ` ' ,V f'n' \— ok y 1 tz, - cnro (II gtecol--Q- If et I T -vim te / - m? - o7 Q-014 1 /,�� � v we o k.-0,- 2z c o-a-t.r AttRuche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Co moors,Inc. ADDITIONAL WORK AUTHORIZATION (Dolly) Bill Dote: Job Job to: Weld County/Roche Constructors.Inc. 1-3-O7 Nome:WELD JAIL PHASE Ill No.: O615 Specifically describe Remove blankets and recover footing concrete after pour. Also added 1%Polar Set on 26 CYD concrete Line 14.7 tooter from L.5 to R AWA 020 Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PTBI Total Hrs. Ha. Rate Raw Rudy '1.5.OO 4 ' 1... ,_ :fti'n Bob f.00 '" ; John _0 r 0 0 tin °4t '4S2c'<" _ Ryan 3O.O0 ' " Henry 3O.O0 rz'r: `7tiMa .•.f.+� � Greg 33.00 MtGio... .1!V WV. _ MIke 95.00 t • 'i • :'.'rIP'!"-, 1,' ?saL4 • t.:-wig�� Labor subtotal Vggi Cost Code Material Req. Quan. Unit Sub Tox •Total Total IR Polar Set for 26 CYO 2.6 F.50 a_, MS, material Subtotal2-Wi. Cost Code Tools or Equip. NO. Rate Rental Period Total Tools 8.Equip.Subtotal . .re Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keller Subcontractor Subtotal U C 6 Yel1119 . SUBTOTA$111•5‘.00 RCI Rep OVERHEAD( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes_of day(s) Owner/Sub Rep PROFIT(_%) 90 39'dd 31321ONOD 213d3I)I 8598Z8D0L6 6D:ZT L00Z/LT/T0 Si Co t'A 'F1 24 lady i J r co-,tie.-t" etzicea tr wA 6 r 61 la(� Roche . Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Construclon e.Inc. • ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors.Inc. 144,07 Nome:WELD JAIL PHASE III No.: 0615 Specifically describe Remove blankets and recover footing 14.3 from L to R t/-concrete offer pour. AWA 022 Keifer Concrete. Shaded area for office v$e only Cost Code Employee's name Reg. Rote O.T. O.T. Total PT&I • Total Hrs. Hrs. Rote Raw Rudy 35.00 '} -Van�!'L+.T T:7.... Bob 730.01 Ryon .3O� ! '' 1"+ 'S ttt-ce Henry 30.09 gL+-..: °:? ,:'3,S'3. • c.,.:F Greq .35. 00 Plea v t''.Iszt, is;":'.at}'..' Mike /fS.o Q •`ty$f'.- , 3,.. . -:.:: S:F'';t.-.' + ::Jt3 DDon #2 '15.0(i %�. Y i'i: —y 3 00 [: r Calvin ��j U 0 ,. nwYv y..J, Lorry i0. 09 eistegE Travis �D•5.00 "'�'•= ;F.? 'yt. s y, i.AFX George 75..00 Fes, , r x- emu:,ice,', Jason 00 a1i S??. ...17011::.7.7‘?:•. .:^'Ca:::i-3. ' 4/1.5 00 Lobo. subtotal P. 0 r Cost Code Material Req. Ouan. Unit Sub Tax Total Total 1%Poly Set for 26CYD 10 p:C "'•'^st•` T„50S Material Subtotal ;, Cost Code Tools or Equip. NO. Rote Rental Period Total Tools&Equip_Subtotal -'s Invoice No. Subcontractor Amount • ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Subtotal SUBTOTAI$ t�(J Cr 0O RCI Rep OVERHEAD i_%.) Calendar day extension 0 No SUBTOTAL ❑ Yes of days) Owner/Sub Rep PROFIT(_%( •.r,- c:i .. - ., . car S0 39Vd 313210N00 ?J3d3IN 8698Z8V0L6 6D:Zi L00Z/LT/T0 / - ' - O7 o 904 RA4k /3 il11 !daddy • CA t,r d u) ;714 r� y I % R ` elY \ Cotaft k-nty itRoche • 6 Greeley.Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. - ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 1-5-07 Name:WELD JAIL PHASE III • NO.: 0615 Specifically descrbe SNOW REMOVAL FOR STORM OVERNIGHT ON I-4-07. also add Polor Set for footing pour line 14.3 AWA 024 Keifer Concrete. Shaded area for office use only Cost Code Empbyee's name Reg. Rate O.T. 0.T. Total PTBI Total Hrs. Firs. Rote Row tidy 3.5 3 S.0 ... 122.50 Bob 3.5 30,0 ':.:. „L '' •r!aa IF<• , /0-5.00 1g50s John 74 .5 B'.•-00 2.25.o 2.2.10. Son 7.5 5(J.C7U 'YY<•,cc:;tl ., ,:;en;..,r„s7JYal 2_500 It 5.0 Henry 3.5 3V,OC 103.00. '05.00 La 0 Leery 7.5 " .0 u , Yid :, .,� ._LLT-5,un 1 2.5.0' Crappy 33 r}S,00 • slimy, :` 155O, "'!57.50 157.so i �,72 ,rU• 122.s 3.5 Doi 2 qs�o �.�� . ��. a• _%•f10S° a7,ot Geo,Is 7.5 `,5700 li i r S, 2 '.537.5 t: Labor subtotal j 5,1c72..; 16'72.50 Cost Code • Material Req. guan. • Unit Sub Tax Total Total 2%Polar Set for 26 Cm ire / 9- c Co p - �' Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Total Period • • • Tools&Equip.Subtotal Invoice No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor • • Subtotal SUBTOTS 2-3 .50 RCI Rep OVERHEAD L____%) Calendar doy extension . ❑.No SUBTOTAL • • O Yes of day(s) bR Rltir1 RIRN.'lNflf ?fl T)l RCORT.Rbc/F fb:TT /RGi7.// T/TR 5-- d 7 06 14 a k '° 7y F 2frvts k:k CA) 7/ Show gtifik To ifs' 7 Pa711/114 PA4 t y .101 r, v • f22 Roche 7� 6rtsele ado Las Vegas,Nevada Westminster,Colorado Cunshucton{•Inc. ADDITIONAL WORK AUTHORIZATION (Dolly) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. I-8-07 Name:WELD JAIL PHASE III _ No.: 0615 Specifically describe Remove blankets and recover footing 14.3 from L to R v/-concrete otter pour. AWA 037 Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. 0.T. Total PT&I Total Hrs. Hrs. Rate Row 35.00 +:`` Bob .30.r10. '. r Greg ,35,00 rik _Rudy i2 �s I _ e?3., Colvin .orgy Aa rry _ Larry .15.cot I. L' $..,., 30,Croppy pp• �zq 0c Labor subtata,/�,� Cost Code Material Req. Quan. Unit Sub Tax Total Total 2%Poior Sal fa 20 CYD p _ //0 ry/ry F .. Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal z Amount Invoice No. Subcontractor ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Subtotal sty SUBTOTAL 1-383.00 RCI Rep OVERHEAD(_%( Calendar day extension O No SUBTOTAL ❑ Yes_ofdoy(sl Owner/Sub Rep PROFIT(_%( TOTAL :;. Thi i T .{L l:dv ' - . �./:'• ;L 'T .; .. Gr1 L'. ')_/ :;OL3_ .r 1 y 'i..o:..l: ,:. ..� .Lb E0 39Cd 313J0N00 J3d3I)1 8998Z8P0L6 6b:ZT L00Z/LI/I0 / - 0 12 or!) t / 144 oydWI I JON-15-2007040N) IR: 30 ROCHE P. 002/002 RX4% Ron.�che Greeley,Colorado Las Vegas,Nevada Westminster,Colorado ADDITIONAL WORK AUTHORIZATION (Doily) Bill Dale: 1 Job I Job lo: Weld County/Roche Conehuctors,Inc. I 1-I I-0) I Name:WELD JAIL PHASE IN N 0615 Specifically describe 4 Remove blankets and recover looting lino conceit oiler pour, uncover and recover forms for retaining woN Ikte 1 AWA 040 Keller Concrete, Coll Code Em Shodod 000 to ellke use on lv�r ployee's name Reg. Rate O.T. Q.T. Told . PT&I Total I Hrs. Hrs. Role Row RuovIt1 2 33.00 Boo �_`sv.vo 4..r 60 o0 70 _ r2 2 ' 0 _ �x�w� w�.r. -J(�r . /0.00 )C T 2 33.00 ..JAI+: irb.r Su 7/0q.40, )0 2 ll%ao z Cid€021.1 24 41 John ye 1 Son 2 3U,op Catvin 2 ar•0 0 'i" 27 %0.0 0 70 Den 2 2Q.UU �4 9 `ts pp r .�.u4ilr tr�e44 60.00:. 60 �/S Do -:, imetbet--.04I-i` +0.00 •^ o __say I 45. 0 =._:.-:...a rr-�_^r-11.:-- Ly*t_;.''JJQ go • •�gyroo Labor subtotal .eysob s( Coss Code Material Req. Quan. Unit Sub ' Tax Total • IR Pdar5el loss CYa Total lip= 55 -3-0 ,;L _-- e in e,' .;,lea Mr R : 4 .Aii: Materiel Subtotal .:: `10.30 Cost Cade Tools or Equip. NO. Rote Rental Period Total Invoice No. Tools A Equip.Subtotal NO Subconhoator Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subconaoclo Subtotal n SUBTOTAL. 131'1.SQ Rd Rep Calendar day extension OVERHEAD i_....%) ❑ No SUBTOTAL ❑ Yes_atday(s1 Owner/Sub Rep PROFIT I R; TOTAL CO 39Gd 3I3210N00 213d3IDI 8998ZBV0L6 60lZT LOOZ/LT/I0 I ROC1 ,e \11 Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Igt Co1W[mLYot lt. ADDITIONAL WORK AUTHORIZATION (Daily) 611 Date: Job Job to: Weld County/Roche Constructors.Inc. 1-15-07 Name:WELD JAIL PHASE III , No.: 0615 Specificolly describe Remove blankets and recover forms for retaining wall line I AWA 042 Keifer Concrete. Shaded area for office use only COSI Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw r Et_CI 'TAY'.' ^laF ea 7 3,$.00 ��LTTTear9 `-S.00 .: H✓,r 1r •-± , Labor subtoto Cost Code Material Req, Quan. Unit Sub Tax Total Total 1%Polar Set for 55 CYD Fro it e1 Fl ix- e i I'i f Material Subtotal Y iji Cost Code Tools or Equip.. NO. Rate Rental Period Total Tools 8 Equip.Subtotal, es Invoice No.. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Subtotal SUBTOT$ 02 50 RC!Rep OVERHEAD Calendar day extension ❑ No SUBTOTAL ❑ Yes ofday(s) r s e 'ya7r..e 3 °J'`1C- C� ���'!.+�.1 t4 .1ti (IN):SLfGu :c-(•JNI.SGb19 �..1 ro-lmn+(JO) 3.1-3J If 1r1i-/at . c(ur15a) :6 ft..L?i(ANi3 ) 1 ..l-y,Cbu-eau ,.. sSCIoitai Z0 39Cd 313a0N00 213d3IN 8598Z8VOLE PEleI an/8T/TO /' / 5- 9 / t " R fir' i � 1r fr / a #* \� * ) / § �� � 6 6 1 �' . r y\ \ $*t \ / vs.. &»© . . f Ell% Roche �c d.,Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Cenowuciorc,inc ADDITIONAL WORK AUTHORIZATION (Dally) 0➢l Date:/6 Job Job to: Weld County/Roche Constructors,Inc. I-)$07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Remove blankets and snow from tine 22 footing poured on 1-I 1-07 AWA 043 Kelfer Concrete. Shaded urea for office use only Cost Code Employee's nome Reg. Rate O.T. O.T. Total P18.1 Total firs. Hrs. Rate Raw •a.� 2 '5.00 — -tvvR3.iiiiti:t'-4:.v':.z`dre'k 2 _ - A.co" 'u]� >. ii2�_ _ Rudy ;30.00 0+ ]ye . .. x'256 "va` am* 1O1O1 e-..4 {� re. ' � sy�-S�'• 00 n 0 'n 0 2,70,Q0 Labor subtotal Cost Code Material Req. Ouan. Unit Sub Tax Total Total V%Polar Sot for 55 CYD 170 = 5:5 Y 50 •= _ ' u.n s r..• Sat .4th.Pfk, Material Subtotal '' Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip_Subtotal :1 Invoice No_ Subcontractor Amount ALL PRICING.SUBJECT TO REVIEW SEE ATTACHED field note list from Keller Subcontractor Subtotal SUBTOS 757:S Q RC'Rep OVERHEAD Calendar day extension Q No SUBTOTAL O Yes_of dayls) Owner/Sub Rep PROFIT I__%) TOTAL > r 6 � ,.;ni.c(9>0)'nrLu :.aO]d)];6d:d9 .. vv.1., ��,(fg3)yi•I flit. JAI/!"nv. y., (Cur.!4) 1•u.Li,. (80.)11) r.cultr,Cnaaur. wwwacciucc aia.r..tn r. TS :r �..t .. CO 39Vd 313a0N00 a3d3IN 8598Z8DOL6 7E:4T L00Z/8I/T0 /._, / -- 9 / ( 2 !f + K \rd 1-,,,,, ‘) - � \ iz« act, O 7 / / /- , ± � �! 7 . ® rp.5pe \ - 2« ® « - . \\ » I . k ,w, / \ #ra 1 a. ^ JRN-19-2007(FRI) 10: 53 ROCHE P 002/003 tRoche Greeley,Gatorade Las Vegas,Nevada Westminster,Colorado Gwwtnclers,Ina ADDITIONAL WORK AUTHORIZATION(Dally) Bttl Dole. Job .04 lo: Weld County/Roche Construction.Inc. 1-1607 Name:WELD JAIL PHASE III No. Oat$ SPectficasy describe Remove blankets and recover elevolOr pits AWA 046 Keller Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rots O.T. O.T. Total PT$J ' Total Hrs. Hrs. Ralo Raw .been l W Gloa 1 ' 53253 y I -� Rudy t =on dJrl Henry I $30.00 : I n��.11lr�It s{,4;.., Mike 1 3/5,00Rae ,Zq" •�3r1 !old 1'y.,� it 4 r' —` __�, i• Mr -4;41- .2, 18Q.09 Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total �y Total 2%Pala Sol tors Cr) 2W �p p G•5Q r - I N 1L r ■aY� $'5'3.0?ab0ria SO131010t Cost Code Tools or Equip. NO. Rate Rental Period Total Tool A Equip.Subtotal Invoke Na. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer S-ubcontractor Subtotal SUBTOTAL$333.0 0 RCI Rep -*• OVERHEAD 1 TL) rr'- C iendar day extension No SUBTOTAL ��/ j a ye.-of dayltl Owrwr/SVb Rep PROFIT TOTAL t - .•n m .11..,..,. yrl'•)�.: 1',i ..v.:-Mr rly:'.:tr Illy J 1:1'. . 21�CL;) I Yee J_J--u3.! r e cV L': . .v .rn'.J t. 1 ..,i.L.OI Z0 39 d 313210N00 NadJIN 9598Z840L6 L£ :ST L00Z/6T/T0 JON-19-2007(FRI) 1O 5& ROCHE P. 003/003 • �pI / Vic. vwc �G a' ' TA'S��. • 9/ el a • £0 39tid 313NJNO3 N333IN 8S98Z890L6 LE:£T L00Z/6T/T0 JAN-20-2007(9AT) 09: 13 ROCHE S`��//O P. 003/003 V 6Y AllRoche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado truclank Inc. ADDITIONAL WORK AUTHORIZATION (Daffy) J I Dole: Jo: Weld County/Roche Conductors.Inc. ( I-19-07 I Hartle:WELD JAIL PHASE III I No- Da t s SDOdllcolly detcttbe Remove blonkels and 'weever elevator pits,build tent for wall One I heal protection, Cover the 212 and 22 from Sic L.1 la R+/-• Note wal crew on tent ham around noon on. AWA 049 Keifer Concrete. Cost Code Employee's rams Reg. Shaded area for office use only Rote O.T. O.T. Told Pap Total L. Hrs.. Role Raw town _ . ayae ^—• c � sawn It7 i!I„eIlr, s 1 '+we.:" W u — HenryL 530,00 {r.-.- :.. 'a�,� _ 41 )4D r.. r'f 0 j Mkt 3 443!30 , ' i.. tar Rv�� N, _ _'I 3S.on 0 dot . r-Iv C{ 4 -^ i i �y�� Yc Cab al✓.'., 30300 .09 — •' :i - ittwa --l'Ilte 'mg le L,¢rr,�^ 4 30.QQ 0 ^"4, ,dry--J>i : _ ^ ri000 ' A!L, t s ., ,4,: tits Lredly yILL". ��s it RS %r:.-TA/ink►a---Nita lea.:ri, S1 b t/..5 F5.00 Laborsubtotol 1:-: . --,Lk. , ' G colt code .. 6S 1r, tooled Req. Callon. Unll Sub Tax Total TOPS .1-71V bas for tailing welt end Olerata Pit _ - (2z) 5.62 f f: 1z3.6N 20 Ca ttC''-1 Pre lot rot - ® !" J pr 9 Moteriol'... _.. ,. 61. __. 00 "rt 6r, SUetati _--- Cost Code Tools or Equip. NO, Rote Rental Period Total Tool:&Equip.Subtotal -_ _- Involea No. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW • SEE ATTACHED Held note list from Keifer fir (` SUbconhoatorSubtotal SUBIOTA /7 69.lH WO Rep OVERHEAD(_%I Colander day extonslon .._ C No .,• , '`ti -~- CI Yes_of daylsl SUBTOTAL `Owner/Sub ep PROFIT(_,S) Z0 39Cd 313a0N00 2I3d3IN 8998Z8h0L6 LI :TT L00Z/ZZ/T0 JAN-20-2007(5RT) 09: 13 R0CHE Pie J * P. 002/003 AltRoche eomlrvrrar,lnc. Greeley,Colorado Laaa Vegas,Ne eda Westminster,Colorado • ADDITIONAL WORK AUTHORIZATION (Daly) SW Dole: Job Job lo: weld County!Roche Constructors,Inc. 1.20.07 Name:WELD JAII.PnAtic Ill No,; 0615 Specifically descnbe Remove blankets and recover elevator nits.uncover recover wall line l for hoot g ollectlon• AWA 050 Keifer Concrete. Ir--• Cost Code Em .- Shaded area for elflee use only ployee's name Reg. Rate O.T. O.T. Total PM Told tin. Hrs. Rote Raw Jams _ 1 Greg535•. Rudy H 5. +T+:•t'*y� !!P�r*+r 3 Do woo S W faaio rT.o Mike — I. 00 ;rwM,' L'•f'� '�tYltr. k�, _ Groper 11 i�1lt»' t. r., gr.pP �ravh' I ;TOO -- * Tee�rr e.-1rre, y. H / 30,o D _me- td 1;a 1111 SC} Ir 70.00 �po� Y ',J.o0 -` -1I r - Ta1a 11Iwi1 -. 30.00 Ri,' r M. I 35.P 4 - J 9r.00 fir,, sic- s°:(3 1�1s rcf►1N•1..r C ...4.,-, • "^ Labor subtotal 3 630.00 Cost Code Material Req. Quart Unit Sub Tax Told To101 I?, Par 125 yrel S 7,50 .;, .�7{ .�_ 104,50 20 JOalleni .0 P . prnea,C.- 3.05 off 41.00 $ 1/23:so Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal klila Invoice No. SuboenaoCtor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keller • 1 Subcontractor Subtotal��� SUBTOTAL$ I)53,50 RCI Rep OVERHEAD t_%) . r • Calendar day extension// te SUBTOTAL ❑ Yes—of doylsl Owner/Sub Reps PROFIT I %J E0 39dd 313N0N0D el3d3I�1 8998Z8b0L6 LiiTi L00Z/ZZ/i0 JRN-23-2007(TUE) 1E:2d ROCHE P 002/003 ltflOehe Greeley,Colorado Les Vegas,Nevada Westminster,Colored* Canrwman,Inc. yZ-07 ADDITIONAL WORK AUTHORIZATION (Dolly) line Dale: Job Job lo; Weld County/Roche Constructorl10c, I-2607 Name:WEIR JAIL PHASE III No.; 0615 Spocilloolly desuibe Remove SNOW REMOVAL.MELTING ICE IN WALL KEY WAYS UNCOVER AND RECOVER FOOTING UNE22 S.212. AWA 053 Keller Concrete. Shaded area for office use only` Cost Code Employee's name Reg Rale O.T. O.T. Total PT&i Idiot Hrs. Hrs. Rate Raw Goago 2 54500 Travis 2. ;.15.02 r Da.....--&--L-1---fI.. �',i•.w .1, .• Dc_, Ryon 2 a30,W "f 94.Ir.'IT' i „Le H 2 _ j35dp y' ice--, DoMan 2 345, alp !(d'.lJYI ri.'s ri IF.. 00 Neal 2 X000 Crisper 2 i*. +I -frllloe S�a3op Can a MO I rr l ' -- fr 3 5400 7.11:444 t fL Henn A M'144' .. -...-. rn �i000 '`,rirrJc i- '4nrlrlet Jon S90A0 - • r��i[ ll it�I el �.1 Agnsµl5' 1 1,► 1 J. 7 m1 i v7y t}Itr�lwf� _ 116161 r 1 •. X1205. •6 1 4'5 r'axw-I a 9 �r, j1-1. h'I 00 Labor sublolot /L..% r Colt Code Material Req. quan. Unit SUb Tox Told 20 aoR'roaerre Total Told I6I 00 *^ .,-- -.Jill; aw Irl.l ., fl Material Subtotal r Cost Code Tools or Equip. NO. Role Rental Period Total I Tools 8 Equip.Subtotal ',;I?,, Invoice Na. Subcontractor Amount ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note ILO from Keifer Subcontractor Subtotal ) SUBTOTALS ill 617.00 RCI Rep OVERHEAD(...._%1Calendar day extension /` Et Ye SUBTOTAL Owh6/Sub Re. PROFIT(__-I . 0:}r, it)rq(-$i it .1 c'9In):5-'61r l:en;:Prvrr•o 1 411;1.11 S;', 761:1"fvelLe it^.C1+) on I! I . (P0',J'I rir'rly Cof;-dc N.'1I P'"e^n:1L.U.r:.cem Z0 3DVd 313?JON00 2i3d3IN1 8S98Z8DgL6 SE:ST L00Z/EZ/T0 07 o p C-eo a • 7,c�� el c i' • ifya-yt) • 2oay 14 a At) A• E M PGA o ; A/ea / 2 J C '- vet 3 4 C Qfir:at' £0 39Vd 313d0N00 2J3d3IN 8598Z8POL6 52.5T L00Z/EZ/T0 A . /- & a io Ce.a 1.S. a y Z ( Rio elk 7 hi irt O0s) frtr3oS 3 ILdea eft /vfh 3 Cd ' �'° '+ aria tgalf T. C a r�e-,w y a ,r 7`'�'°C.CB 39Vd 313213NO3 d3d3IN 8998Z840L6 SI:VI L00Z/£Z/t0 'ill Roche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job to: Weld Count//Roche Constructors,Inc. 17-23-0% 1 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Uncover Fooling, move snow, cover footing Job AWA 057 Keifer Concrete. Cost Code Em Shaded area for office use onl Employee's name Rag. Rate O.T. O.T. Total PT81 Total Hrs. Hrs. Rate Raw Hem 3 35.00 : �a a a.> Jon 3 3000 ^Jri- lv Sr , a uux•. Neal 3. 30.00 J�r x t 4 i.TF ,5290. 2 30.00 _: , r ..:.+u ..�.:-.' &eft+.:"t 5'1"-7-t"� ° f.N5, ..;e.._e..�.t. ::/r,.n.'k;R ha:P :CeXsA. yu�- tJ',F t ..sty ''S ,wii �. ! .. %Y .1 4 SC's].' F .i....C. !, Labor subtotal -' Co3t Code Material Req. Ducts. Unit Sub Tax Total 1 Polar set for 28 Twgl yds. 8.50 6, x Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total • Tools 8.Equip.Subtotal r_,•• ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Subtotal $583.00 SUBTOTAL RCI Rep OVERHEAD(_%1 Calendar day extension ❑ No SUBTOTAL O Yes_of doy(s) Owner/Sub Rep PROFIT f _,L1 TOTAL.—.. . el/II:,:Itt,J(!ii ...... ..... In” . .. .._ I fn;j'oi::In .o!n A,-ii,et:we;nP ii.r,.vtr isoeV) <;,L.•kr.rotlYai.. 0.•J V'00h'i Pitt o:wr..umi Z0 39tid 3132f0N00 N3d3IN 8598Z8b0L6 617:9I L00Z/bZ/i0 AltRoche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 1-26-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Cover Retaining wall reinforcement. AWA 64 Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw Ned 1 30.00 .f XIS i - - x Henry _ 1 30.00 'mac z `� r,, -5. :V.-.=';-. F , , : a,> "T ;"' : ..bg,3 >: 0 .n l L_3 ,,, !'r x� ?3' .wtF c• k-,:4:4'1:1i..kr ':,.447i..14,h4tIp_f•yxtilei `T 4 it - 74 , '' i' . { ti .'. •._...,,,,404.40.0 •1 .uz' f labor subtotal '''_=5.45:7".: Cost Code Material Req. Quan. Unit Sub Tax Total Total r Materiol Subtotal ' Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal IIIII ALL PRICING SUBJECT TO REVIEW Subcontractor Subtotal Itr60.00 SUBTOTAL RCI Rep OVERHEAD( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL lior? / ,i _ ' Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71•'Avenue(90634) P.O.Box 1727(80632) Greeley,Colorado www.rocheconstructors.com - i, '.Y 4` • r Roche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors.Inc. 1-30-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Cover Wall lines 22 & 21.2 AWA 068 Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw Don 45.00 elc 13_ xv`E" *e. t:'"4&d0 sr Rud H. 35.00 100724 Rud M. 35.00 EMENE, friVarn, x'.tfl Jason 35.00 aaa eaa Bob Calvin 35.00 EMNEWSZtalcalaPal Collin 35.00ee 71 ,LTV Labor subtotal % .a-:a Cost Code Material Req. Quan. Unit Sub Tax Total � Total gg�.M -'-0211;.,qdri .2?-76771 . S5re I 44,44 Material Subtotal 4,4 ahrw.�. Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal r' ' ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keller Subcontractor Subtotal $250.00 SUBTOTAL RCI Rep OVERHEAD ( %( Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL if hY {2:` �'' l Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)524-3716 361 71v Avenue(80634) P.0 Box 1727(80632) Greeley,Colorado www.rocheconstructors.com N�' 3t AtRoche \V V � Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,inc. - ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job - Job to: Weld County/Roche Constructors,Inc. 1-31-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Building tent over retaining wall and grade beam AWA 071 Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT8.1 Total Hrs. Hrs. Rate Raw Don 4 45.00 t860o'.ess. Mike 4 45.00 'y'.' ;, x;S';' + ;'F'$f},6(ZOe: CroPPY 4 45.00 MaSEOMMEAM5/444. Boakc `. Jason 4 35.00 Rudy H. 4 35.00 041/421111INEMICEIP rin Rudy M. 4 35.00 '. r er Calvin 4 35.00 a a * Neal 4 30.00 are =` Bob 4 30.00 Greg 4 35.00 riisaa lc- 41 2/a-azic -s .,. a >F f e ap's � ry Illlllllllllll,• Labor subtotal ,a ifit; Cost Code Material Req. Quan. Unit Sub Tax Total Total f f Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Total Period Tools 8 Equip.Subtotal ALL PRICING SUBJECT TO REVIEW Subcontractor Subtotal $1480.00 olV/ SUBTOTAL RCI Rep OVERHEAD ( %( Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) .,..tee.,. ... TOTAL • (.0, Office(970)356-3611 fax(9/0)356-3619 Denver Metro(303)5343716 361 71 Avenue(80634) P.O.Bon 1/27(80632) Greeley,Colorado v vv,racheconstructors.com atRoche _I F (; �b I r Colorado Las Vegas,Nevada Westminster,Colorado Constructors Inc. V ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors, Inc. 2-1-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Uncover Wall Line L.5 to continue form work AWA 075 Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw George 45.00 X.W-742tTh.7414 7r4.406fa. Travis 35.00 h ;341';'. Ryan 30.00 Larry 30.00 ib s-.-.a„- hssrrid,- .mom, ;9000 x'E- Jason 35.00 ; -53500r.J. Mike 45.00 ' "S'43v Y1 '4S0 e' -Ton C. 30.00 WA*. 'se~'�# a'''30.00-t, itt 4v y x„ :t tF r crire V1" lat 1111'" _ a j '. Y 1.. :Yr Arm rS Labor subtotal .t {lit t Cost Code Material Req. Quan. Unit Sub Tax Total Total ' 1 � Material Subtotal - Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ' � ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Subtotal $250.00 SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT(_%) TOTAL rt t Y4L Office(970)356-3611 Fax(910)356-3619 Denver Metro(303)534-3716 361 7P`Avenue(80634) P.O.Box 1727(90632) Greeley,Colorado cnvuv.rocheconstructors.corn AllRoche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-5-07 Name:WELD JAIL PHASE Ill No.: 0615 Specifically describe Removed Tent, Moved Rebar AWA Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I ' Total Hrs. Hrs. Rate Raw Don 1.5 45.00 i "` f -N-it:--'1''''v.;67.56;' mike 1.5 45.00 t'4110;',-,:',4:i ",=:.:',..4,4‘k'1,..4,P. ' :x':67_50` Jason 1.5 35.00 iii 04":,7,Ve..r: a� . ;5250 Neal 1.5 30.00 Ng.44C.:, ' 'v'r `C" #� "I'45 00 t`; Calvin 1.5 35.00 17_A A•,t 1,,, "n,'�',•,,,-;-.... "5502-. Bob 1.5 30.00 ' t `- n45,00 Rud , s.y 1.5 35.00 1 ? ":t 50 Henry 1.5 30.00 a it A 4 * nlrs '4500 i , • ','1'414, • y�,.� �, }k5 iii �.._ h," rya tx RAJ 7{\ C :,k4..,.:';',1 Yr(l kt Labor subtotal ,;e". Cost Code Material Req. Quan. Unit Sub Tax Total Total Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal No ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Subtotal $427.50 SUBTOTAL RCI Rep OVERHEAD( _%) Calendar doy extension 0 No SUBTOTAL 0 Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL t. :'.,,, ,i:,:: ,:" ::''?..1.",i1' � ti' Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71'`Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado wvnv.rocheconstructors.com AllRoc e Constructors,Inc. Greeley,Colorado Las Vegas, Nevada Westminster,Colorado ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-6-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Building tent for retaining wall AWA Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&1 Total Hrs. Hrs. Rate Raw Travis 4 35.00 c v Larry 4 30.00 � ' �; tt rl4 tilbir Jot r t1 It 4+,jiex l Ryon 4 30.00 Henry 3 30.00 ::,' ,.".,.,Ciii.c+..s� askr.wr;.-,.,ri:• a a.t . Jon C. 4 30.00 t t` lc +�,�I-'�+w},��.. g' , Neal 4 30.00 44-i::r.v„n:, ',:sra:^s.,...,.., r.`"tu°:LI Bob 3 30.00 ',�i{ fii•-i'04V i ! .7 y toga 46* ,04t It'4177'4 s Colvin 3 35.00 _ awl,(i+Yil y 0f1.*I.wM r iY {,.'. r.....'.�.M1r t 3 A . i' ft� r } Y IY' rF- r.„.1,-...",.-, _ {'fir: l Labor subtotal i4 3, Cost Code Material Req. Quan. Unit Sub Tax Total Total Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Subtotal 905.00 SUBTOTAL RC!Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL O Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL £i <y �tzs 1; ,'thy t. Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71"Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado wwew.rocheconstruetors.com Roche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job fo: Weld County/Roche Constructors,Inc. 2-7-07 Name:WELD JAIL PHASE Ill No.: 0615 _ Specifically describe Finished Building tent. AWA Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw George 1 45.00 a ` +e4 Travis 1 35.00 i.oa man I 30.00 n: + Ar. Jon C. 1 30.00 eas Larry 1 30.00 ..:�, . mod+, :iii._.-W - fi APT S .iim d ry q�xxr ^ r'itit/etitthtti7, :,:....: t^ °Ltsa. 5 ', art. '?1/,!.'''.". �_ . ,}} Labor subtotal : =xa a� Cost Code Material Req. Quan. Unit Sub Tax �Total� Total _ -- ,, �i Material Subtotal au3. Cost Code Tools or Equip. NO. Rate Rental Period Total Tools &Equip Subtotal "',�,' IC TO EV , SEEALL ATTACHED NG SUBJE field noteT list froIEWm Keifer Subcontractor Subtotal $170.00 SUBTOTAL RCI Rep OVERHEAD I %) Calendar day extension o Na SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL IOHiCe(970)356-3611 Fax(970)356-3619 Denver Metro(303)5343716 361 21"Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rocheconstructors.com AllRoche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 1 2-9-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Uncover and cover footing AWA Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&1 Total Hrs. Hrs. Rate Raw Jason 1 35.00 •r ir.� • � 1--,.._..t.,;_.....,_ -_-_,--,t-,,7: Rudy M. 1 35.00 1 '�' Henry 1 30.00 Bob 1 30.00 - r ;`1 Neal 1 30.00 �� 1 s=.. .-� . r � gp�y + tw _ ....rv3'.a": r ' c r a: 'tom . Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total Total _ 8 Bags of sawdust 8 6.50 - Material Subtotal ... ......... . Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Subtotal $212.00 SUBTOTAL RCI Rep OVERHEAD (_%) Calendar doy extension 0 No SUBTOTAL O Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL l >< -I �-- Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71 Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rocheconstructors.corn Roche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Ine. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-12-07 Name:WELD JAIL PHASE Ill No.: 0615 Specifically describe Uncover and cover footing AWA Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O. O.T. Total PT&Ittirticrifir Total Hrs. Hrs.T. Rafe Raw Rudy M. 0.5 35.00 Bob ra 0.5 30.00 Calvin 0.5 35.00 m Henry _ 0.5 30.00 ”tf rra;i , r., Labor subtotal •,. s® 14. Cost Code Material Req. Quan. Unit Sub Tax Total Total •e,}u4 Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW ■ SEE ATTACHED field note list from Keifer Subcontractor Subtotal $65.00 SUBTOTAL RCI Rep OVERHEAD ( %( Calendar day extension ❑ No SUBTOTAL ❑ Yes of days) Owner/Sub Rep PROFIT( %) TOTAL rh.t 's+ s 4ks'm Office(970)356-3611 Fag(970)356-3619 Denver Metro(303)534-3716 361 71"Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado wwrvv.rocheconstructors.com d' Roche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-13-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Uncover and cover footing AWA Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T- O.T. Total PT&I Total _ Hrs. Hrs. Rate Raw Rudy M. 1 35.00 s4 `r Rudy H. _ 1 35.00 'a"; " �`35 00 Bob I 30.00 `, r:,, $ •30.00.' Calvin I 35.00 Henry 1 30.00 s= :v'-�:ta �^t ^'., 530.00.;t;2• T'"j:4`,C=` (,i.,nttY.?r'i tt{�M$ •i s1y.iwr wry y ,'ir r itS Irj 'i'wt it�7.m a+ R`i,iar%.` 'MiiitiFl,Irviu' Labor subtotal Cost Code Material Req. Ouan, Unit Sub Tax Total Total 4 bags sawdust 4 6.50 Material Subtotal .. Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Kiefer Subcontractor Subtotal $191.00 SUBTOTAL RCI Rep OVERHEAD( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL Lz� ; 9 "' r, office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534.3716 361 71'Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rocheconstrudors.Com it R., .. p,111Roche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Doily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-15-07 Name:WELD JAIL PHASE Ill No.: 0615 Specifically describe Uncover and cover footing and wall. AWA Keifer Concrete. Shaded area for office use only Cost Code Employee's name Reg. r Rate O.T. O.T. Total PT&I Total Hrs. His. Rate Raw Mike 2 45.00 • 0 " (" e r Jason 2 35.00 x.. fir. Ot q r a a Greg 2 35.00 Rudy 2 35.00 y l+tw ni tit' A*I�5,npa(l� •' tl ycr + wisirrr)r+++rtxr+ Henry 2 30.00 r Collin 2 35.00 at•``A. Geor e 3 45.00 w•.�+{rrKf, 1 Travis 3 35.00 I i{ lilu�a, I C +u�w= i0,4, Neal 3 30.00 w.+��litilgi i9i: /I�t171:10; 'rt2xriyt),«.r,y;r. .. 5fun J.N. • .wi 4 -rtt a Labor subtotal �.. Cost Code Material Req. Quon. Unit Sub Tax Total Total Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Keifer Subcontractor Subtotal $760.00 SUBTOTAL RCI Rep OVERHEAD( %) Calendar day extension ❑ No SUBTOTAL O Yes of day(s) Owner/Sub Rep PROFIT(_%) TOTAL A =. - Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71='Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado =Ay.rocheconstructors.tom -.'�i t. k AltRoche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors.Inc. 2-I6-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Uncover and cover footings and walls AWA Kiefer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw Jason 1 35.00 „ '' ' A, is x `3500,7 Rudy H. 1 35.00 B ;` " `H a..t35.00 Rudy M. __ I 35.00 'p._ ;14,K,4:-4,'35.00. :. Neal 1 30.00 -n r - ', 'a*='WA.,'`:30.00 Henry 1 30.00 'i:' r.•i,at' ' . tt .--30.00 Don 1 45.00 -,,,,t,.- , _:tits, , :-f4.5 00 Bob 1 30.00 ..!!-.. '-`,*4 .et'ri+r v i'4 at,{: tr"4 a30 04 5.kjItqr.,:,,; ., .r 5.y. .rte''.' ,,.. George 1 45.00 41� ,T a:} ;: DD n 4S Travis 1 35.00 Ryan 1 30.00 g'..' 4 ''00'' I. ....4., .• r,.f 7.1,!=- :4 1'4, ..,wt�" w - }r. .. z n S '.itt Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total Total Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Kiefer Subcontractor Subtotal $350.00 SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension El No SUBTOTAL Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL y j/ ..:1 Office(970)356-3611 Far(970)356-3619 Denver Metro(303)534-3716 361 71"Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rocheconstructors.com glaRoche Greeley,Colorado Las Vegas,Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors, Inc. 2-20-07 Name:WELD JAIL PHASE Ill No.: 0615 Specifically describe Build tent over wall, and uncover and cover tooting AWA 102 Kiefer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw George 3 45.00 .44-444'1't 4f s' :'^ Travis 3 35.00 "`' 'fir. . of s' 3 az w z Ryon 3 30.00 =w� t�'.m ,+&.7 Jon 3 30.00 `°Sst d e,':',;k*INC4.1g1Larry 3 30.00 Neal 3 30.00 " 4rtf Don 1 45.00 Jason 1 35.00 ;tf�•" 4tg Rudy M. I 35.00 r*IQ* 35t%T Bob 1 30.00 'r Ttt tK�EkUD ;WOW 440,4aV4 ` 9 J AI . �ut.�t�,tr 7� ;. Labor subtotal ;'ryi , Cost Code Material Req. Quan. Unit Sub Tax Total Total Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Kiefer Subcontractor Subtotal $745.00 SUBTOTAL RCI Rep OVERHEAD( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL FyN ".;.*;45,:t - Office(970)356-3611 Pax(970)356-3619 Denver Metro(303)534-3716 36I 71"Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rocheconstructors.com Raehe Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-22-07 Name:WELD JAIL PHASE III No: 0615 Specifically describe Uncover and cover footing and wall AWA 111 Kiefer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate C.T. O.T. Total PT&I Total Hrs. Hrs. Rate Raw Ryan 1 30.00 Jon I 30.00 Rudy H. 1 r 35.00 Bob _ 1 30.00 Mike 1 45.00 .ffvc;f4Ent Colvin 1 35.00 _ Henry 1 30.00 rs - i w, w• Labor subtotal Cost Code Material Req. Quan. Unit Sub Tax Total Total 19 yrds. With 1% Polar Set 19 8,50 Material Subtotal Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Kiefer Subcontractor Subtotal $396.50 SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL 4 fiy' ,�ke}v tt w Office(970)356-3611 Paz(970)356-3619 Denver Metro(303)534-3716 361 71'`Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rocheconstructors.com Roche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,Inc. ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-26-07 Name:WELD JAIL PHASE III , No.: 0615 Specifically describe Uncover and cover both wall and footing AWA Kiefer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate C.T. O.T. Total PT&I Total Hrs. Hrs. Rafe Raw Henry 30.00 _ .:t ur i:-oa' ?• Bob 30.00 tie',' S' Neal 30.00 4t: Rudy H. 35.00 Calvin 35.00 4 _. e® Lorry 30.00 ifiir' K.v ,_ tie Ryan 30.00 1 ci" : ' am^,e Labor subtotal (471.1197..31. Cost Code Material Req. Quan. Unit Sub Tax Total Total Material Subtotal •� : Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Kiefer Subcontractor Subtotal $220.00 SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) ,,. TOTAL a Office(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71"Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado tame n checonstructors.com it t Roche Greeley,Colorado Las Vegas, Nevada Westminster,Colorado Constructors,, ADDITIONAL WORK AUTHORIZATION (Daily) Bill Date: Job Job to: Weld County/Roche Constructors,Inc. 2-28-07 Name:WELD JAIL PHASE III No.: 0615 Specifically describe Uncovered and covered footing AWA 112 Kiefer Concrete. Shaded area for office use only Cost Code Employee's name Reg. Rate O.T. O.T. Total PT&I Total Ha. Hrs. Rate Raw Larry 30.00 1a 3, ,. v ,'e +a g. Ryan 30.00 Calvin 35.001:it, t egl:. Bob 30.001„ �.° a er Rudy H. 35.00 =>' ,. :+ r- a at 3h": Travis 35.00 '"° ere George 45.00 : .,eat +a _.tea as war Labor subtotal 3 ,`,./.r. . Cost Code Material Req. Quan. Unit Sub Tax Total Total M ;,„,_, . i #e. Material Subtotal z., .. Cost Code Tools or Equip. NO. Rate Rental Period Total Tools&Equip.Subtotal ALL PRICING SUBJECT TO REVIEW SEE ATTACHED field note list from Kiefer Subcontractor Subtotal $240.00 SUBTOTAL RCI Rep OVERHEAD ( %) Calendar day extension ❑ No SUBTOTAL ❑ Yes of day(s) Owner/Sub Rep PROFIT( %) TOTAL once(970)356-3611 Fax(970)356-3619 Denver Metro(303)534-3716 361 71"Avenue(80634) P.O.Box 1727(80632) Greeley,Colorado www.rocheconstructors.com 05-21-2007 10:33 Roche Constructors, Inc. PAGE: 1 BY: TARA JOB COST TRANSACTION REPORT JC\RTRANS PERIODS: September 2006 thru May 2007 Job: 0615C0 Weld County North Jail Complex Phase III ighest P/R W/E Date 05/13/07 Highest 8/0 W/E Date 05/13/07 DIV - CLIENT/VENDOR -- DETAIL JRNL ENTRY/ POSTING DATE ---- POSTED ANODNT ---- CC TP DESCRIPTION DESCRIPTION INVOICE JOURNAL POSTED BILLINGS COSTS 01 General Conditions 01565 Winter Protection .00 E SO RENTAL - W/E 01/31/07 EQ-420 02/18/07 10,891.12 E EQ RENTAL - W/E 02/28/07 EQ-424 03/19/07 240.76 E EQ RENTAL - W/E 03/31/07 EQ-428 04/18/07 13,137.25 G Rental Service Corp Propane fuel 31557789-003 PJ-22522 04/13/07 43.07 G Rental Service Corp LPG Fuel service-02/02/07 31560586-001 PJ-22138 02/16/07 763.14 G Barnaco West, Inc. Hydraulic speed plug/boots BARE 1014132 PJ-22218 03/05/07 236.42 G Big R of Greeley Thermometers/lighters 1904919 PS-22218 03/05/07 62.90 R United Rentals Ground heater 1/10-3/7/07 62062065-001 PS-22088 03/08/07 8,141.88 A United Rentals Ground heater 2/7-3/7/07 62062065-002 PJ-22341 03/19/07 8,003.60 R United Rentals Ground heater FINAL BILL 62062065-003 PJ-22341 03/19/07 76.76 A Rental Service Corp Propane fuel 31434953-001 PJ-22274 03/13/07 540.31 R Rental Service Corp Propane fuel - 01/23/07 31445585-001 PJ-22159 02/20/07 521.16 R Rental Service Corp Propane fuel 31557789-001 PJ-22274 03/13/07 489.26 R Rental Service Corp Propane tank rntl thr 03/02/0731557789-002 PJ-22522 04/13/07 171.24 R Rental Service Corp Propane 31585016-001 P3-22522 04/13/07 1,180.61 R Rental Service Corp Propane rntl thru 03/12/07 31649292-001 PJ-22522 04/13/07 276.54 R Rental Service Corp Propane tank rntl thr 03/08/0731649292-002 PJ-22522 04/13/07 132.42 R Equipment Savers-Mobile Fuelin Generator/heater 2001746 P3-22153 02/19/07 368.71 R Equipment Savers-Mobile Fuelin Heater/tank 2001984 PS-22153 02/19/07 490.18 T Labor Ready, Inc. Temp labor w/e 01/19/07 47772254 PJ-22150 02/19/07 876.80 T Labor Ready, Inc. Temp labor w/e 01/26/07 48192254 PJ-21150 02/19/07 1,438.50 T Labor Ready, Inc. Temp labor w/e 02/02/07 48642254 PJ-22150 02/19/07 726.10 T Labor Ready, Inc. Temp labor w/e 02/09/07 49202254 PJ-22321 03/16/07 109.60 T Labor Ready, Inc. Temp labor w/e 02/23/07 49992254 PJ-22321 03/16/07 191.80 T Labor Ready, Inc. Temp labor w/e 03/2/07 50452254 PJ-22414 03/29/07 191.80 T CLP Resources, Inc. Temp labor w/e 12/29/06 1648042 PJ-22005 01/23/07 430.00 T CLP Resources, Inc. Temp labor w/e 01/05/07 1650055 PJ-22019 01/25/07 1,720.00 T CLP Resources, Inc. Temp labor w/e 01/12/07 1650865 P3-22085 02/08/07 1,524.00 T CLP Resources, Inc. Temp labor w/e 01/19/07 1653275 PJ-22150 02/19/07 1,182.50 T CLP Resources. Inc. Temp labor w/e 01/26/07 1654569 PS-22150 02/19/07 1,730.25 T CLP Resources, Inc. Temp labor w/e 02/09/07 1657273 PJ-22274 03/13/07 1,343.75 T CLP Resources, Inc. Temp labor w/e 02/16/07 1658428 PI-22274 03/13/07 1,048.13 T CLP Resources, Inc. Temp labor w/e 02/23/07 1660104 PJ-22349 03/19/07 1,263.13 T CLP Resources, Inc. Temp labor w/e 03/02/07 1661247 PJ-22414 03/39/07 830.75 01565 Winter Protection Cost Code Subtotal 60,364.44 01 General Conditions Division Subtotal 60,364.44 0615CO - Weld County North Jail Complex Phase III Job Total 60,364.44 Cost Type Summary For Job: 0615C0 Weld County North Jail Complex Phase III TYPE DESCRIPTION BILLINGS COSTS T TEMP LABOR 14,607.11 E OWNED EQUIP 24,259.13 A RENTED EQUIP 20,392.67 G GENERAL 1,105.53 05-21-2007 10:33 Roche Constructors, Inc. PAGE: 2 BY: TARA JOB COST TRANSACTION REPORT JC\RTRANS PERIODS: September 2006 thru May 2007 Job: 0615CO Weld County North Jail Complex Phase III Highest P/R W/E Date 05/13/07 Highest B/p W/E Date 05/13/07 DIV - CLIENT/VENDOR -- DETAIL JRNL ENTRY/ POSTING DATE ---- POSTED AMOUNT ---- CC TP DESCRIPTION DESCRIPTION INVOICE JOURNAL POSTED BILLINGS COSTS Cost Type Summary For Job: 0615CO Weld County North Jail Complex Phase III (Con't) TYPE DESCRIPTION BILLINGS COSTS Cost Type Total: 60,364.44 Hello