HomeMy WebLinkAbout20081823.tiff • CHANGE ORDER NO.1 Bridge 27/66A Replacement Project Description: Replacement of existing steel bridge on WCR 27 over the Greeley Canal #2. The new bridge will be a reinforced concrete structure approximately 40' wide by 60' long. Short Elliott Hendrickson Inc. (S.E.H.) has completed the design of the new bridge. Construction bidding is scheduled for September, 2008. Owner: Weld County Public Works Department, PO Box 758, Greeley, Colorado 80632 Consultant: Short Elliott Hendrickson Inc., 2000 South Colorado Boulevard, Suite 6000, Colorado Center Tower One, Denver, CO 80222-7938 The following change is hereby made to the Contract Documents: Contract Time Extension: The original Agreement for Professional Services is extended one full year for upcoming construction. The anticipated construction services completion date is June 1, 2009. Change to Contract Scope: Engineering Construction Services shall be added to the Contract. A detailed description and cost breakdown of these services is attached. CHANGE TO CONTRACT PRICE: Original Contract Amount $170,106.38 Change Order No.1 Costs $88,934.31 Revised Contract Amount $259,040.69 CHANGE TO CONTRACT TIME: The Contract time will be increased by 365 calendar days. RECOMMENDED: JUN 3 0 2008 Owner Representative: Date: William H. Jerke, Chair Engineer: cvt 1-E Date: Co 1(0 APPROVALS: Consultant: Short Elliott Hendrickson Inc. AZ By:/�� 7)4, l/-v/ Date: 6A5/Co Title: 7/0 if'c I1Coyua Pj (Peviii.e �2vIe��rzc�L— a eys 8 -3n-vsv £'O ; 0.0 6 o 06/30 42- gJas d' -41,73 1414 SEH June 13,2008 RE: Weld County WCR 27/66A Bridge Replacement SEH No. AWELDC0801.00 Mike Bedell Weld County 1111 H Street Greeley, CO 80632 Dear Mike: This letter supplements and amends the Agreement for Professional Services between Weld County, Owner, and Short Elliott Hendrickson Inc. (SEH°) dated 9/12/07 and addresses providing services in connection with the design and construction administration of a replacement bridge for Weld County Bridge 27/66A, BRO C030-030, Project Code/SA# 14655, and related improvements (hereinafter called the "Project"). The County has requested that SEH provide services through the re-construction of the bridge. The scope of services to be provided is shown in the attached material, but generally consists of: full time construction inspection provided by Mike Shrout, material testing as outlined in the attached CDOT Form 250, and shop drawing review and other technical assistance(included in the existing contract). You will pay us a fee for these services,currently estimated to be$88,934.31, in accordance with the Agreement. This brings the total authorized fee to$259,040.69 when the design engineering fee of $170,106.38 is included. This letter, the Supplemental Letter Agreement dated April 9, 2008, and the Agreement for Professional Services dated 9/12/07 along with Exhibits A and B represent the entire understanding between you and us in respect of the Project and may only be modified in writing signed by both of us. If it satisfactorily sets forth your understanding of our agreement, please sign the enclosed copy of this letter in the space provided below and return it to us. Sincerely, SHORT ELLIOnHE� TTT HENDRICKSON INC. 77 Mark Hildahl Project Manager Accepted by: Weld County By: 1 Y -:—LLZ ?,c_J2, CX Date: (-O' I (.0 ( 0?) Authorized Client Signature Encl: Construction Services Estimate,Terracon's Fee Breakdown,CDOT 250 Form,M. Shrout's Resume Short Elliott Hendrickson Inc.,2000 South Colorado Boulevard,Suite 6000,Colorado Center Tower One Denver,CO 80222-7938 SEH is an equal opportunity employer I www.sehinc.com I 720.540.6800 I 800.490.4966 720.540.6801 fax Weld County 6/6/2008 WCB 27/66A Weld County Road 27 over Greeley Canal #2 Construction Services Estimate Construction Inspection Assume 120 days construction duration => 17 weeks Include 1 week before and after for Project Start-Up and Closeout 19 weeks total @ 40 hr/wk = 760 hours Michael Shrout's Billing Rate= 87.00 $/hour Total: $66,120.00 This includes pre-bid meeting, pre-construction meeting, and substantial completion inspection. PM, Review, &Admin PM Review Admin Hildahl Davis Osmanovic Hours 12 12 4 Rate $153.82 $166.95 $85.58 $1,845.84 $2,003.40 $342.32 Total: $4,191.56 Michael lives nearby, so no per diem is needed. Vehicle: $4.50 /hour + Mileage: 950 miles (5 miles each 760 hours $0.505 /mile way per day) $3,420.00 $479.75 Total: $3,899.75 Material Testing Terracon Estimate Testing: $14,723.00 Shop Drawing Review&Technical Assistance 30 hours for shop drawing review and technical assistance are included in existing contract, dated 9/21/07. No additional hours are included. Total Construction Management Estimate: $88,934.31 o¢ ., ., ., .. ., - N I '° a c o! a N N o a a cv O E c v a N m` m a w a ! I O Ts a o L 3 Ln Q m 0 a N O l- N N N in N 0 0 0 l 0 ' 0 NI N N N N a a o o N al O O O1 w N. ma m 'E o O o CO a ❑ _ Q r •.- •-• r r r N Q N r N N Q en m 0 0 N y j a s 2 5 L W ti .- N M O h cp Q H a O 0-2 I III n N. N N •Q N N 1. N m y l CO 2 Lou ^ N O a in a n m 0 " Q .6 N N 0 co U r r r r '., r O h N T) O co¢ Q a , C O. N g i d N O 2 o Q - a ' I III N a a a W 73 - 'a J m N tI v Nin W UC ° -1N a a r N m I a UVN a N m 0 O03 M U III N 4i. Ma- 0o. o en g w E' 'c 2 r n m c u a = o I O w w a E .i m m Tu , a` T. m o th m o - 3 t 0. F O w j P_ 9 O m o x o 12 a 0. a a a 0- E � O E C Es 0 a m 22 c m E ..1 m d 2 0 2 c a x C 311 a e r S in o fr m m N N U ° k m T. a \ li O N N N b (0 m k d E 6 A m 2 > a 69 �' o' c `�- O O t a CI - o o m 0)4.. _. `c I I ty''1 a E "o E C m L N m N O 0 6 VO N V CO 2 N o 2 p C• 2 9 m O W a, ¢ U N 0520c 2 o c 'o m I I = = 5. a .E q n N N U ! CO N N yH g 02 q „ Nre H NI a p 1 9 CO ! y C 3 I > b4 p' O i 2 a m 6.I. m 0 I a in o x 5 o '2 m I- 69 0 w W 1 p W O m m O N CO H 2 2 o C a o,2• I I U E3 N m a I a e a a LL = o w o ¢ I I o. m I E 0 e I J N LL I a ! N to� N N w It , c E E E g " I r 0 o U a w a ¢ I a to th 3 0 CO w a N I f m a) C A O O a I I I N 5, N N I I iii a y a o, E O o o t n a o N N ' Q a a m N 2 I Z E.O. E ° LL w E I a s Q NJ N oo r O o a N I C. I ¢ ` ...-1 w O O fil 2 ro o a e) in a N r-- ,. Do 0 — .— m N CO N a 2 � N N N a ` h Ts 2 m U U U y Zr y y V YO y y O y y O O V y U U T 0 v N CD 01 (� d m N N r ' r r N ' r 3- Q N 0) ,_ 0 ,- N 0) m O O C N g ❑ 0 Agri; m a w m g m 7, a m d » Y 44 m E a a r a a U c0 m c a .. W " u n Y°c u x °m m 5 c O. $ m r243 - 2 = L y 9 E o Y y o a x n E v m 2' a m t. a o m @ a Z o UT a H N N p ° - = m 2 m o m m o g o n o m o 2 E m` 01 Eaz n m o 0 m '" a E m @ @ m a m m m a m E '^ U a U v 'E W E p N. m 9 2 a o a a s 2 a a 2 a E -O O. E m v a 0 K r LTJ w 2 -, ._ 2 m _ o a '_ x a '_ o_. E c b y LI,E 2 W m N tii 55 -a m N a E o N E O Ea N N n Q (O w ° R E U ~ E a a a N N C Q Q in a t° Michael Shrout Senior Designer/Construction Inspector Experience Education Stantec Consulting,Fort Collins Co-Senior Designer. University of Colorado Boulder, Primary duties—creation of plans for roadway projects,and water Co utility/storm drainage pipelines for Environmental Infrastructure and Urban Land projects Certifications/Training ACI Concrete Field Testing Colorado Dept of Transportation,Durango& Greeley,Colorado- Technician— Grade 1 ACI Concrete Transportation Engineering/Physical Sciences Technician III.Primary duties— Construction Inspector creation of complete plans/specs packages for advertised highway RMAEC Asphalt Technician A- construction projects, including: resurfacing,minor and major widening, Laydown &Asphalt Inspector minor and major reconstruction,bridge replacement with detours, Level ICDOT Erosion Control complete virgin alignments, realignments, intersection design, Supervisor Training g interchange layout,grade and superelevation improvements,safety improvements,drainage, irrigation,cost estimates. 8 Mile Major New Alignment,US 34 at Dearfield. Design and Construction.Design and Construction.This was a complete major new alignment with a bridge over a canal. Michael performed construction inspection on the bridge,canal realignment,many irrigation structures, asphalt pavement, and wrote a large percentage of the CDOT Form 266s that measured work, allowing payment to the Contractor. 8 Mile Overlay, I-25, SH 52 to SH 66. Design and Construction/Assistant Project Engineer. This was a night paving project. Michael performed reviews of the traffic control, performed asphalt inspection,and wrote most of the CDOT Form 266s that documented work, allowing payment to the Contractor. Bridge Replacement with Detour,SH 392 E of Windsor. Design and Construction/Assistant Project Engineer. This was a bridge replacement over a canal. Michael was de facto Project Engineer and performed reviews of traffic control, performed inspection of the detour and new bridge, performed asphalt inspection,and wrote nearly all of the CDOT Form 266s that documented work,allowing payment to the Contractor. 8 Mile Overlay,I-76,Lochbuie To Hudson.Design and Construction/Assistant Project Engineer. This was a resurfacing project. Michael performed reviews of the traffic control, performed asphalt inspection, and wrote most of the CDOT Form 266s that documented work, allowing payment to the Contractor. Bridge Replacement with Detour, US 36 W/O Last Chance.Design and Construction/Assistant Project Engineer.This was a bridge replacement over a draw. Michael performed reviews of traffic control, performed inspection of the detour and new structure, performed asphalt 1 inspection,and wrote nearly all of the CDOT Form 266s that documented SEHMichael Shrout I Senior Designer/Construction Inspector I page 1 work,allowing payment to the Contractor. Additional Experience • Construction Inspector and Assistant Project Engineer • Proficient in AutoCAD,Eagle Point,COGO, etc. • Gaining experience with Bentley MicroStation and InRoads • Proficient with most Microsoft Office applications • Familiar with CDOT specifications and practices,AASHTO standards, MUTCD SEE' Michael Shrout I Senior Designer/Construction Inspector I page 2 BOARD OF COUNTY COMMISSIONERS REVIEW/WORK SESSION REQUEST RE: Construction Services Change Order for Bridge 27/66A Replacement DEPARTMENT: PUBLIC WORKS DATE: 6/18/08 PERSON REQUESTING: Wayne Howard, Engineering Division Brief description of the problem/issue: Weld County received federal funds for the replacement of Bridge 27/66A. The design is now complete, and R.O.W./Easements acquisition is ongoing. The project is scheduled to be bid out in September 2008. Construction is scheduled to be completed in May, 2009. Public Works is recommending that Short Elliott Hendrickson Inc., the consultant who completed the design, be utilized for construction services. The construction services will entail daily inspection, materials quality control, and documentation. This work requires an inspector who is familiar with CDOT regulations and paperwork requirements. What options exist for the Board: The cost for the work was negotiated and the proposed Change Order No.1 amount is $88,934.31. Weld County's portion of this amount is 20% ($17,786.86), and the federal funds cover the remaining 80%. The Board could either accept or not accept the Change Order No.1. Not accepting this change order could result in the bridge replacement project not meeting completion deadlines, and Public Works would be required to seek an alternate means of accomplishing the construction services work. Recommendation to the Board: I recommend approval for the Change Order No.1. Approval will allow the project to proceed in a timely manner, and ensure inspection by a well-qualified individual. The proposed cost is reasonable when compared to similar completed projects and industry standards. Approve Schedule Recommendation Work Session Comments William H. Jerke, Chair c/ Robert D. Madsen, Pro-Tem V William F. Garcia Vl.4 David E. Long J Douglas Rademacher Attachments: Change Order (11.- , MEMORANDUM TO: Clerk to the Board DATE: June 23, 2008 FROM: Wayne Howard, Chief Senior Engineer, Public Works COLORADO SUBJECT: Agenda Item Change Order No. 1 for Bridge 27/66A Replacement Project with Short Elliott Hendrickson Attached are TWO original Change Order No. 1. PLEASE RETURN ONE ORIGNAL TO PUBLIC WORKS as soon as it is signed. pc: Mike Bedell, Engineering M:\Francie\Agenda Wayne Howard.doc 2008-1823 Hello