HomeMy WebLinkAbout20082579.tiff a rs MEMORANDUM 1 CTO: Clerk to the Board DATE: September 19, 2008 • COLORADO FROM: Wayne Howard, County Engineer/CIP, Public Works SUBJECT: CONSENT AGENDA ITEM Work Order Form No. 6 with Short Elliot Hendrickson for the Bridge 13/54A Replacement Project in the amount of$49,347.70. Attached are two original Work Order Form No. 6 documents. Please return one signed original to Public Works. pc: Mike Bedell,Public works M:\Francie\Agenda Wayne Howard.doc •.,1 OO L E00.54)Cvow �lvt1 a 2008-2579 bbl d(l : /Id( r-t.; r WORK ORDER FORM PURSUANT TO AN AGREEMENT BETWEEN WELD COUNTY AND SHORT ELLIOTT HENDRICKSON INC. DATED: 9-03-08 Work Order Number: SEH-6 Project Title: Bridge 13/54A Replacement Commencement Date: November 1,2008 Completion Date: July I, 2009 Limitations on compensation: Total Contract Not to Exceed $49,347.70. (Weld County Cost-Share portion of this project is approximately 10%). Project Description: Assisting Weld County with Construction Inspection services. This Federal-Aid project requires the services of an inspector with sufficient knowledge and certifications to fulfill all of the required duties. The same inspector will be assisting Weld County with the construction of Bridge 27/66A. It is anticipated that both projects will follow similar schedules starting in December, 2008 and completion by the summer of 2009. Scope of Services: See attached Construction Services Estimate Professional agrees to perform the services identified above and on the attached forms in The attached forms are hereby accepted and accordance with the terms and conditions incorporated herein, by this reference, and contained herein and in the Professional Notice to Proceed is hereby given. Services Agreement between the parties. In the event of a conflict between or ambiguity in the terms of the Professional Services Agreement Weld County and this work order (including the attached forms) the Professional Services Agreement By: Michael Bedell P.E.-Senior Engineer shall control. Date: `'13 O8 Professional By: / Y Ozr Depa tment Head Short Elliott Hendrickson Inc. Date: • r+ —"re' 2000 South Colorado Blvd., 6000 �� Colorado Center Tower One By: Denver, CO 22-79 Direct r f inane and Administration Date: 09 24/2008 By: /J�/ /'"/'t//1/CiA•¢L By:Chairman, O< n Z� Titl Chairman, Weld County Commissioners (Pro—Tern) Date: 09/24/2008 Date: D 9. 9• Ff c200d-a6-2 ' c Weld County 7/31/2008 WCB 13/54A Weld County Road 13 over Big Thompson River Construction Services Estimate Construction Inspection Assume 150 days construction duration =>21 weeks Include 1 week before and after for Project Start-Up and Closeout Michael Shrout will be working nearby on WCB 27/66A for 19 weeks. 23 weeks @ 20 hr/wk = 460 hours Michael Shrout's Billing Rate = 87.00 $/hour Total: $40,020.00 This includes pre-bid meeting, pre-construction meeting, and substantial completion inspection. PM, Review, &Admin PM Review Admin Hildahl Davis Osmanovic Hours 15 15 5 Rate $153.82 $166.95 $85.58 $2,307.30 $2,504.25 $427.90 Total: $5,239.45 Michael lives nearby, so no per diem is needed. Vehicle: $4.50 /hour + Mileage: 3450 miles (15 miles each 460 hours $0.585 /mile way per day) $2,070.00 $2,018.25 Total: $4,088.25 Material Testing Material Testing will be provided under a separate contract, and is not included. Shop Drawing Review &Technical Assistance It is assumed that shop drawing review and technical assistance will be provided by the design engineer, and are not included. Total Construction Management Estimate: $49,347.70 r Michael Shrout Senior Designer/Construction Inspector Experience Education Stantec Consulting,Fort Collins Co- Senior Designer. University of Colorado Boulder, Primary duties—creation of plans for roadway projects, and water co utility/storm drainage pipelines for Environmental Infrastructure and Urban Land projects Certifications/Training ACI Concrete Field Testing Colorado Dept of Transportation,Durango& Greeley, Colorado- Technician—Grade t Engineering/Physical Sciences Technician III.Primary duties— ACI Concrete Transportation creation of complete plans/specs packages for advertised highway Construction Inspector RMAEC Asphalt Technician A- construction projects, including: resurfacing,minor and major widening, Laydown &Asphalt Inspector minor and major reconstruction,bridge replacement with detours, Level ICDOT Erosion Control complete virgin alignments, realignments, intersection design, Supervisor Training interchange layout,grade and superelevation improvements, safety improvements,drainage, irrigation, cost estimates. 8 Mile Major New Alignment,US 34 at Dearfield.Design and Construction.Design and Construction.This was a complete major new alignment with a bridge over a canal. Michael performed construction inspection on the bridge, canal realignment,many irrigation structures,asphalt pavement, and wrote a large percentage of the CDOT Form 266s that measured work, allowing payment to the Contractor. 8 Mile Overlay,I-25,SH 52 to SH 66.Design and Construction/Assistant Project Engineer.This was a night paving project. Michael performed reviews of the traffic control,performed asphalt inspection,and wrote most of the CDOT Form 266s that documented work,allowing payment to the Contractor. Bridge Replacement with Detour,SH 392 E of Windsor.Design and Construction/Assistant Project Engineer.This was a bridge replacement over a canal. Michael was de facto Project Engineer and performed reviews of traffic control,performed inspection of the detour and new bridge,performed asphalt inspection, and wrote nearly all of the CDOT Form 266s that documented work, allowing payment to the Contractor. 8 Mile Overlay,1-76,Lochbuie To Hudson.Design and Construction/Assistant Project Engineer.This was a resurfacing project. Michael performed reviews of the traffic control,performed asphalt inspection,and wrote most of the CDOT Form 266s that documented work,allowing payment to the Contractor. Bridge Replacement with Detour,US 36 W/O Last Chance.Design and Construction/Assistant Project Engineer.This was a bridge replacement over a draw. Michael performed reviews of traffic control, performed inspection of the detour and new structure,performed asphalt inspection,and wrote nearly all of the CDOT Form 266s that documented SEli Michael Shrout I Senior Designer/Construction Inspector I page 1 work,allowing payment to the Contractor. Additional Experience • Construction Inspector and Assistant Project Engineer • Proficient in AutoCAD,Eagle Point,COGO,etc. • Gaining experience with Bentley MicroStation and InRoads • Proficient with most Microsoft Office applications • Familiar with CDOT specifications and practices,AASHTO standards, MUTCD SEEMichael Shrout I Senior Designer/Construction Inspector I page 2 BOARD OF COUNTY COMMISSIONERS REVIEW/WORK SESSION REQUEST RE: Bridge 13/54A Construction Services DEPARTMENT: PUBLIC WORKS DATE: 9/12/08 PERSON REQUESTING: Wayne Howard, P.E., County Engineer/CIP Brief description of the problem/issue: The 13/54A Bridge over the Big Thompson River is scheduled for construction in November 2008 through May 2009. This Federal-Aid project requires the services of an inspector with sufficient knowledge and certifications to fulfill all of the required duties. We recommend using our current On-Call Engineering Consultant (Short Elliott Hendrickson Inc.) for these services since they have qualified staff located in the Greeley area. The same inspector will be assisting Weld County with the construction of Bridge 27/66A simultaneously, which will reduce the overall inspection costs. Weld County cost-share portion of this project is approximately 10%. What options exist for the Board? (Include consequences, impacts, costs, etc. of options) The Board could choose to not approve this Work Order. The Public Works Department would then have to seek out professional services from another consultant. Approval of the Work Order will allow the construction to proceed on schedule, and ensure that a qualified individual is overseeing the construction. Recommendation to the Board: Attached is Work Order No. 6 with S.E.H. whom would perform the work. I recommend approval of the Work Order. The hourly rates and associated costs are reasonable. Approve Schedule Recommendation Work Session Comments William H. Jerke, Chair \1v Robert D. Masden, Pro-Tem William F. Garcia CAA David E. Long J Douglas Rademacher Attachments: Work Order No. 6 Hello