September 14, 2009
Laboratory Services Division
8100 Lowry Blvd.
Denver, Colorado 80230-6928
(303) 692-3090
Certified Mail No: 7007 0220 00010162 4840
Return Receipt Requested
Mr. John Moser
Stromo LLC6600 W. 20th St #11
Greeley, CO 80634
RE: Informal Conference Held Pursuant to August 6, 2009 Compliance Advisory
Stromo Compost Facility, Weld County, Colorado
SW/WLD SCF 1.6
Dear Mr. Moser:
Colorado Department
of Public Health
and Environment
Thank you very much for taking the time to meet with Department representatives on September 10, 2009 to discuss
resolution of the Compliance Advisory. According to what we discussed during the meeting and what you documented in
your August 31, 2009 response to the Compliance Advisory, the facility appears to be taking steps toward a return to
compliance. Based on our discussion, deficiencies 2, 3 and 5 from the Compliance Advisory appear to have already been
remedied. The documentation related to Deficiency 6 is under review by the Department. As for the remaining items, the
following schedule was agreed to during the conference.
1. Deficiency 1, Requested Action la: Within sixty (60) calendar days of September 14, 2009, complete regrading of
the site and re -orientation of windrows toward the stormwater drainage ditch. This work will be completed by
November 13, 2009.
2. Deficiency 1, Requested Action 1b: Within thirty (30) calendar days of September 14, 2009, a revised engineering
design for the stormwater controls at the site will be submitted to the Department and Weld County. This submittal
will be received by October 14, 2009. The engineering design submittal shall include a construction schedule.
3. Deficiency 1: Construction of the approved revisions referenced in #2 above will commence on or before May 15,
2010 and be completed on or before August 15, 2010.
4. Deficiency 4: Results from analytical testing on the balance of the finished compost on site will be submitted to the
Department within fourteen (14) calendar days. This submittal wiii be received by September 24, 2009.
If you should have any questions, please feel free to call me at 303-692-3455.
Sincerely,
enderson
olid Waste and Material Management Unit
Solid and Hazardous Waste Program
cc.
Weld County Commissioners
Doug Ikenberry, HMWMD
Lindsay Sartorius, AgPro
Troy Swain, WCDPHE
(/7,/27fA// r 77c, ✓S
(.7 L23-
2009-2533