HomeMy WebLinkAbout20093396.tiffCHANGE ORDER AM DOCUMENT G701 OWNER ARCHITECT CONTRACTOR FIELD O"i l IER X x X RCI Project # 0818CO PROJECT: (name, address) TO CONTRACTOR Weld County Social Services Building B 315 North 1 Ith Avenue Greeley, CO 80631 ROCHE CONSTRUCTORS, INC. Post Office Box 1727 Greeley, CO 80632 The Contract is changed as follows: CHANGE ORDER NUMBER: Four DATE: ARCHITECT'S PROJECT NO: CONTRACT DATE: 8/12/2008 CONTRACT FOR: Change Order Request No. 003 - Supply and install additional exit lights with battery backup and self diagnostics as required by Weld County Building Inspector. Includes labor to install (I) owner supplied exit light Total 12/21/2009 Construction $1,865.00 $1,865 00 Not valid until signed by Owner, Architect, and Contractor The original (Contract Sum) was $4,776,700.00 Net change by previously -authorized Change Orders $285,763.00 The (Contract Sum)(Guaranteed Maximum Price) prior to this Change Order was $5,062,463.00 The (Contract Sum) will be increased by this Change Order in the amount of $1,865.00 The new (Contract Sum) including this Change Order will be $5,064,328.00 The Contract Time will be N/A by ( -0- ) days. The date of Substantial Completion as of the date of this Change Order thereof is NOTE: This summary does not reflect changes in the Contract Sum, Contract Time, or Guaranteed Maximum Price which have been authorized by Construction Change Directive. HAUSER ARCHITECTS, P.C. ROCHE CONSTRUCTORS, INC. ARCHITECT CONTRACTOR By dia ISFIQ / Alan Hauser Date 22./a) P. 0. Box 1727 Greeley, CO 80632 Joey M. Fliers Date 12/21/2009 WELD COUNTY OWNER as Rad coacher, Pro - Date D 282 9 AIA DOCUMENT G701 • CHANGE ORDER • 1987 EDITION • AIM® • ©1987 • THE AMERICAN INSTITUTE OF ARCIIITECTS. 1735 NEW YORK AVE.. NW.. WASHINGTON. D.C. 20006 G701-1987 ,230/-.3304: ROCHE CONSTRUCTORS, INC. CHANGE ORDER REQUEST SUMMARY SHEET Weld County Social Services Building B Remodel 315 N. 111th Avenue Greeley, CO Roche Project No. 0818OO RCI's COR # 003 Date: December 21, 2009 Description of Change: Supply and install (7) each additional Lithonia LQMSW3G120/277ELNSD Exit Lights with battery backup and self diagnostics as required by Weld County Building Inspector as a life safety requirement. Includes all labor, materials and overnight charges to expedite shipment in order to install fixtures in time for required re -inspections. Cost also includes labor to install (1) owner supplied exit light. Company Amount Warkenfin Electric Sub -Total $ 1,691.00 $ $ 1,691.00 Roche Constructors Breakdown: Sub -Totals Taxes (0% mat'I; 50.00% labor burden) Sub -Total RCI Total $ Material 0 Sub/Equip $ Labor $ 0.00 0 0.00 0.00 0.00 Summary: Subcontractor Totals Overhead on Sub Work (5%) Profit on Sub Work (5%) RCI Work Mark -Up on RCI Work (10%) Sub -Total Payment & Performance Bond (.8%) General Liability Insurance (.55%) 1,691.00 85.00 89.00 0.00 0.00 1,865.00 0.00 0.00 Total: Total $ 1,865.00 This price is good for seven (7) days. Time extension required for this work: 0 days. Approved alolj..te Dou as Rademacher Chair Pro-T•m Weld County Board of Commissioners Date DEC 2 8 2009 WARKENTIN ELECTRIC 1531 4TH AVENUE GREELEY, CO 80631 CSSIC. Gotit005 NAME/ADDRESS ROCK CONSTRUCTORS 361 71ST AVE GREELEY, CO 80634 CHANGE ORDER DATE CHANGE OR... 12/17/2009 586 Project WELD COUNTY SOCIAL SERVICES ADDITIONAL EMERGENCY LIGHTS P.O. NO. PROJECT DESCRIPTION QTY TOTAL ELECTRICIAN 7 420.00 MISC MATERIAL 7 105.00 LQMSW3G120/277ELNSD - EXIT LIGHT WITH BATTERY BACKUP & SELF 7 946.40 DIAGNOSTICS ESTIMATED OVERNIGHT CHARGES I 145.00 LABOR (CORY) INSTALL OWNER PROVIDED EMERGENCY LIGHT I 60.00 MISC MATERIAL FOR INSTALLING OWNER PROVIDED LIGHT I 15.00 TOTAL $1,691.40 SIGNATURE Doug as Ra.emacher, Chair Pro —Ti Weld Count Board of Commissioni 0E 2 8 2009 Joey Hiers From: Sent: To: Subject: Toby Taylor [TTaylor@co.weld.co.us] Friday, December 18, 2009 12:52 PM Joey Hiers RE: 0818CO Weld Co. Bldg B COR 003 Please proceed with the installations identified in COR 003 Toby Taylor Building Maintenance Coordinator Voice: (970) 304-6531 Fax: (970) 304-6532 1105 H Street P.O. Box 758 Greeley, CO 80632 Original Message From: Joey Hiers [mailto: jhiers@rocheconstructors.com] Sent: Friday, December 18, 2009 12:50 PM To: Toby Taylor Subject: 0818CO Weld Co. Bldg B COR 003 Toby - Attached please find Change Request No. 003 and associated backup regarding installation of the additional exit signs for Weld Co. Bldg. B. You can either sign, scan and fax back or email me authorizing the work to proceed. If you should have any questions or need anything, please contact me. Thanks. Joey M. Hiers Project Manager Roche Constructors, Inc. Greeley, Colorado Phone 970.356.3611 Fax 970.356.3619 www.rocheconstructors.com <http://console.mxlogic.com/redir/?5-VEVuuvohdIIFLT7e9CM0kqS9 _gIajyTgtoQVv3t-huuK-Vt5xUTsS8AVv6wazmNfXlxismXj H6DbCTxRNMUSyCUyyU- ZtUSPsTtV5Ui31Ew0nPQ3h091UQg39W14Qg39Ew4wM2Ph1uX9KvxYY1NJ4SyrppjvKehhd-e5aP4c> P Do you need to print this email? Think green! 1 Hello