HomeMy WebLinkAbout20093776.tiffGEOTECHNICAL ENGINEERING REPORT
PROPOSED PUMP HOUSE AND SEPARATOR FACILITY
SOUTHEAST OF WELD COUNTY ROAD 49 AND WELD COUNTY ROAD 34
WELD COUNTY, COLORADO
Terracon Project No. 21095002
June 17, 2009
Prepared for:
LAMP RYNEARSON & ASSOCIATES, INC.
808 8T" STREET
GREELEY, COLORADO 80631
Attn: Mr. Daniel Hull, P.E.
Prepared by:
Terracon Consultants, Inc.
301 North Howes Street
Fort Collins, Colorado 80521
Phone: 970-484-0359
Fax: 970-484-0454
lierracon _
/4/a8/.2,04y
dot) Q-377,
PLA031
lrerracon
June 17, 2009
Lamp Rynearson & Associates
808 8th Street
Greeley, Colorado 80631
Attn: Mr. Daniel Hull, P.E.
Re: Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Southeast of Weld County Road 49 and Weld County Road 34
Weld County, Colorado
Terracon Project No. 21095002
Terracon Consultants, Inc. (Terracon) has completed the geotechnicai engineering study for the
proposed pump house and separator facility to be located southeast of Weld County Road 49
and Weld County Road 34 in Weld County, Colorado. This study was performed in general
accordance with our proposal number P2108044 dated May 20, 2009.
The results of our engineering study are attached. These results include the Boring Location
Diagram, laboratory test results, Logs of Boring, and the geotechnical recommendations needed
to aid in the design and construction of foundations and other earth connected phases of this
project.
We appreciate being of service to you in the geotechnical engineering phase of this project, and
are prepared to assist you during the construction phases as well. Please do not hesitate to
contact us if you have any questions concerning this report or any of our testing, inspection,
design and consulting services.
Sincerely,
TERRACON CONSULTANTS, INC.
Christopher M. -mperline
Staff Geologis r Geotechnical Services Department Manager/ Gea echnical Services
Joels C. Malama, P.
Reviewed by: Brent Wilkens, P.E.
Department Manager / Geotechnical Services
Copies to: Addressee (5)
Terracon Consultants, Inc. 301 North Howes Street Fort Collins, Colorado 80521
P [970] 484 0359 F [970] 484 0454 terracon.com
Geotechnical ■ Environmental ■ Construction Materials • Facilities
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 2/095002
Terracon
TABLE OF CONTENTS
Page No.
Letter of Transmittal ii
INTRODUCTION 1
SITE EXPLORATION 2
Field Exploration 2
Laboratory Testing 3
SITE CONDITIONS 3
Soil and Bedrock Conditions 4
Field and Laboratory Test Results 4
Groundwater Conditions 5
ENGINEERING RECOMENDATIONS 5
Geotechnical Considerations 5
Separator Tanks Foundation 5
Modular Office and Injection Building Foundations 6
Lateral Earth Pressures 7
Seismic Considerations 7
Floor Slab Design and Construction 7
Gravel Roadway Design and Construction 8
Concrete Truck Unloading Pad Construction 9
Earthwork 10
General Considerations 10
Site Preparation 10
Subgrade Preparation 11
Fill Materials and Placement 11
Excavation and Trench Construction 12
Additional Design and Construction Considerations12
Exterior Slab Design and Construction 12
Corrosion Protection 13
Surface Drainage 13
GENERAL COMMENTS 14
iii
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
TABLE OF CONTENTS (cont.)
BORING LOCATION DIAGRAM Figure No. I
APPENDIX A: LOGS OF BORING
APPENDIX B: LABORATORY TEST RESULTS
APPENDIX C: GENERAL NOTES
iv
GEOTECHNICAL ENGINEERING REPORT
PROPOSED PUMP HOUSE AND SEPARATOR FACILITY
SOUTHEAST OF WELD COUNTY ROAD 49 AND WELD COUNTY ROAD 34
WELD COUNTY, COLORADO
Terracon Project No. 21095002
June 17, 2009
INTRODUCTION
This report contains the results of our geotechnical engineering exploration for the proposed
project to be located south and east of Weld County Road 49 and Weld County Road 34 in
Weld County, Colorado.
The purpose of these services is to provide information and geotechnical engineering
recommendations relative to:
• subsurface soil and bedrock conditions
• groundwater conditions
• foundation design and construction
• lateral earth pressures
• floor slab design and construction
• roadway construction
• septic systems
• earthwork
• drainage
The recommendations contained in this report are based upon the results of field and laboratory
testing, engineering analyses, our experience with similar soil conditions and structures, and our
understanding of the proposed project.
PROJECT INFORMATION
Terracon understands the site will be developed with a pump house and 10 to 13 separator
tanks. Additional infrastructure on the site will consist of a modular office building, a wood
framed injection building, gravel access roads, and an individual sewage disposal system
(I.S.D.S.) to service the office building. We understand that the separator tanks will be
approximately 10 to 15 feet in diameter with a 30,000 gallon total tank capacity. It is our
understanding that the separator tanks are planned to be supported by one mat foundation.
Other site development may consist of paving a portion of the proposed access road with
concrete for use as a truck unloading pad. Based on conversations with a representative of the
client the concrete pad and the I.S.D.S. will be designed by other design team members.
1
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
Final site grading plans were not available prior to preparation of this report. However, we
assume cuts or fills will be 3 feet or less.
SITE EXPLORATION PROCEDURES
The scope of the services performed for this project included site reconnaissance by an
engineering geologist, a subsurface exploration program, laboratory testing and engineering
analysis.
Field Exploration: A total of 11 test borings were drilled on May 21, 2009 to depths of about 3
to 30 feet below existing site grade at the approximate locations shown on the Boring Location
Diagram, Figure 1. Two borings were drilled within or near the footprint of the proposed
separator tank mat foundation, one boring was drilled within or near the footprint of the injection
building, one boring was drilled within or near the footprint of the proposed modular office
structure and the area of proposed concrete un-loading pad. One soil profile boring and 6
percolation test holes were drilled in the location of the proposed septic system. Percolation
tests were conducted in accordance with Weld County requirements.
The borings were drilled with a CME-55 truck -mounted rotary drill rig with solid -stem augers.
Lithologic logs of the borings were recorded by the engineering geologist during the drilling
operations. At selected intervals, relatively undisturbed samples of the subsurface materials
were obtained by driving a standard penetration sampler (SS) and ring barrel samplers (RS).
Penetration resistance values were recorded in a manner similar to the standard penetration test
(SPT). This test consists of driving the sampler into the ground with a 140 -pound hammer free -
falling through a distance of 30 inches. The number of blows required to advance the sampler 12
inches or the interval indicated, is recorded and can be correlated to the standard penetration
resistance value (N -value). The blow count values are indicated on the boring logs at the
respective sample depths, ring barrel sample blow counts are not considered N -values.
A CME automatic SPT hammer was used to advance the samplers in the borings performed on
this site. A greater efficiency is typically achieved with the automatic hammer compared to the
conventional safety hammer operated with a cathead and rope. Published correlations between the
SPT values and soil properties are based on the lower efficiency cathead and rope method. This
higher efficiency affects the standard penetration resistance blow count value by increasing the
penetration per hammer blow over what would be obtained using the cathead and rope method.
The effect of the automatic hammer's efficiency has been considered in the interpretation and
analysis of the subsurface information for this report.
2
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 2/095002
Terracon
The standard penetration test provides a reasonable indication of the in -place density of sandy
type materials, but only provides an indication of the relative stiffness of cohesive materials
since the blow count in these soils may be affected by the moisture content of the soil. In
addition, considerable care should be exercised in interpreting the N -values in gravelly soils,
particularly where the size of the gravel particle exceeds the inside diameter of the sampler.
Groundwater measurements were made in each boring at the time of site exploration, and
several days after drilling.
Laboratory Testing: Samples retrieved during the field exploration were returned to the
laboratory for observation by the project geotechnicai engineer, and were classified in general
accordance with the Unified Soil Classification System described in Appendix C. Samples of
bedrock were classified in accordance with the general notes for Rock Classification. At that
time, an applicable laboratory -testing program was formulated to determine engineering
properties of the subsurface materials. Following the completion of the laboratory testing, the
field descriptions were confirmed or modified as necessary, and Logs of Borings were prepared.
These logs are presented in Appendix A.
Laboratory test results are presented in Appendix B. These results were used for the
geotechnical engineering analyses and the development of foundation, roadway, and earthwork
recommendations. Laboratory tests were performed in general accordance with the applicable
local or other accepted standards.
Selected soil and bedrock samples were tested for the following engineering properties:
• Water content
• Dry density
• Consolidation
• Expansion
SITE CONDITIONS
• Grain size
• Plasticity Index
• Water soluble sulfate content
At the time of drilling operations the site consisted of open pasture land. The site was bounded
on the north by Weld County Road 34, on the east and west by ranch land with single family
ranch houses with associated out buildings and ranch equipment, and on the south by cattle
pasture. Vegetation consisted of a native grass and weed growth. Weld County Road 49 is
located beyond to the west. The ground surface was generally sloped to the south and west on
a majority of the site. The east portion of the site is sloped to the south and east with a natural
drainage along the east border. Based on the site diagram provided by the client, the site
exhibits approximately 20 feet of relief from Weld County Road 34 to the proposed injection
building location.
3
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
Soil and Bedrock Conditions: As presented on the Logs of Borings, poorly graded sand with
varying amounts of silt was encountered at the surface and extended to depths of about 13 to
26 feet below existing site grade. Clay with varying amounts of sand was encountered below
the sand material in Test Borings Nos. 3 and 4 and extended to a depth of about 19-1/2 feet
below existing site grade. Claystone bedrock was encountered below the sand and clay
overburden soils and extended to the full depth of exploration of about 25 to 30 feet below site
grade.
Field and Laboratory Test Results: Field test results indicate that the sand soils vary from
very loose to medium dense in relative density. The clay soils vary from medium stiff to stiff in
consistency. Laboratory test results indicate that subsoils at shallow depth have non- to low
expansive potential. Laboratory tests indicate a negligible water soluble sulfate content of less
than 100 ppm.
Percolation testing conducted in the area of the proposed soil absorption bed is summarized as
follows:
Test
Hole
Soil Type at
Approximate Bottom of
Percolation field
Depth to
Bedrock {ft.)
Depth to
Groundwater
{ft.}
Percolation
Rate
(min. /in.)
P4
Poorly Graded Sand
Not
encountered
Not
encountered
4
P2
Poorly Graded Sand
Not
encountered
Not
encountered
4
P3
Poorly Graded Sand
Not
encountered
Not
encountered
6
-
P4
Poorly Graded Sand
Not
encountered
Not
encountered
3
P5
Poorly Graded Sand
Not
encountered
Not
encountered
1
P6
Poorly Graded Sand
Not
encountered
Not
encountered
7
Field test results indicate that a standard septic system and leach field (soil absorption bed) is
feasible for construction on the site at the location of percolation test holes 1 through 6. The
system should be designed in accordance with Weld County Individual Sewage Disposal
System Regulations dated August 15, 2005. An average percolation rate of four (4) minutes per
inch is recommended for design purposes. Based upon Weld County Individual Sewage
Disposal System Regulations dated August 15, 2005, a percolation rate faster than five (5)
minutes per inch is considered un-acceptable for a soil absorption bed. However sandy soils
that percolate faster than five (5) minutes per inch, but slower than three (3) munites per inch,
may be allowed if requirements of section 30-5-30.A.2.a are met.
Groundwater was not encountered in the soil profile boring located at the proposed soil
absorption bed. According to Weld County Individual Sewage Disposal System Regulations
4
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
Sec. 30-5-40 A.2.b, systems may not be permitted or installed in areas where the maximum
seasonal level of the groundwater table is less than four (4) feet below the bottom of the
proposed absorption system. Under this condition the septic system must be designed by a
Registered Professional Engineer.
Groundwater Conditions: Groundwater was encountered at depths of about 28 to 29 feet
below existing site grade in the test borings at the time of field exploration. When checked
several days after drilling, groundwater was measured at depths of about 16 to 18 feet below
existing site grade. These observations represent groundwater conditions at the time of the field
exploration, and may not be indicative of other times or at other locations. Groundwater levels
can be expected to fluctuate with varying seasonal and weather conditions.
ENGINEERING RECOMMENDATIONS
Geotechnical Considerations: Based on the results of our field investigation, laboratory
testing program and geotechnical analyses, development of the site is considered feasible from
a geotechnical standpoint provided that the conclusions and recommendations provided herein
are incorporated into the design and construction of the project.
Areas of very loose to loose sand soils will require particular attention in the design and
construction of the project. Due to the presence very loose to loose sand soils we recommend
that foundation and pavement elements bear on a minimum of 3 feet of moisture conditioned
and recompacted and/or replacement with non- to low expansive onsite or imported materials.
Design and construction recommendations for the foundation system and other earth connected
phases of the project are outlined below:
Separator Tanks Foundation: A mat foundation bearing on a minimum of 3 feet of moisture
conditioned and recompacted and/or replacement with non- to low expansive onsite or imported
materials is recommended for support of the proposed separator tanks and pumps. The
foundation may be designed for a maximum allowable bearing pressure of 1,500 pounds per
square foot (psf). We understand the tanks will be supported on a single mat. If this is incorrect
we should be contacted to modify our recommendations.
Total movement resulting from the assumed structural loads is estimated to be on the order of 1
to 2 inches. Additional foundation movements could occur if water from any source infiltrates
the foundation soils; therefore, proper drainage practices should be incorporated into the design
and operation of the facility. Failure to maintain soil water content will nullify the movement
estimates provided above.
For structural design of mat foundations, a modulus of subgrade reaction of 100 pounds per
cubic inch (poi) may be used. Other details including treatment of loose foundation soils and
5
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
observation of foundation excavations are applicable for the design and construction of the
foundation at the site and are outlined below.
Exterior foundations should be placed a minimum of 30 inches below finished grade for frost
protection and to provide confinement for the bearing soils. Finished grade is the lowest
adjacent grade for perimeter footings.
Modular Office and Injection Building Foundations: Due to the presence of very loose to
loose sand soils on the site, spread footing foundation systems bearing upon a minimum of 3
feet of moisture conditioned and recompacted and/or replacement with non- to low expansive
onsite or imported materials are recommended for support of the proposed modular office and
injection buildings. The footings may be designed for a maximum bearing pressure of 1,500
pounds per square foot (psf). The design bearing pressure applies to dead loads plus design
live load conditions. The design bearing pressure may be increased by 1/3 when considering
total loads that include wind or seismic conditions.
Footings should be proportioned to relative constant dead load pressure in order to reduce
differential movement between adjacent footings. Total movement resulting from the assumed
structural loads is estimated to be on the order of about 1 inch. Additional foundation
movements could occur if water from any source infiltrates the foundation soils; therefore,
proper drainage should be provided in the final design and during construction.
Foundations should be placed a minimum of 30 inches below finished grade for frost protection
and to provide confinement for the bearing soils. Finished grade is the lowest adjacent grade
for perimeter footings.
Footings, foundations and masonry walls (if used) should be reinforced as necessary to reduce
the potential for distress caused by differential foundation movement. The use of joints at
openings or other discontinuities in masonry wails is recommended.
Foundation excavations or new fill placement operations should be observed by the
geotechnical engineer. If the soil or fill conditions encountered differ significantly from those
presented in this report, supplemental recommendations will be required.
6
Geotechnicai Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
Lateral Earth Pressures: For soils above any free water surface, recommended equivalent
fluid pressures for unrestrained foundation elements are:
= Active:
Cohesive soil backfill (clays) 55 psflft
Cohesioniess soil backfill (sands) 35 psf/ft
• Passive:
Cohesive soil backfill (clays) 225 psf/ft
Cohesionless soil backfill (sands) 350 psf/ft
• Coefficient of base friction 0.35*
*The coefficient of base friction should be reduced to 0.30 when used in conjunction with
passive pressure.
Where the design includes restrained elements such as pit walls, the following equivalent fluid
pressures are recommended:
• At rest:
Cohesive soil backfill (clays) 75 psf/ft
Cohesioniess soil backfill (sands) 55 psf/ft
The lateral earth pressures herein do not include any factor of safety and are not applicable for
submerged soils/hydrostatic loading. Additional recommendations may be necessary if
submerged conditions are to be included in the design.
Fill against foundations should be compacted to densities specified in the "Earthwork" section of
this report. Compaction of each lift adjacent to walls should be accomplished with hand -
operated tampers or other lightweight compactors. Overcompaction may cause excessive
lateral earth pressures which could result in wall movement.
Seismic Considerations: A site classification "C" should be used for the design of structures
for the proposed project (2006 International Building Code, Table No. 1613.5.2).
Floor Slab Design and Construction: Slab -on -grade construction for interior floor systems is
generally considered acceptable when bearing a minimum of 3 feet of moisture conditioned and
recompacted and/or replacement with non- to low expansive onsite or imported materials,
provided that some movement can be tolerated. Movement on the order of about one inch is
possible. Use of structural floor systems, structurally supported independent of the subgrade
soils, is a positive means of reducing the potentially detrimental effects of floor movement.
7
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
For structural design of concrete slabs -on -grade, a modulus of subgrade reaction of 100 pounds
per cubic inch (pci) may be used for floors supported on existing sand soils or non -expansive,
imported fill meeting the specifications outlined below.
Additional floor slab design and construction recommendations are as follows:
• Positive separations and/or isolation joints should be provided between slabs and all
foundations, columns or utility lines to allow independent movement.
• Control joints should be provided in slabs to control the location and extent of
cracking.
• Interior trench backfill placed beneath slabs should be compacted in accordance with
recommended specifications outlined below.
• The use of vapor retarder should be considered beneath concrete slabs -on -grade
that will be covered with wood, tile, carpet or other moisture sensitive or impervious
coverings, or when the slab will support equipment sensitive to moisture. When
conditions warrant the use of a vapor retarder, the slab designer and slab contractor
should refer to ACI 302 for procedures and cautions regarding the use and
placement or a vapor retarder.
• Floor slabs should not be constructed on frozen subgrade.
• Other design and construction considerations, as outlined in Section 302.1R of the
ACI Design Manual, are recommended.
Gravel Roadway Design and Construction: Design of the gravel access roads for the project
has been based on the procedures outlined in the 1993 Guide for Design of Pavement
Structures by the American Association of State Highway and Transportation Officials
(AASHTO).
For gravel access road design, a modulus of aggregate base layer of 30,000 psi was utilized
along with an allowable depth of rutting of 2.5 inches. The Equivalent Daily 18 kip Load
Application (EDLA) for the project was assumed to be 50. Based on the subsurface conditions
encountered at the site, and the laboratory test results, it is recommended that the access road
areas be designed using a minimum R -value of 20. Based on Figure 4.3, Design Chart for
Aggregate -Surfaced Roads Considering Allowable Rutting, 1993 Guide for Design of Pavement
Structures by the American Association of State Highway and Transportation Officials
(AASHTO), the recommended thickness of the roadbase section was determined to be 9
inches. Terracon should be notified if any of the assumptions made for the roadway design are
not correct.
8
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
We recommend the roadway areas be rough graded and then thoroughly proofrolled with a
loaded tandem axle dump truck prior to final grading. Particular attention should be paid to
areas where backfilled trenches are located. Areas where unsuitable conditions are located
should be repaired by removing and replacing the materials with properly compacted fills.
Roadway areas should be moisture conditioned and properly compacted to the
recommendations in this report immediately prior to paving.
Aggregate base course should consist of a blend of sand and gravel which meets strict
specifications for quality and gradation. Use of materials meeting Colorado Department of
Transportation (CDOT) Class 5 or 6 specifications is recommended for base course.
Aggregate base course should be placed in lifts not exceeding 6 inches and compacted to a
minimum of 95 percent standard Proctor density (ASTM D698).
Preventative maintenance on the proposed gravel access road should be planned and provided
for through an ongoing management program to enhance future roadway performance.
Preventative maintenance activities are intended to slow the rate of deterioration and to
preserve the roadway investment.
Preventive maintenance is usually the first priority when implementing a planned roadway
maintenance program and provides the highest return on the investment. After the gravel
access road is paved, both localized maintenance (e.g. replacement of areas that have lost
stability) and global maintenance (e.g. periodic grading) will be required.
Concrete Truck Unloading Pad Construction: Based on conversations with a representative
of the client we understand that the concrete pad will be designed by the project structural
engineer. The pad may be designed for a maximum allowable bearing pressure of 1,000
pounds per square foot (psf). For structural design, a modulus of subgrade reaction of 100
pounds per cubic inch (pci) may be used.
Due to the presence of very loose to loose sand soils we recommend that the pad bear on a
minimum of 3 feet of moisture conditioned and recompacted and/or replacement with non- to
low expansive onsite or imported materials.
We recommend the pad subgrade be rough graded and then thoroughly proofrolled with a
loaded tandem axle dump truck prior to final grading. Particular attention should be paid to
areas where backfilled trenches are located. Areas where unsuitable conditions are located
should be repaired by removing and replacing the materials with properly compacted fills.
9
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Earthwork:
Terracon
General Considerations: The following presents recommendations for site preparation,
excavation, subgrade preparation and placement of engineered fills on the project.
Earthwork on the project should be observed and evaluated by Terracon. The evaluation of
earthwork should include observation and testing of engineered fills, subgrade preparation,
foundation bearing soils and other geotechnical conditions exposed during the construction
of the project.
Site Preparation: Strip and remove existing vegetation, and other deleterious materials
from proposed building, mat foundation, and pavement areas. Exposed surfaces should be
free of mounds and depressions which could prevent uniform compaction.
Stripped materials consisting of vegetation and organic materials should be wasted from the
site or used to revegetate landscaped areas or exposed slopes after completion of grading
operations. If it is necessary to dispose of organic materials on -site, they should be placed
in non-structural areas and in fill sections not exceeding 5 feet in height.
The site should be initially graded to create a relatively level surface to receive fill and to
provide for a relatively uniform thickness of fill beneath proposed structures.
Exposed areas which will receive fill, once properly cleared and benched, should be
scarified to a minimum depth of 12 inches, conditioned to near optimum moisture content
and compacted.
Although evidence of fills or underground facilities such as septic tanks, cesspools,
basements and utilities was not observed during the site reconnaissance, such features
could be encountered during construction. If unexpected fills or underground facilities are
encountered, such features should be removed and the excavation thoroughly cleaned prior
to backfill placement and/or construction.
The stability of the subgrade may be affected by precipitation, repetitive construction traffic,
or other factors. If unstable conditions are encountered or develop during construction,
workability may be improved by scarifying and drying. Overexcavation of wet zones and
replacement with granular materials may be necessary. Use of lime, fly ash, kiln dust,
cement or geotextiles could also be considered as a stabilization technique. Laboratory
evaluation is recommended to determine the effect of chemical stabilization on subgrade
soils prior to construction. Lightweight excavation equipment may be required to reduce
subgrade pumping.
10
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
The individual contractor(s) is responsible for designing and constructing stable, temporary
excavations as required to maintain stability of both the excavation sides and bottom.
Excavations should be sloped or shored in the interest of safety following local and federal
regulations, including current OSHA excavation and trench safety standards.
Subgrade Preparation: Areas of soft or loose soils may be encountered at foundation
bearing depth after excavation is completed for footings or mats. When such conditions
exist beneath planned footing areas, the subgrade soils should be removed, replaced,
and/or recompacted prior to placement of the foundation system.
Subgrade soils beneath interior and exterior slabs and beneath roadways should be
scarified, moisture conditioned and compacted to a minimum depth of 12 inches. The
moisture content and compaction of subgrade soils should be maintained until slab or
pavement construction.
Fill Materials and Placement: Clean on -site soils or approved imported materials may be
used as fill material.
Imported soils (if required) should conform to the following:
Percent finer by weight
Gradation (ASTM C136)
6" 100
3" 70-100
No. 4 Sieve 50-100
No. 200 Sieve 35 (max)
Liquid Limit 30(max)
Plasticity Index 15 (max)
Maximum expansive potential (%)* 1.5
*Measured on a sample compacted to approximately 95 percent of the ASTM D698
maximum dry density at about 3 percent below optimum water content. The sample is
confined under a 100 psf surcharge and submerged.
Engineered fill should be placed and compacted in horizontal lifts, using equipment and
procedures that will produce recommended moisture contents and densities throughout the
lift. Recommended compaction criteria for engineered fill is 95 percent of the maximum dry
density (ASTM D698).
11
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
On -site and imported sand soils should be compacted within a moisture range of 3 percent
below to 3 percent above optimum moisture content. Imported clay soils should be
compacted within a moisture range of optimum to 3 percent above optimum unless modified
by the project geotechnical engineer.
The recommendations for placement and compaction criteria presented assume that fill
depths will be less than 10 feet. Fills less than 10 feet, when placed and compacted as
recommended in this report, will experience some settlement (generally 1 inch or less in
addition to }. The amount and rate of settlement will be increased if water is introduced into
the fill.
Excavation and Trench Construction: Excavations into the on -site soils will encounter
caving sand and possibly groundwater, depending on the depth of excavation. The
individual contractor(s) should be made responsible for designing and constructing stable,
temporary excavations as required to maintain stability of both the excavation sides and
bottom. Excavations should be sloped or shored in the interest of safety following local and
federal regulations, including current OSHA excavation and trench safety standards.
The soils to be penetrated by the proposed excavations may vary across the site. The
preliminary soil classifications are based solely on the materials encountered in widely
spaced exploratory test borings. The contractor should verify that similar conditions exist
throughout the proposed area of excavation. If different subsurface conditions are
encountered at the time of construction, the actual conditions should be evaluated to
determine any excavation modifications necessary to maintain safe conditions.
As a safety measure, it is recommended that vehicles and soil piles be kept to a minimum
lateral distance from the crest of the slope equal to no less than the slope height. The
exposed slope face should be protected against the elements.
Additional Design and Construction Considerations:
Exterior Slab Design and Construction: Exterior slabs -on -grade, exterior architectural
features, and utilities founded on or in backfill may experience some movement due to the
volume change of the backfill. Potential movement could be reduced by:
• minimizing moisture increases in the backfill.
▪ controlling moisture -density during placement of backfill.
• using designs which allow vertical movement between the exterior features and
adjoining structural elements.
• placing effective control joints on relatively close centers.
12
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
Terracon
Corrosion Protection: Results of soluble sulfate testing indicate that ASTM Type I
Portland cement is suitable for all project concrete on and below grade. However, if there is
no (or minimal) cost differential, use of ASTM Type II Portland cement is recommended for
additional sulfate resistance of construction concrete. Foundation concrete should be
designed in accordance with the provisions of Section 318, Chapter 4, of the ACI Design
Manual.
Surface Drainage: Grades must be adjusted to provide positive drainage away from the
structures during construction and maintained throughout the life of the proposed project.
Infiltration of water into utility or foundation excavations must be prevented during
construction. Landscaped irrigation adjacent to the foundation systems should be minimized
or eliminated. Water permitted to pond near or adjacent to the perimeter of the structures
(either during or post -construction) can result in significantly higher soil movements than
those discussed in this report. As a result, any estimations of potential movement described
in this report cannot be relied upon if positive drainage is not obtained and maintained, and
water is allowed to infiltrate the fill and/or subgrade.
Exposed ground should be sloped at a minimum of 10 percent grade for at least 10 feet
beyond the perimeter of the buildings and mat, where possible. The use of drainage swales,
sidewalk chases, and/or area drains may be required to facilitate drainage. Backfill against
footings, exterior walls and in utility and sprinkler line trenches should be well compacted
and free of construction debris to reduce the possibility of moisture infiltration. After building
construction and prior to project completion, we recommend that verification of final grading
be performed to document that positive drainage, as described above, has been achieved.
Flatwork and pavements will be subject to post construction movement. Maximum grades
practical should be used for paving and flatwork to prevent areas where water can pond. In
addition, allowances in final grades should take into consideration post -construction
movement of flatwork, particularly if such movement would be critical. Where paving or
flatwork abuts the structure, care should be taken that joints are properly sealed and
maintained to prevent the infiltration of surface water.
Planters located adjacent to the structures should preferably be self-contained. Sprinkler
mains and spray heads should be located a minimum of 10 feet away from the buildings.
Roof drains should discharge on pavements or be extended away from the structure a
minimum of 10 feet through the use of splash blocks or downspout extensions. A preferred
alternative is to have the roof drains discharge to storm sewers by solid pipe or daylighted to
a detention pond or other appropriate. outfall.
13
Geotechnical Engineering Report
Proposed Pump House and Separator Facility
Terracon Project No. 21095002
GENERAL COMMENTS
Terracon
Terracon should be retained to review the final design plans and specifications so comments
can be made regarding interpretation and implementation of our geotechnical recommendations
in the design and specifications. Terracon should also be retained to provide testing and
observation during the excavation, grading, foundation and construction phases of the project.
The analysis and recommendations presented in this report are based upon the data obtained
from the borings performed at the indicated locations and from other information discussed in
this report. This report does not reflect variations that may occur between borings, across the
site, or due to the modifying effects of weather. The nature and extent of such variations may
not become evident until during or after construction. If variations appear, we should be
immediately notified so that further evaluation and supplemental recommendations can be
provided.
The scope of services for this project does not include, either specifically or by implication, any
environmental or biological (e.g., mold, fungi, bacteria) assessment of the site or identification or
prevention of pollutants, hazardous materials or conditions. If the owner is concerned about the
potential for such contamination or pollution, other studies should be undertaken.
This report has been prepared for the exclusive use of our client for specific application to the
project discussed and has been prepared in accordance with generally accepted geotechnical
engineering practices. No warranties, either express or implied, are intended or made. Site
safety, excavation support, and dewatering requirements are the responsibility of others. In the
event that changes are planned in the nature, design, or location of the project as outlined in
this report, the conclusions and recommendations contained in this report shall not be
considered valid unless Terracon reviews the changes, and either verifies or modifies the
conclusions of this report in writing.
14
C ` — �, \
f� I WELD COUNTY R�,D . 34 cb
65„-
31.4 48--
`4$23 \ \ ,\ 1
\ ` ` \ \
C9'2\
`\ , ‘ \
N N \ ♦ rs\ 4---..
N.
N. N \ N \' 1
\ \ \ \
\
TANK AREA
SURVEYED TO
OUTSIDE TOE
��x
r / \
\ /
N � _?--1� /1 I I I I I I
\ ) 1-^------� I , +, I II
\ ` ) ` 1 OFFICE BUILDING ALTERNATIV PERC.I1
\ �1 - - , - - LOCATION #1
N \--/1-
`—
P1 P2 P3
PFiOFIL
P5 PG- .y
i N
`\•
' •
No
No.2'
N
ref
N ) /I, f— N\ N.
\ \ ( N\ No.4 - No..3
k w
\ I \ \ 1 INJECTION \
▪ t \
/ ��i ▪ 4 \ \ \
N Z \
— N
N \ q.UILDf-OG
Ae soRPI1oN- BED
OPTION # 1
1 1
\f
CONCRETE \▪ UNLOAD I NG PA)1\I
\
/ y 1
�/ — \
CONCRETE TANK PAO —`
- //
// 1/ /.-- --- \IR
N � `� N \ \ \ \ \� \ ` \\ r1 �1 / /t\ II
lir
60
J
• - APPROXIMATE PERCOLATION TEST BORING LOCATION
LEGEND 0 30
• - APPROXIMATE TEST BORING LOCATIONS r-
s.
Pined Hr
on 5r
Cheekat Sy.
CMG
DJS
JM
PnaHt 21095002
Stale:
Vela
06/01709
lrerracon
Consulting Engineers and Sdendsls
FIGURE 1: BORING LOCATION DIAGRAM
PROPOSED PUMP HOUSE and SEPARATOR FACILITY
SOUTHEAST OF THE INTERSECTION OF WELD COUNTY ROADS 34 & 49
WELD COUNTY, COLORADO
FIG. No.
1
Approval ey,
JM
301N, HOWES FORT COLLINS, CO SM21
PH.IA7U]4144399 FAX (9701494-0454
Negrojecte - Other officesl3reefev - Office No. 21521095002 CADDS21095002-1.dwg
APPENDIX A
lierracon
r LOG OF BORING NO. 1 Page 1 oft
CLIENT
Lamp Rynearson And Associates
SITE S. and E. of the Int. of WCR's 34 and 49
Weld County, Colorado
PROJECT
Proposed Pump House and Separator
L7
Si
U
t.9
DESCRIPTION
Approx. Surface Elev.: 4817 ft
Y
o
o
00
>-
'
SAMPLES
TESTS
Q
w
z
F
>-
w
>
L
-
rn
m
mg
a
z
aw
z
g o
~
Z
o.
Q Q
2 _
u-
zZ
cc
Ow u~i
''.
POORLY GRADED SAND
medium
4797
—
=
i
Medium grained, very loose to
dense, tan
20
—SP
1
RS
12
5
4
5
—SP
2
SS
12
4
6
TO
—
15
SP
3
RS
12
26
2
110
-
20
SP
4
SS
12
10
20
CLAYSTONE
g
4787
—
—
25—
—
—
_
_
—
Medium hard, red brown, tan, olive
30
~
,_
C
F-
o
a
r.1
a
—
30
5
RS
12
50/0.6
13
112
n
i
n
BOTTOM OF BORING
The stratification lines represent the approximate boundary lines
between soil and rock types: in -situ, the transition may be gradual.
S. WATER LEVEL OBSERVATIONS, ft
7
erracon
BORING STARTED 5-21-09
t WL
7 28 WD
I Graded over
BORING COMPLETED 5-21-09
5' WL
3
V.
RIG CME 55
FOREMAN CMG
u
D WL
APPROVED JCM
JOB # 21095002
LOG OF BORING NO. 2 Page 1 of 1
CLIENT
Lamp Rynearson And Associates
SITE S. and E. of the Int. of WCR's 34 and 49
Weld County, Colorado
PROJECT
Proposed Pump House and Separator
GRAPHIC LOG
DESCRIPTION
Approx. Surface Elev.: 4822 ft
DEPTH, ft.
USCS SYMBOL
SAMPLES
f TESTS
NUMBER
w
RECOVERY, in.
BLOWS / ft.
WATER
CONTENT, %
DRY UNIT WT
Pci
UNCONFINED
STRENGTH, psf
% SWELL
SURCHARGE
•
_: •
POORLY GRADED SAND,with silt
4796
0.0%
500psf
—
SP
1
RS
12
3
3
Medium grained, very loose to medium
dense, tan
26
—•
—
SP
2
RS
12
15
6
109
5
-
SP
3
SS
12
6
2
10
-
SP
4
RS
12
14
9
118
15 -
—=SP
5
SS
12
16
3
20 -J
-1
25--
—•
=:
CLAYSTONE
red brown, tan, olive
4782
Medium hard,
30
--
sa
6
RS
12
50
BOTTOM OF BORING
The stratification lines represent the approximate boundary lines
between soil and rock types: in -situ, the transition may be gradual.
WATER LEVEL OBSERVATIONS, ft
erracon
w -
BORING STARTED 5-21-09
WL
V 28 WD
I Graded over
BORING COMPLETED 5-21-09
WL
Y
Y
RIG CME 55
FOREMAN CMG
WL
_
APPROVED JCM
JOB # 21095002,
LOG OF BORING NO. 3 Page 1 of 1
CLIENT
Lamp Rynearson And Associates
SITE S. and E. of the Int. of WCR's 34 and 49
Weld County, Colorado
_
PROJECT
Proposed Pump House and Separator
GRAPHIC LOG
DESCRIPTION
Approx. Surface Elev.: 4816 ft
DEPTH, ft.
USCS SYMBOL
SAMPLES
I TESTS
NUMBER
TYPE
RECOVERY, in.
BLOWS/ft.
WATER
CONTENT, °I°
DRY UNIT WT
Pcf
UNCONFINED
STRENGTH, psf
• •
POORLY GRADED SAND
tan
4802
—
—
Medium grained, very loose to loose,
14
SP
1
RS
12
4
1
133
--
5
-SP
2
RS
12
14
9
10
—
LEAN LEAN CLAY. with sand
i
4796.5
—
CL
3
SS
12
12
15
Stiff, brown
19.5
15
--
-
_.
4
RS
12
40
9
118
CLAYSTONE.
tan, olive
Q
4786
20
=
25-
-
-.
Firm to medium hard, red brown,
3
BOTTOM OF BORING
30
The stratification lines represent the approximate boundary lines
between soil and rock types: in -situ, the transition may be gradual.
_
WATER LEVEL OBSERVATIONS, ft
erracon
BORING STARTED 5-21-09
WL
V29 WD
L 18 5/28/09
BORING COMPLETED 5-21-09
WL
I
Y
RIG CME 55
FOREMAN CMG
WL
APPROVED JCM
JOB # 21095002
LOG OF BORING NO. 4 Page 1 of 1
CLIENT
Lamp Rynearson And Associates
SITE S. and E. of the Int. of WCR's 34 and 49
Weld County, Colorado
PROJECT
Proposed Pump House and Separator
GRAPHIC LOG
DESCRIPTION
Approx. Surface Elev.: 4813 ft
DEPTH, ft_
USCS SYMBOL
SAMPLES
TESTS
NUMBER
TYPE
RECOVERY, in.
BLOWS / ft.
WATER
CONTENT, %
DRY UNIT WT
Pcf
UNCONFINED
STRENGTH, psf
% SWELL
SURCHARGE
POORLY GRADED SAND
dense,
4800
—
—•
0.6%
500psf
Medium grained, loose to medium
tan
13
—SP
1
SS
12
8
4
5
-
SP
2
RS
12
25
6
114
10
—
LEAN CLAY, with sand
1
4793.5
Stiff, brown
19 5
--
CL
3
SS
12
13
16
15
-
20
4
RS
12
48
14
115
CLAYSTONE
tan, olive
4788
Firm to medium hard, red brown,
Interbedded sandstone lenses
encountered
2
BOTTOM OF BORING
25
The stratification lines represent the approximate boundary lines
between soil and rock types: in -situ, the transition may be gradual.
WATER LEVEL OBSERVATIONS, ft
BrraCOf
BORING STARTED 5-21-09
WL
Z DRY WD - 16 5/28/09
BORING COMPLETED 5-21-09
WL
I Y
RIG CME 55
FOREMAN CMG
WL
APPROVED JCM
JOB # 21095002
CLIENT
LOG OF BORING NO. Pere Profile
Lamp Rynearson And Associates
Page 1 of 1
SITE S. and E. of the Int. of WCR's 34 and 49
Weld County, Colorado
PROJECT
Proposed Pump House and Separator
CD
0
J
0
DESCRIPTION
Approx. Surface Elev.: 4824 ft
POORLY GRADED SAND
Medium grained, tan
W
a-
w
0
USCS SYMBOL
SAMPLES
TESTS
w
CO
2
z
w
a
I-
› -
RECOVERY, 1n_
BLOWS / ft.
in
Zig
°C1
I- LL h
Cew z zz
w
<0 �t zi-
0 ❑ a D. 01
9
4815
BOTTOM OF BORING
5 -
SP
1
BS
12
4
The stratification lines represent the approximate boundary lines
between soil and rook types: in -situ, the transition may be gradual.
WATER LEVEL OBSERVATIONS, ft
WL
DRY WD
1 DRY 5/28/09
WL
WL
lierracon
BORING STARTED 5-28-09
BORING COMPLETED 5-28-09
RIG CME 55
FOREMAN CMG
APPROVED JCM JOB # 21095002
TC CONSOL STRAIN 2109511 2.CR1 FORT COLLINS 116368.G0T 6PI1
AXIAL STRAIN, %
_,O O W N O N b
1,000 10,000
PRESSURE, psf
Specimen Identification
Classification
Yd, pcf
WC,%
• 2 14.0ft
POORLY GRADED SAND
118
9
Notes:
1 ie rr actin
SWELL CONSOLIDATION TEST
Project: Proposed Pump House and Separator
Site: S. and E. of the Int. of WCR's 34 and 49 Weld County, Colorado
Job #: 21095002
AXfAL STRAIN, %
J
A O Oo O) � N 4
I
1,000 10,000
PRESSURE, psf
Specimen Identification
Classification
X, pcf
WC,%
• 4 19.0ft
LEAN CLAY, with sand
115
14
Notes:
1 Brr actin
SWELL CONSOLIDATION TEST
Project: Proposed Pump House and Separator
Site: S. and E. of the Int. of WCR's 34 and 49 Weld County, Colorado
Jab #: 21095002
U.S. SIEVE OPENING IN INCHES I U.S. SIEVE
6 4 3 2 1.5 1 3/4 1/2 $ 3 6 $10 1416
NUMBERS I HYDROMETER
i 4030 50 60 1001200
100
95
y _"�
1
■
ill
I
IlII
I
90
IIIIMIIIII
75
1
llfIMI
75
I
70
1■■
1■�1111
U
601■�1
L
551■■�U1lUll__1111111__IU
1
_IIliii__I■
5011
1L
i ii!
z 45
Lu
ce 40
ui
a
35
30
1
DI
25
I
20
#i
15
III
In
10
1
M.-
5
0
1
100
10 1 0 1
GRAIN SIZE IN MILLIMETERS
0.01 0.001
GRAVEL
SAND
SILT OR CLAY
COBBLES
coarse
I fine
coarse I
medium I
fine
Specimen Identification
Classification
LL
PL
PI
Cc
Cu
•
1 4.0ft
POORLY GRADED SAND(SP)
NP
NP
NP
1.25
2.74
I
2 9.0ft
POORLY GRADED SAND with SILT(SP-SM)
NP
NP
NP
1.33
2.89
•
4 14.0ft
LEAN CLAY with SAND(CL)
29
12
17
Specimen Identification
D100
D60
D30
D10
%Gravel
%Sand
%Silt
%Clay
•
1 4.0ft
2
0.298
0.201
0.109
0.0
95.3
4.7
CO
2 9.0ft
2
0.278
0.189
0.096
0.0
94.6
5.4
A
4 14.0ft
9.5
1.0
23.7
75.3
GRAIN SIZE DISTRIBUTION
1 rerr acon
Project: Proposed Pump House and Separator
Site: S. and E. of the Int. of WCR's 34 and 49 Weld County, Colorado
Job #: 21095002
Date:
60
CH
ICL
50
P
L
A
s 40
T/7
'I
C
I
T 307Y
I
N
20
D
E
X l
Ai
,0007
10,
CL -ML
/
ML
CD
(11
20 40 60 80 100
LIQUID LIMIT
Specimen Identification
LL
PL
PI
%Fines
Classification
•
1 4.Oft
NP
NP
NP
5
POORLY GRADED SAND(SP)
m
2 9.Oft
NP
NP
NP
5
POORLY GRADED SAND with SILT(SP-SM) ,
IA
4 14.Oft
29
12
17
75
LEAN CLAY with SAND(CL)
11 IIIHI''11.11r
ATTERBERG LIMITS RESULTS
Project: Proposed Pump House and Separator
Site: S. and E. of the Int. of WCR's 34 and 49 Weld County, Colorado
Job #: 21095002
Sheet 9 of 1
Borehole
Depth
ft
Liquid
Limit
PlasticitySoluble
Index
% <#200
Sieve
Water
Sulfates
(PPm)
AASHTO
Class-
ification
USCS
Class-
ification
Water
Content
(%)
Dry Unit
Weight
(pct)
Swell (%)/
Surcharge
(psf)
1
4.0
_
NP
0
5
A-3
SP _
4
1
9.0
6
1
14.0
2
110
1
19.0
20
1
2
29.0
0.5
13
112
- ---
3
2
4.0
0
6
109
2
9.0
NP
0
5
A-3
SP-SM
2
2
14.0
9
118
0.0/500
2
19.0
3
3
4.0
I 100
1
133
3
9.0
9
3
14.0 I
15
3
19.0
_
... —.
_
. - 9
118
3
�
29.0
15
4
4.0
4
4
9.0
6
114
4
14.0
29
17
75
A-6
CL
16
4
19.0
14
115
0.6/500
4
24.0
21
Dere Profilc
8.0
4
TC LAB SUMMARY 21095002.GPJ FORT COLLINIS 11MDR _G0T SP - TM
ll�rracon
SUMMARY OF LABORATORY RESULTS
Project: Proposed Pump House and Separator
Site: S. and E. of the Int. of WCR's 34 and 49 Weld County, Colorado
Job #: 21095002
APPENDIX C
lierracon. _
GENERAL NOTES
DRILLING & SAMPLING SYMBOLS:
SS: Split Spoon - 1-3/8" I.D., 2" O.D., unless otherwise noted
ST: Thin -Wailed Tube - 2" O.D., unless otherwise noted
RS: Ring Sampler - 2.42" 1,D., 3" O.D., unless otherwise noted
DB: Diamond Bit Coring - 4", N, B
BS: Bulk Sample or Auger Sample
HS:
PA:
HA:
RB:
WB:
Hollow Stem Auger
Power Auger
Hand Auger
Rock Bit
Wash Boring or Mud Rotary
The number of blows required to advance a standard 2 -inch D.D. split -spoon sampler (SS) the last 12 inches of the total 18 -inch
penetration with a 140 -pound hammer falling 30 inches is considered the "Standard Penetration" or "N -value". For 3" O.D. ring
samplers (RS) the penetration value is reported as the number of blows required to advance the sampler 12 inches using a 140 -
pound hammer falling 30 inches, reported as 'blows per foot," and is not considered equivalent to the "Standard Penetration" or "N -
value",
WATER LEVEL MEASUREMENT SYMBOLS:
WL: Water Level
WCI: Wet Cave in
DCI: Dry Cave in
AB: After Boring
WS:
WD:
BCR:
AC R:
While Sampling
While Drilling
Before Casing Removal
After Casing Removal
Water levels indicated on the boring logs are the levels measured in the borings at the times indicated. Groundwater levels at other
times and other locations across the site could vary. In perilous soils, the indicated levels may reflect the location of groundwater.
In low permeability soils, the accurate determination of groundwater levels may not be possible with only short-term observations.
DESCRIPTIVE SOIL CLASSIFICATION: Soil classification is based on the Unified Classification System. Coarse Grained Soils
have more than 50% of their dry weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand.
Fine Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they are
plastic, and silts if they are slightly plastic or non -plastic. Major constituents may be added as modifiers and minor constituents may
be added according to the relative proportions based on grain size. In addition to gradation, coarse -grained soils are defined on the
basis of their in -place relative density and fine-grained soils on the basis of their consistency.
FINE-GRAINED SOILS COARSE -GRAINED SOILS BEDROCK
RS (SS) R5
Blows/Ft. Blows/Ft. Consistency Blows/Ft.
<3 0-2 Very Soft 0-6
3-4 3-4 Soft 7-18
5-9 5-8 Medium Stiff 19-58
10-18 9-15 Stiff 59-98
19-42 16-30 Very Stiff > 98
> 42 > 30 Hard
RELATIVE PROPORTIONS OF SAND AND
GRAVEL
Descriptive Terms of Percent of
Other Constituents Dry Weight
Trace < 15
With 15 — 29
Modifier > 30
RELATIVE PROPORTIONS OF FINES
Descriptive Terms of
Other Constituents
Trace
With
Modifiers
Percent of
Dry Weight
<5
5-12
> 12
u
Blows/Ft.
<3
4-9
10-29
30-50
> 50
Relative
Densi
Very Loose
Loose
Medium Dense
Dense
Very Dense
RS SS
Blows/Ft. Blows/Ft.
<30 <20
30-49 20-29
50-89 30-49
90-119 50-79
>119 >79
GRAIN SIZE TERMINOLOGY
Major Component
of Sample
Boulders
Cobbles
Gravel
Sand
Silt or Clay
Consistency
Weathered
Firm
Medium Hard
Hard
Very Hard
Particle Size
Over 12 in. (300mm)
12 in. to 3 in. (300mm to 75 mm)
3 in. to #4 sieve (75mm to 4.75 mm)
#4 to #200 sieve (4.75mm to 0.075mm)
Passing #200 Sieve (0.075mm)
PLASTICITY DESCRIPTION
Term
Non -plastic
Low
Medium
High
Plasticity Index
0
1-10
11-30
30+
lrerracon
UNIFIED SOIL CLASSIFICATION SYSTEM
Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests"
Soil Classification
Group
Symbol
Group Name°
Coarse Grained Soils
More than 50% retained
on No. 200 sieve
Gravels Clean Gravels
More than 50% of coarse Less than 5% fines`
fraction retained on
No. 4 sieve
Cu ≥ 4 and 1 s Cc s 3E GW Well graded gravelF
Cu < 4 and/or 1 > Cc > 3E GP Poorly graded gravel'
Gravels with Fines More Fines classify as ML or MH
than 12% fines`
GM Silty graver.'
Fines classify as CL or CH GC Clayey gravelF 4"
Sands
50% or more of coarse
fraction passes
No. 4 sieve
Clean Sands
Less than 5% fines°
Cu?6and 1sCcs30
Cu < 6 and/or 1 > Cc> 3E
SW Well graded sand'
SP Poorly graded sand'
Sands with Fines
More than 12% fines'
Fines classify as ML or MH SM
Slaty sand°.'"
Fines classify as CL or CH
SC Clayey sande.'"
Fine -Grained Soils Silts and Clays
50% or more passes the Liquid limit /ess than 50
No. 200 sieve
inorganic
PI > 7 and plots on or above "A" lined CL
Lean clay" ,4"
PI < 4 or plots below "A" line' ML
Silr "
organic
Liquid limit - oven
dried
<0.75
Organic L1.4.N
OL
Liquid limit - not organic slit"•".°
dried
Silts and Clays inorganic
Liquid limit 50 or mare
Highly organic soils
PI plots on or above "A" line CH Fat clay" 4"
PI plots below "A" line MH Elastic silt"."
organic Liquid limit - oven dried
Liquid limit - not dried
Primarily organic matter, dark In color, and organic odor
<0.75 OH
Organic clay",'-'
Organic silt".".'"
PT Peat
"Based on the material passing the 3 -in. (75 -mm) sieve
a If field sample contained cobbles or boulders, or both, add "with cobbles
or boulders, or both" to group name.
c Gravels with 5 to 12% fines require dual symbols: GW-GM well graded
gravel with silt, GW-GC well graded gravel with clay, GP -GM poorly
graded gravel with sill, GP -GC poorly graded gravel with clay.
° Sands with 5 to 12% fines require dual symbols: SW-SM well graded
sand with silt, SW -SC well graded sand with clay, SP-SM poorly graded
sand with silt, SP -SC poorly graded sand with clay
sCu = De"1Di° Cc= �°f₹
Gho x Dea
F If soil contains ≥ 15% sand, add "with sand" to group name.
° If fines classify as CL -ML, use dual symbol GC -GM, or SC-SM.
PLASTICITY INDEX (PI)
For Classification of fine-grained
soils and fine-grained traction
50 _, of coarse -grained soils
Equation of "A- - line
Horizontal at PI=4 to LL=25.5.
40 ! - then PI -0.73 ILL -20) --
Equation of "U" - line
Vertical at LL=18 to P3_7.
30 - then Pt 0.9 (LL -S)
20
10
7
4
0
0 10 16 20
"If fines are organic, add "with organic fines" to group name.
' If soil contains z 15% gravel, add "with gravel" to group name.
If Atterberg limits plot in shaded area, soil is a CL -ML, silty clay.
K If soil contains 15 to 29% plus No. 200, add "with sand- or with
gravel," whichever is predominant.
L If soil contains ≥ 30% plus No. 200 predominantly sand, add
"sandy" to group name.
mlf soil contains z 30% plus No. 200, predominantly gravel, add
"gravelly" to group name.
"PI z 4 and plots on or above A" line.
°PI < 4 or plots below "A" line.
PPI plots on or above "A" line.
°PI plots below "A" line.
30 40 50 60 70
LIQUID LIMIT (LL)
80 90 100
42,
MHor OH
110
lrerracon_
LABORATORY TEST
SIGNIFICANCE AND PURPOSE
TEST
SIGNIFICANCE
PURPOSE
California Bearing
Ratio
Used to evaluate the potential strength of subgrade soil,
subbase, and base course material, including recycled
materials for use in road and airfield pavements.
Pavement Thickness
Design
Consolidation
Used to develop an estimate of both the rate and amount of
both differential and total settlement of a structure.
Foundation Design
Direct Shear
Used to determine the consolidated drained shear strength
of soil or rock.
Bearing Capacity,
Foundation Design,
and Slope Stability
Dry Density
Used to determine the in -place density of natural, inorganic,
fine-grained soils.
index Property Soil
Behavior
Expansion
Used to measure the expansive potential of fine-grained
soil and to provide a basis for swell potential classification.
Foundation and Slab
Design
Gradation
Used for the quantitative determination of the distribution of
particle sizes in soil.
Soil Classification
Liquid & Plastic Limit,
Plasticity Index
Used as an integral part of engineering classification
systems to characterize the fine-grained fraction of soils,
and to specify the fine-grained fraction of construction
materials.
Soil Classification
Permeability
Used to determine the capacity of soil or rock to conduct a
liquid or gas.
Groundwater Flow
Analysis
pH
Used to determine the degree of acidity or alkalinity of a
soil.
Corrosion Potential
Resistivity
Used to indicate the relative ability of a soil medium to carry
electrical currents.
Corrosion Potential
R -Value
Used to evaluate the potential strength of subgrade soil,
subbase, and base course material, including recycled
materials for use in road and airfield pavements.
Pavement Thickness
Design
Soluble Sulphate
Used to determine the quantitative amount of soluble
sulfates within a soil mass.
Corrosion Potential
Unconfined
Compression
To obtain the approximate compressive strength of soils
that possess sufficient cohesion to permit testing in the
unconfined state.
Bearing Capacity
Analysis for
Foundations
Water Content
Used to determine the quantitative amount of water in a soil'
mass.
index Property Soil
Behavior
irffcon
REPORT TERMINOLOGY
(Based on ASTM D653)
Allowable Soil
Bearing Capacity
Alluvium
Aggregate Base
Course
Backfill
Bedrock
Bench
Caisson (Drilled
Pier or Shaft)
Coefficient of
Friction
Colluvium
Compaction
Concrete Slab -on -
Grade
Differential
Movement
Earth Pressure
ESAL
Engineered Fill
Equivalent Fluid
Existing Fill (or
Man -Made Fill)
Existing Grade
The recommended maximum contact stress developed at the interface of the foundation
element and the supporting material.
Soil, the constituents of which have been transported in suspension by flowing water and
subsequently deposited by sedimentation.
A layer of specified material placed on a subgrade or subbase usually beneath slabs or
pavements.
A specified material placed and compacted in a confined area.
A natural aggregate of mineral grains connected by strong and permanent cohesive forces.
Usually requires drilling, wedging, blasting or other methods of extraordinary force for
excavation.
A horizontal surface in a sloped deposit.
A concrete foundation element cast in a circular excavation which may have an enlarged
base. Sometimes referred to as a cast -in -place pier or drilled shaft.
A constant proportionality factor relating normal stress and the corresponding shear stress
at which sliding starts between the two surfaces.
Soil, the constituents of which have been deposited chiefly by gravity such as at the foot of a
slope or cliff.
The densification of a soil by means of mechanical manipulation
A concrete surface layer cast directly upon a base, subbase or subgrade, and typically used
as a floor system.
Unequal settlement or heave between, or within foundation elements of structure.
The pressure exerted by soil on any boundary such as a foundation wall.
Equivalent Single Axle Load, a criteria used to convert traffic to a uniform standard, (18,000
pound axle loads).
Specified material placed and compacted to specified density and/or moisture conditions
under observations of a representative of a geotechnical engineer.
A hypothetical fluid having a unit weight such that it will produce a pressure against a lateral
support presumed to be equivalent to that produced by the actual soil. This simplified
approach is valid only when deformation conditions are such that the pressure increases
linearly with depth and the wall friction is neglected.
Materials deposited throughout the action of man prior to exploration of the site.
The ground surface at the time of field exploration.
Ii2rracon
REPORT TERMINOLOGY
(Based on ASTM D653)
Expansive
Potential
Finished Grade
Footing
Foundation
Frost Depth
Grade Beam
Groundwater
Heave
Lithologic
Native Grade
Native Soil
Optimum Moisture
Content
Perched Water
Scarify
Settlement
Skin Friction (Side
Shear)
Soil (Earth)
Strain
Stress
Strip
Subbase
Subgrade
The potential of a soil to expand (increase in volume) due to absorption of moisture.
The final grade created as a part of the project.
A portion of the foundation of a structure that transmits loads directly to the soil.
The lower part of a structure that transmits the loads to the soil or bedrock.
The depth at which the ground becomes frozen during the winter season.
A foundation element or wall, typically constructed of reinforced concrete, used to span
between other foundation elements such as drilled piers.
Subsurface water found in the zone of saturation of soils or within fractures in bedrock
Upward movement.
The characteristics which describe the composition and texture of soil and rock by
observation.
The naturally occurring ground surface.
Naturally occurring on -site soil, sometimes referred to as natural soil.
The water content at which a soil can be compacted to a maximum dry unit weight by a
given compactive effort.
Groundwater, usually of limited area maintained above a normal water elevation by the
presence of an intervening relatively impervious continuous stratum.
To mechanically loosen soil or break down existing soil structure.
Downward movement.
The frictional resistance developed between soil and an element of the structure such as a
drilled pier.
Sediments or other unconsolidated accumulations of solid particles produced by the
physical and chemical disintegration of rocks, and which may or may not contain organic
matter.
The change in length per unit of length in a given direction.
The force per unit area acting within a soil mass.
To remove from present location.
A layer of specified material in a pavement system between the subgrade and base course.
The soil prepared and compacted to support a structure, slab or pavement system.
Iferracon
Hello