Loading...
HomeMy WebLinkAbout20082164WORK ORDER FORM PURSUANT TO AN AGREEMENT BETWEEN WELD COUNTY AND FELSBURG HOLT & ULLEVIG DATED: 7-24-08 Work Order Number: FHU-13 Project Title: Weld/Adams WCR 49 Alignment Study Commencement Date: August 1, 2008 Completion Date: December 1, 2008 Limitations on compensation: Total Contract Not to Exceed $10.000.00. Weld County Portion Not to Exceed $5,000.00. See attached cost breakdown (Exhibit A). Project Description: Assisting Weld County and Adams County in assessing future alignment of WCR 49 between WCR 4 and Imboden Road in Adams County. This study will identify alternative alignments which will serve the best interests of the two Counties, as well as the adjacent "Estates at Horse Creek" development which is currently being planned for this area.. Scope of Services: See attached Scope of Work Professional agrees to perform the services identified above and on the attached forms in accordance with the terms and conditions contained herein and in the Professional Services Agreement between the parties. In the event of a conflict between or ambiguity in the terms of the Professional Services Agreement and this work order (including the attached forms) the Professional Services Agreement shall control. Professional: Felsburg Holt & Ullevig 6300 South Syracuse Way, Suite 600 Centennial, O 80111 By: Title: Date: •,Ac•psl The attached forms are hereby accepted and incorporated herein, by this reference, and Notice to Proceed is hereby given. Weld County By: Wayne Hoyardf opnty Engineer - OP B By: Departmentl lead Date: :p 'S -O S1, _ By: 'PI/ V/vim_ Three or of Fij r,Cce,agd.ddministration Date: IWO l LUU� By: Chairman, Weld County Commissioners Date: AUG 1 1 2008 ted e45-4' C'(I ;/30(io-i)) 0 h - O?a"`7/65 Weld/Adams County Line Crossroads Alignment Study Scope of Work County Road 49 is one of seven roadways identified as strategic roadway corridors in Weld County. Due to the significance of County Road 49 extending from State Highway 2 to Interstate 70, coordination and planning needs to occur between Weld County and Adams County. This scope of work describes a study that will connect County Road 49 at County Road 4 to Imboden Road at 160 Avenue. This alignment will cross many features including the Box Elder Nursery, Box Elder Creek, the Estates at Horse Creek development and an irrigation canal. This study will identify different alternative alignments for the study area along with a "preferred" alignment that will give transportation engineers and planners the tools they need to help preserve the right-of-way required for the improvements or work with incoming development to construct the improvements. Through their existing on call services contract with Weld County, the consulting firm of Felsburg, Holt and Ullevig (FHU) will be required to coordinate the work with representatives from Adams County and Weld County. Weld County will be the lead agency on the project. Purpose The information gathered and compiled in this task will serve as the basis for creating and evaluating alternative alignments. The intent is to utilize available information to the maximum extent possible and to conduct new data collection only as necessary. Subtask 1.1 FHU will assemble pertinent data and information in order to have a thorough understanding of current and projected conditions for the study area. All available land use plans, transportation plans, and specific development plans will be compiled and reviewed. Other collected data will include aerial photography, right-of-way and parcel ownership information, access and intersecting roads inventory, environmental considerations, roadway geometrics, utility information, drainage and flood studies and USGS topographic information. All of this information will be summarized in both graphic and tabular forms to produce a comprehensive representation of the physical characteristics of the study area. Subtask 1.2 In this task, all of the information compiled in Subtask 2.1 will be reviewed and interpreted in order to identify opportunities and constraints related to potential alternative alignments. County Line Crossroads Alignment Study Page 1 of 3 Purpose The purpose of this task is to identify up to four possible alternative alignments for the study area. This work will draw to a large degree on the data, opportunities and constraints compiled in Task 1. Subtask 2.1 In this first step, key crossing/intersecting features will be identified. These will include such features as current land improvements, alignment restrictions or obstacles, and major drainageways. Based on criteria such as topographic conditions, physical characteristics, intersection spacing, geometric conditions, and drainageway widths, possible points at which these features could be reasonably crossed or intersected will be established. Purpose The purpose of this task is to establish evaluation measures and to apply those measures to each alternative to identify the preferred alignment. Subtask 3.1 Using a standard roadway cross-section, the various alternatives for the study area will be assessed through an evaluation process to determine the advantages and disadvantages of the developed alternatives. It is envisioned that the evaluation parameters will include but not be limited to the following: • Horizontal and Vertical Geometry • Community Impacts • Land Use Consequences • Traffic Operations • Environmental Impacts • Right -of -Way Impacts • Safety • Constructability • Cost and Economic Feasibility Subtask 3.2 Information on each alternative will be compiled into an evaluation matrix. A comparative review of the data will be conducted independently by each member of the project team to identify a preferred alternative alignment for the study area. Purpose In this task, FHU will refine the recommended alignment for the study area. This information will be documented in a final report. County Line Crossroads Alignment Study Page 2 of 3 Subtask 4.1 The selected alignments will be refined to reflect any review comments received through the public input review process. Such refinements are not expected to be significant, but they should reflect the best knowledge about the alignment. Subtask 4.2 The findings of the study will be documented in a draft report which will be distributed with 5 bound copies and one electronic version to the local agencies for review. The report will include data collected, analyses conducted, findings of the analyses, and the recommendations of the study process. After review of the draft report, FHU will prepare and deliver 5 copies and electronic version of the final report. Purpose In order to reach a corridor consensus regarding the alignments, it will be critical that the work be closely coordinated between the project team, local agency representatives, elected officials and affected property owners/developers. This task will include a series of meetings to achieve close and continuous coordination. Subtask 5.1 Monthly (and more frequently if necessary) coordination meetings with both County's representatives will be utilized to review and coordinate the work efforts and to resolve problems as they arise. It is anticipated that there will be three monthly coordination meetings conducted for this project. Subtask 5.2 The study process will be divided into an initial phase and final phase. Local agency meetings and public open houses will be conducted for each phase. Public open houses may not be required if individual meetings with affected property meetings is sufficient for the study. County Line Crossroads Alignment Study Page 3 of 3 V N a V 61 0 G 0 O U co 9 Q J t N W N $ u.OO pa!O.a IO our.y .alu.s lruaue.lwd »»» «» O i- H Rf «» at n el ul gg N E ,.§v ri n m raj w .aas auapo n«» 13 RI «» N a,lWtl m W rue.* r+!uag Iruoln.p/d n i7'0 0 0 Ct argrga!uIwptl ^ at to p.usi.ra io!u.sl .euaaaa xr..oaoa peal 0 6u!pu.au.O P.'S 0 N paau6ud aoiuesl ia6ruryl laa(wtl ^ n a'd'6uueuwyu.a wr al p (l l.dauud) >y6pJaO °Paul l pajoJd el N 4 a Id'6uryawd UINO el 6 yi Z E p.d 0 Fees calculated using FHU's 2007 Rate Schedule for Weld County On -Call Services. MEMORANDUM 1111D C. COLORADO TO: Clerk to the Board DATE: August 5, 2008 FROM: Mike Bedell, Public Works SUBJECT: Consent Agenda Item Two original Work Order Forms No. FHU-13 with Felsburg Holt & Ullevig dated 7/24/2008 Please send one signed original Agreement to Public Works. Enclosures M 9Franc ie'Ageeda M ikeBedell.doc eNsett1 AffiIda 2008-2164 otry; wIiDc. COLORADO MEMORANDUM TO: Clerk to the Board DATE: February 23, 2009 FROM: Mike Bedell, Public Works SUBJECT: Consent Agenda Item Change Order No. l with FHU for the WCR 49/Imboden Road Alignment Study. Attached are two originals, please return a signed original to Public Works. Enclosures M:FrancieAAgendaMikeBedell doe CHANGE ORDER NO.1 WCR 49/Imboden Road Alignment Study Project Description: This transportation study will result in a preferred future alignment for an arterial roadway that will connect WCR 49 to Imboden Road in Adams County. The two agencies are sharing the costs associated with the engineering services. Owner: Weld County Public Works Department, 1111 H Street, Greeley, CO 80632 Consultant: F.H.U., 6300 South Syracuse Way, Suite 600, Centennial, CO 80111 The following change is hereby made to the Contract Documents: Contract Time Extension: The original Contract (work order #FHU-13) is extended 4 months for inclusion of additional meetings and coordination with affected landowners. The anticipated study completion date will change from December 1, 2008 to April 1, 2009. Change to Contract Scope: Unforeseen additional design services, meetings, and coordination with affected landowners caused added expenses. In addition, the team underestimated the original scope of work requirements. The recently completed "O Street" Study cost $48,000. The WCR 49/Imboden Study is similar in length of roadway and scope of work, and will cost $36,630. Each agency will be responsible for 50% of the costs. A description and scope of work of the additional services is attached. CHANGE TO CONTRACT PRICE: Original Contract Amount Change Order No.1 Costs Revised Contract Amount RECOMMENDED: Owner Representative: Engineer: William F. Garcia, Chair APPROVALS: Consultant: F.H.U. Ire. By: $20,000.00 $16,630.00 $36,630.00 ayne Howard, County Engineer CIP V Title: PY�^c`Qti� Date: Date: 02/25/2009 Date: ' - ,?O4P- g/ Weld County Road 49/Imboden Road Alignment Study Change Order #1 This study is encountering numerous additional required tasks that need to be completed in order to properly evaluate the generated alternatives and complete the study of the Weld County Road 49 and Imboden Road corridor. In order to complete the additional tasks as well as those identified below, FHU is requesting Weld County and Adams County to approve this Change Order #1. The following tasks and anticipated budget is FHU's best attempt to anticipate the required work remaining to complete this study along with preparing the final report. There may be circumstances that will be encountered during the completion of the final tasks associated with this project that may not be captured with this estimation. October/November 2008 Initial Open House and Local Agency Meeting — an initial open house will be conducted with the public to present the findings of the alternatives to be evaluated and the anticipated evaluation process that will be followed. The history of Weld County Road 49 as a strategic roadway as well as Imboden Road as a strategic roadway corridor will also be generated to give the public the required background information for the purpose of this study. This task includes the labor to create the "initial" final open house graphics as well. Anticipated Budget — $4,030 24 hours for a Senior Engineer 8 hours for a Senior Designer (Open House Displays/Graphics) Other Direct Costs (Handouts, Plots, Copies, etc.) December 2008 Local Agency Meeting — a local agency meeting will be conducted to discuss the evaluation results. This task will also include the compilation of the received scoring results. Anticipated Budget — $800 6 hours for a Senior Engineer Other Direct Costs (Plots, Copies, etc.) January 2008 Local Agency Meeting — a local agency meeting will be conducted to review the proposed final open house graphics. This task will include the labor required to generate the "draft" final open house graphics as well. Weld County Road 49/Imboden Road Alignment Study — Change Order #1 Page 1 of 2 Anticipated Budget - $2,300 12 hours for a Senior Engineer 8 hours for a Senior Designer (Open House Displays/Graphics) Other Direct Costs (Plots, Copies, etc.) January 2008 Final Open House — a final open house will be conducted with the public to present the findings of the evaluation process and the "preferred alignment". This task will include the labor to create the "final" final open house graphics as well. Anticipated Budget — $4,000 24 hours for a Senior Engineer 8 hours for a Senior Designer (Open House Displays/Graphics) Other Direct Costs (Plots, Copies, etc.) February 2008 Report Preparation — a report will be created that displays the study process and the results of the evaluation process. It is anticipated that a "draft" report will be generated and submitted to the Counties for review, and then a "final" report will be assembled that incorporates that Counties' comments. Anticipated Budget — $5,500 30 hours for a Senior Engineer 4 hours for a Senior Designer (Report Graphics) 20 hours for Administrative (Word Processor) Other Direct Costs (Plots, Copies, etc.) Based on the above -described work, it is estimated that $16,630 is required for this effort. Therefore, FHU is requesting an additional $16,630 to be added to the existing contract amount of $20,000 for a new revised contract amount of $36,630. Weld County Road 49/Imboden Road Alignment Study — Change Order #1 Page 2 of 2 Hello