Hearing Hearing
1 Staff Comments X
Department of Planning Services Field Check Form
Planning Commissioner Field Check Form
Letter to Applicant
Affidavit of sign posting
Legal Notifications
2 Application X
Maps
Deed/Easement Certificate
Surrounding Property/Mineral Owners
Utilities
• 3 Referral List X
Referrals without comment
Weld County Zoning Compliance, referral dated August 5, 2011
Weld County Sheriff's Office, referral dated August 9, 2011
Division of Water Resources referral dated August 9, 2011
Weld County School District RE-1, referral dated August 13, 2011
�' 4 Referrals with comments X
Weld County OEM Office referral dated August 9, 2011
Weld County Department of Public Works, referral dated August 18, 2011
Weld County Department of Public Health and Environment, referral dated
August3l, 2011
City of Greeley, referral dated August 24, 2011
Weld County Department of Building Inspection, referral dated August 31,
2011
5 PC Exhibits X
q, Memorandum to Planning Commissioners dated September 20, 2011
•
2011-2670
S ty.Y , Vt„*;
.
i herebu certLfu that the 5Ltevvs LdentLfted herein were subvu,Ltted to the tp.epartineeht of PLann%ng
Services at or pr-or to the `n leeel,di/��o4 PLc.Vwl.Lng GOWcvvissLovLrs hearing.DV ot,PlaNs19nM q'pm.c,
on:at=us,do CO,et=wem,
EcKO,ou-Weld County,
Ogle omg,00=u:ers.to=am
Ogle
Date 2011 10 06 1452 01 06'00'
K,Lvu ogle O PLawner
.
1861 - 2011
WELD,-COUNTY LAND USE APPLICATION
SUMMARY SHEET
PRELIMINARY
Case Hearing Date: September 20, 2011
Number: USR11-0005
Applicant: DCP MIDSTREAM, LP
Address: Go Patrick Groom, Esq., of Witwer, Oldenburg, Barry & Johnson, LLP
822 71h Street, Suite 760, Greeley CO 80631
Request: A Site Specific Development Plan and a Special Review Permit for Oil and Gas Support and
Service, including oil and gas processing facilities and related equipment, including, but not
limited to, four (4) compressors associated with gas processing or which compress gas to
enter a pipeline for transport to market, in the A(Agricultural) Zone District
Legal Lot B RE-1905; Part NE4 of Section 10, T4N, R66W of the 6th P.M., Weld County,
Description: Colorado
Location: West of and adjacent to County Road 33; Approximately 0.5 miles North of CR 46
• Size of Parcel: 150 +/-acres Parcel Number: 1057-10-1-00-018
POSSIBLE ISSUES SUMMARIZED FROM APPLICATION MATERIALS
The criteria for review of this Special Review Permit is listed in Section 23-2-220 of the Weld County Code.
The Department of Planning Services' staff has received responses with comment from the following
agencies:
➢ Weld County OEM Office referral dated August 9, 2011
Weld County Department of Public Works, referral dated August 18, 2011
• Weld County Department of Public Health and Environment, referral dated August 21, 2011
• City of Greeley, referral dated August 24, 2011
Weld County Department of Building Inspection, referral dated August 31, 2011
The Department of Planning Services' staff has received responses without comment from the following
agencies:
Weld County Zoning Compliance, referral dated August 5, 2011
Weld County Sheriff's Office, referral dated August 9, 2011
'r Division of Water Resources referral dated August 9, 2011
• Weld County School District RE-1, referral dated August 13, 2011
The Department of Planning Services' staff has not received responses from the following agencies:
• State of Colorado, Division of Parks and Wildlife
• Y LaSalle Fire Protection District, referral dated EXHIBIT
KP Kauffman Company
• City of Evans
DCP Midstream, LP—Godfrey Bottoms Compressor Facility,page 1 u11_ s
•
1861 - 2011
SPECIAL REVIEW PERMIT
ADMINISTRATIVE REVIEW
WELft COUNTY
Case Hearing Date: September 20, 2011
Number: USR11-0005
Applicant: DCP MIDSTREAM, LP
Address: do Patrick Groom, Esq., of Witwer, Oldenburg, Barry& Johnson, LLP
822 7th Street, Suite 760, Greeley CO 80631
Request: A Site Specific Development Plan and a Special Review Permit for Oil and Gas Support and
Service, including oil and gas processing facilities and related equipment, including, but not
limited to, four (4) compressors associated with gas processing or which compress gas to
enter a pipeline for transport to market, in the A (Agricultural) Zone District
• Legal Lot B RE-1905; Part NE4 of Section 10, T4N, R66W of the 6th P.M., Weld County,
Description: Colorado
Location: West of and adjacent to County Road 33; Approximately 0.5 miles North of CR 46
Size of Parcel: 150 +/-acres Parcel Number: 1057-10-1-00-018
THE DEPARTMENT OF PLANNING SERVICES'STAFF RECOMMENDS THAT THIS REQUEST BE
APPROVED FOR THE FOLLOWING REASONS:
1. The submitted materials are in compliance with the application requirements of Section 23-2-260 of
the Weld County Code.
2. It is the opinion of the Department of Planning Services'staff that the applicant has shown compliance
with Section 23-2-220 of the Weld County Code as follows:
A. Section 23-2-220.A.1 -- The proposed use is consistent with Chapter 22 and any other
applicable code provisions or ordinance in effect. Section 22-5-100.A. (OG.Goal 1.)states"
Promote the reasonable and orderly exploration and development of oil and gas mineral
resources;" and Section 22-5-100.B. (OG.Goal 2.) states "Ensure that the extraction of oil
and gas resources conserves the land and minimizes the impact on surrounding land and the
existing surrounding land uses;" and Section 22-5-100.B. (OG.Policy 2.9.) states "Impose
protective measures through available state, County and federal regulations to ensure that
the mineral operator conducts operations in a manner that will minimize current and future
environmental impacts." The request for a Site Specific Development Plan and a Special
• Review Permit for a Mineral Resource Development Facility including a Natural Gas
Processing Facility in the A (Agricultural) Zone District is for a new 4 unit gas compressor
DCP Midstream, LP—Godfrey Bottoms Compressor Facility,page 2
• facility, being part of a new five part compressor, pipeline and gas processing plant network
necessitated by the need to move larger volumes of gas due to the recent increases in drilling
activity and projected additional production increases anticipated by producers.
B. Section 23-2-220.A.2--The proposed use is consistent with the intent of the A(Agricultural)
Zone District. Section 23-3-40.A.2 of the Weld County Code provides for Oil and Gas Support
and Service as a Use by Special Review in the A (Agricultural) Zone District.
C. Section 23-2-220.A.3--The uses which will be permitted will be compatible with the existing
surrounding land uses. The property is relatively flat with oil and gas encumbrances present.
Lands to the North, South and West are in agricultural production, with lands to the East
within the City of Evans. There are six(6)single family residences in the immediate vicinity
and also the Five Rivers Ranch Cattle Feeding (JBS) Feedlot[SUP-21]0.5 miles to the west,
and Envirotech one-mile to the north. There are ten (10) property owners within five hundred
feet of this facility. The entire property is presently in old field row crop with oil and gas
encumbrances. Staff has not received any telephone calls, email or letters concerning this
case from surrounding property owners.
D. Section 23-2-220.A.4 -- The uses which will be permitted will be compatible with future
development of the surrounding area as permitted by the existing zoning and with the future
development as projected by Chapter 22 of the Weld County Code and any other applicable
code provisions or ordinances in effect, or the adopted Master Plans of affected
municipalities. The site is within the three mile referral area of the City of Greeley and City of
Evans. The City of Greeley in their referral dated August 24, 2011 had no planning concerns
but did have engineering related recommendations specific to turning radius and site
circulation; stormwater design and drainage related concerns and a notification of the
• required stormwater discharge permit from the Colorado Department of Public Health and
Environment prior to commencing construction. The City of Evans did not return a referral
indicating a conflict with their interests.
E. Section 23-2-220.A.5--The application complies with Section 23-5 of the Weld County Code.
The existing site is not within a recognized overlay district, including the Geologic Hazard,
Flood Hazard or Airport Overlay District. The existing site is within the County-wide Road
Impact Fee, Drainage and County Facility Fee Areas.
Effective April 25, 2011, Building Permits issued on the proposed lots will be required to
adhere to the fee structure of the Weld County Road Impact Program.(Ordinance 2011-2)
Effective April 25, 2011, Building Permits issued on the proposed lots, will be required to
adhere to the fee structure of the County Facility Fee and Drainage Impact Fee. (Ordinance
2011-2)
F. Section 23-2-220.A.6 --The applicant has demonstrated a diligent effort to conserve prime
agricultural land in the locational decision for the proposed use. This proposed facility is
located on a 150 acre parcel utilizing 10 acres for the compressor site. Ongoing agricultural
production will continue on lands not impacted by this proposed facility. The proposed facility
is sited on lands that are designated "Irrigated Not Prime" on the Important Farmlands of
Weld County map dated 1979.
G. Section 23-2-220.A.7 -- The Design Standards (Section 23-2-240, Weld County Code),
Operation Standards (Section 23-2-250, Weld County Code), Conditions of Approval and
Development Standards ensure that there are adequate provisions for the protection of
health, safety, and welfare of the inhabitants of the neighborhood and County.
•
DCP Midstream,LP—Godfrey Bottoms Compressor Facility,page 3
• This recommendation is based, in part, upon a review of the application materials submitted by the applicant,
other relevant information regarding the request, and responses from referral entities
1. Prior to recording the plat:
A. The plat shall be amended to delineate the following:
1. All sheets of the plat shall be labeled USR11-0005. (Department of Planning
Services)
2. The attached Development Standards. (Department of Planning Services)
3. The plat shall be prepared in accordance with Section 23-2-260.D of the Weld
County Code. (Department of Planning Services)
4. The applicant shall delineate the trash collection areas. Section 23-2-260.C.11 and
Section 23-3-350.A.6 of the Weld County Code address the issue of trash collection
areas. Areas used for storage or trash collection shall be screened from adjacent
public rights-of-way and adjacent properties. These areas shall be designed and
used in a manner that will prevent wind or animal scattered trash. (Department of
Planning Services)
5. County Road 33 is designated on the Weld County Road Classification Plan as a
local gravel (Dust Suppression) road, which requires 60 feet of right-of-way at full
build out. The applicant shall verify the existing right-of-way and the documents
creating the right-of-way and this information shall be noted on the plat. All setbacks
• shall be measured from the edge of future right-of-way. If the right-of-way cannot be
verified, it shall be dedicated. This road is maintained by the City of Evans through
an annexation. (Department of Public Works)
6. The City of Evans has jurisdiction over the access to County Road 33 roadway.
Please contact the City of Evans Office to verify the access permit or for any
additional requirements that may be needed to obtain or upgrade the permit.
(Department of Public Works)
7. The applicant shall submit evidence of an approved access from County Road 33.
Proposed traffic includes one employee visiting the site each day and a tractor trailer
every other day to haul produced water from the site. Please show and label on the
Plat, the proposed access width (minimum 20 foot for emergency vehicles), the
turning radiuses into the site(45-60 foot radiuses required to accommodate trucks),
and the proposed 30"RCP culvert at the access.The access shall be placed in such
a location that there is adequate site distance in both directions and not below the
crest of a hill. (Department of Public Works)
8. Tracking control is required to prevent tracking of mud and debris on to the County
roadway. Please show and label a double cattle guard (2 cattle guards placed back
to back to allow for a full rotation of truck tires)at the access. Place the cattle guards
far enough back from the County roadway to allow a tractor trailer to completely pull
off the main roadway before crossing the cattle guards. (Department of Public
Works)
9. Based upon the proposed traffic volumes to this facility a traffic study was not
required. The applicant is indicating approximately one pick up per day by two
• employees and a tractor-trailer rig, one every other day. This will be an unmanned
facility. (Department of Public Works)
DCP Midstream,LP—Godfrey Bottoms Compressor Facility,page 4
• 10. The approved Lighting Plan for the Facility. (Department of Planning Services)
B. The applicant shall address the concerns of the Department of Public Works as indicated in
their referral dated August 18, 2011. (Department of Public Works)
C. The applicant shall submit evidence of an Air Pollution Emission Notice (A.P.E.N.) and
Emissions Permit application from the Air Pollution Control Division, Colorado Department
of Health and Environment, if applicable. Alternately, the applicant can provide evidence
from the APCD that they are not subject to these requirements. (Department of Public
Health and Environment)
D. The applicant shall submit a signed copy of the Spill Prevention, Control and
Countermeasure (SPCC) Plan to the Environmental Health Services Division of the Weld
County Department of Public Health & Environment. (Department of Public Health and
Environment)
E. The applicant shall submit a Lighting Plan for review and approval and include the
manufacture's cut sheets for each of the proposed lighting fixtures and lamps to the
Department of Planning Services. (Department of Planning Services)
F. The applicant shall provide written evidence of compliance with the Tier II reporting and the
development of a Risk Management Plan if this facility meets the EPA standard for reporting.
Further, the applicant shall provide Tier II documentation to the Weld County LEPC and the
Fire District as required. (Sheriff's Office)
• G. The applicant shall either submit a copy of an agreement with the property's mineral
owner/operators stipulating that the oil and gas activities have been adequately incorporated
into the design of the site or show evidence that an adequate attempt has been made to
mitigate the concerns of the mineral owner/operators. Drill envelopes can be delineated on
the plat in accordance with the State requirements as an attempt to mitigate concerns. The
plat shall be amended to include any possible future drilling sites. (Department of Planning
Services)
H. The applicant shall submit two (2) paper copies of the plat for preliminary approval to the
Weld County Department of Planning Services. (Department of Planning Services)
2. Prior to Construction:
A. The project will disturb over an acre of land therefore, a Weld County Grading Permit is
required before construction. The grading permit application must include the grading plan,
erosion and sediment control plan, typical BMP installation details, typical BMP installation
and maintenance notes, and a copy of the Colorado Department of Health and Environment
construction stormwater discharge permit. (Department of Public Works)
B. Building permits shall be obtained prior to the construction of any structure or change of
use of any building. (Department of Building Inspection)
C. A plan review is required for each building. Plans require the wet stamp of a Colorado
registered architect or engineer. (Department of Building Inspection)
D. Buildings shall conform to the requirements of the codes adopted by Weld County at the
time of permit application. Current adopted codes include the 2006 International
• Residential Code; 2006 International Building Code; 2006 International Mechanical Code;
2006 International Plumbing Code; 2006 International Fuel Gas Code; 2006 International
DCP Midstream,LP—Godfrey Bottoms Compressor Facility,page 5
• Energy Conservation Code; 2008 National Electrical Code and Chapter 29 of the Weld
County Code. (Department of Building Inspection)
E. Each building will require an engineered foundation based on a site-specific geotechnical
report or an open hole inspection performed by a Colorado registered engineer.
Engineered foundations shall be designed by a Colorado registered engineer.
(Department of Building Inspection)
F. Fire resistance of walls and openings, construction requirements, maximum building
height and allowable areas will be reviewed at the plan review. Setback and offset
distances shall be determined by the Weld County Code. (Department of Building
Inspection)
G. Building height shall be measured in accordance with the 2006 International Building
Code for the purpose of determining the maximum building size and height for various
uses and types of construction and to determine compliance with the Bulk Requirements
from Chapter 23 of the Weld County Code. (Department of Building Inspection)
H. Building height shall be measured in accordance with Chapter 23 of the Weld County
Code in order to determine compliance with offset and setback requirements. Offset and
setback requirements are measured to the farthest projection from the building.
(Department of Building Inspection)
Provide letter of notification from the LaSalle Fire Protection District having jurisdiction
prior to any new construction. (Department of Building Inspection)
• 3. Upon completion of 1. above the applicant shall submit a Mylar plat along with all other documentation
required as Conditions of Approval. The Mylar plat shall be recorded in the office of the Weld County
Clerk and Recorder by Department of Planning Services' Staff. The plat shall be prepared in
accordance with the requirements of Section 23-2-260.D of the Weld County Code. The Mylar plat
and additional requirements shall be submitted within sixty (60) days from the date of the Board of
County Commissioners resolution. The applicant shall be responsible for paying the recording fee.
(Department of Planning Services)
4. The Department of Planning Services respectively requests the surveyor provide a digital copy of
this Amended Use by Special Review. Acceptable CAD formats are .dwg, .dxf, and .dgn
(Microstation); acceptable GIS formats are ArcView shapefiles, ArcInfo Coverages and Arclnfo
Export files format type is .e00. The preferred format for Images is .tif(Group 4). (Group 6 is not
acceptable). This digital file may be sent to mapsco.weld.co.us. (Department of Planning
Services)
5. In accordance with Weld County Code Ordinance 2005-7 approved June 1, 2005, should the plat not
be recorded within the required sixty(60)days from the date of the Board of County Commissioners
resolution a$50.00 recording continuance charge shall be added for each additional 3 month period.
(Department of Planning Services)
6. The Special Review activity shall not occur nor shall any building or electrical permits be issued on
the property until the Special Review plat is ready to be recorded in the office of the Weld County
Clerk and Recorder. (Department of Planning Services)
•
DCP Midstream,LP—Godfrey Bottoms Compressor Facility,page 6
• SITE SPECIFIC DEVELOPMENT PLAN
SPECIAL REVIEW PERMIT
DEVELOPMENT STANDARDS
DCP Midstream —Godfrey Bottoms Facility
U S R 11-0005
1. The Site Specific Development Plan and a Special Review Permit for Oil and Gas Support and
Service, including oil and gas processing facilities and related equipment, including, but not limited to,
four(4) compressors associated with gas processing or which compress gas to enter a pipeline for
transport to market, in the A(Agricultural)Zone District, and subject to the Development Standards
stated hereon. (Department of Planning Services)
2. Approval of this plan may create a vested property right pursuant to Section 23-8-10 of the Weld
County Code. (Department of Planning Services)
3. All liquid and solid wastes (as defined in the Solid Wastes Disposal Sites and Facilities Act, 30-20-
100.5, C.R.S., as amended) shall be stored and removed for final disposal in a manner that protects
against surface and groundwater contamination. (Department of Public Health and Environment)
4. No permanent disposal of wastes shall be permitted at this site. This is not meant to include those
wastes specifically excluded from the definition of a solid waste in the Solid Wastes Disposal Sites
and Facilities Act, 30-20-100.5, C.R.S., as amended. (Department of Public Health and Environment)
5. Waste materials shall be handled, stored, and disposed in a manner that controls fugitive dust,
fugitive particulate emissions, blowing debris, and other potential nuisance conditions.(Department of
• Public Health and Environment)
6. The applicant shall operate in accordance with the approved "waste handling plan" at all times.
(Department of Public Health and Environment)
7. Fugitive dust shall be controlled on this site. (Department of Public Health and Environment)
8. This facility shall adhere to the maximum permissible noise levels allowed in the Industrial Zone as
delineated in 14-9-30 of the Weld County Code, or with all applicable State noise statutes and/or
regulations. (Department of Public Health and Environment)
9. A permanent, adequate water supply shall be provided for drinking and sanitary facilities when there is
at least one full time employee located on the facility. (Department of Public Health and Environment)
10. An Individual Sewage Disposal System shall be provided when there is at least on full time employee
stationed on site. (Department of Public Health and Environment)
11. Any septic system located on the property must comply with all provisions of the Weld County Code,
pertaining to Individual Sewage Disposal Systems. (Department of Public Health and Environment)
12. All potentially hazardous chemicals must be stored and handled in a safe manner in accordance with
product labeling and in a manner that minimizes the release of hazardous air pollutants(HAP's)and
volatile organic compounds(VOC's). All chemicals must be stored secure,on an impervious surface,
and in accordance with manufacturer's recommendations. (Department of Public Health and
Environment)
13. If applicable, the applicant shall obtain a stormwater discharge permit from the Colorado Department
• of Public Health & Environment, Water Quality Control Division. (Department of Public Health and
Environment)
DCP Midstream,LP—Godfrey Bottoms Compressor Facility,page 7
• 14. The applicant shall comply with all provisions of the State Underground and Above Ground Storage
Tank Regulations. (Department of Public Health and Environment)
15. The operation shall comply with all applicable rules and regulations of the State and Federal agencies
and the Weld County Code. (Department of Public Health and Environment)
16. A building permit shall be obtained prior to the construction of any new structures. (Department of
Building Inspection)
17. A plan review is required for each building or structure for which a building permit is required. Two
complete sets of plans are required when applying for each permit. Include a Code Analysis Data
sheet with each Building permits Submittal plans shall include a floor plan showing the specific
uses of each area for the building. The Occupancy Classification will be determined by Chapter 3
of the 2006 International Building Code. The plans shall also include the design for fire separation
and occupancy separation walls, when required by Chapter 5 and 7 of the 2006 International
Building Code. Fire Protection shall conform to Chapter 9. (Department of Building Inspection)
18. Buildings shall conform to the requirements of the various codes adopted at the time of permit
application. Currently the following has been adopted by Weld County: 2006 International Building
Code; 2006 International Mechanical Code; 2006 International Plumbing Code; 2006 International
Fuel Gas Code; and the 2008 National Electrical Code and Chapter 29 of the Weld County Code.
(Department of Building Inspection)
19. All building plans shall be submitted to the LaSalle Fire Protection District for review and approval
prior to issue of Building Permits, (Department of Building Inspection)
• 20. The historical flow patterns and run-off amounts will be maintained on site in such a manner that it will
reasonably preserve the natural character of the area and prevent property damage of the type
generally attributed to run-off rate and velocity increases,diversions,concentration and/or unplanned
ponding of storm run-off. (Department of Public Works)
21. The applicant must take into consideration storm water capture/quantity and provide accordingly for
best management practices. (Department of Public Works)
22. Weld County is not responsible for the maintenance of onsite drainage related features. (Department
of Public Works)
23. Off-street parking spaces including the access drive shall be surfaced with gravel and shall be graded
to prevent drainage problems. (Department of Public Works)
24. This area IS NOT in a Special Flood Hazard Area(SFHA)as determined by the Federal Emergency
Management Agency (FEMA). (Department of Public Works)
25. The applicant is required to comply with all Colorado Oil and Gas Conservation Commission
(COGCC) rules and regulations including drill pad construction, storm water controls, and
reclamation. (Department of Planning)
26. Effective April 25, 2011, Building Permits issued on the proposed lots will be required to adhere to the
fee structure of the Weld County Road Impact Program.(Ordinance 2011-2)(Department of Planning)
27. Effective April 25, 2011, Building Permits issued on the proposed lots,will be required to adhere to the
fee structure of the County Facility Fee and Drainage Impact Fee. (Ordinance 2011-2) (Department
of Planning)
• 28. The facility will operate 24 hours per day 365 days per year. (Department of Planning Services)
DCP Midstream,LP—Godfrey Bottoms Compressor Facility,page 8
• 29. The facility will comply with the approved Lighting Plan and Section 23-3-250.D.1 Lighting Standards
of the Weld County Code. (Department of Planning Services)
30. The facility is unmanned,without permanent employees on site. (Department of Planning Services)
31. The property owner or operator shall be responsible for complying with the Design Standards of
Section 23-2-240, Weld County Code. (Department of Planning Services)
32. The property owner or operator shall be responsible for complying with the Operation Standards of
Section 23-2-250, Weld County Code. (Department of Planning Services)
33. Necessary personnel from the Weld County Departments of Planning Services, Public Works, and
Public Health and Environment shall be granted access onto the property at any reasonable time in
order to ensure the activities carried out on the property comply with the Conditions of Approval and
Development Standards stated herein and all applicable Weld County regulations. (Department of
Planning Services)
34. The Special Review area shall be limited to the plans shown hereon and governed by the foregoing
standards and all applicable Weld County regulations. Substantial changes from the plans or
Development Standards as shown or stated shall require the approval of an amendment of the Permit
by the Weld County Board of County Commissioners before such changes from the plans or
Development Standards are permitted. Any other changes shall be filed in the office of the
Department of Planning Services. (Department of Planning Services)
35. The property owner or operator shall be responsible for complying with all of the foregoing
• Development Standards. Noncompliance with any of the foregoing Development Standards may be
reason for revocation of the Permit by the Board of County Commissioners. (Department of Planning
Services)
•
DCP Midstream, LP—Godfrey Bottoms Compressor Facility,page 9
PLANNING COMMISSION AND BOARD OF COUNTY
• COMMISSIONERS' SIGN POSTING CERTIFICATE
THE LAST DAY TO POST THE SIGN IS SEPTEMBER 9, 2011 THE SIGN SHALL BE POSTED
ADJACENT TO AND VISIBLE FROM A PUBLICALLY MAINTAINED ROAD RIGHT-OF-WAY.
IN THE EVENT THE PROPERTY BEING CONSIDERED FOR A SPECIAL REVIEW IS NOT
ADJACENT TO A PUBLICALLY MAINTAINED ROAD RIGHT-OF-WAY, THE DEPARTMENT
OF PLANNING SERVICES SHALL POST ONE SIGN IN THE MOST PROMINENT PLACE ON
THE PROPERTY AND POST A SECOND SIGN AT THE POINT AT WHICH THE DRIVEWAY
(ACCESS DRIVE) INTERSECTS A PUBLICALLY MAINTAINED ROAD RIGHT-OF-WAY.
I, KIM OGLE, HEREBY CERTIFY UNDER PENALTIES OF PERJURY THAT THE SIGN WAS
POSTED ON THE PROPERTY AT LEAST TEN DAYS BEFORE THE PLANNING
COMMISSIONERS HEARING AND THE BOARD OF COMMISSIONERS HEARING FOR A SITE
SPECIFIC DEVELOPMENT PLAN AND A SPECIAL REVIEW PERMIT FOR OIL AND GAS
SUPPORT AND SERVICE, INCLUDING OIL AND GAS PROCESSING FACILITIES AND
RELATED EQUIPMENT, INCLUDING, BUT NOT LIMITED TO, FOUR (4) COMPRESSORS
ASSOCIATED WITH GAS PROCESSING OR WHICH COMPRESS GAS TO ENTER A PIPELINE
FOR TRANSPORT TO MARKET, IN THE A (AGRICULTURAL) ZONE DISTRICT
KIM OGLE
Name of Person Posting Sign
• Sig ure of Person Posting Sign
STATE OF COLORADO
) ss.
COUNTY OF WELD # b
The foregoing instrument was subscribed and sworn to me this I ljj 9 day of 2011
WITNESS my hand and official seal.
pVUI IIV4``''
ya`�.... • (ter J1,;,
(: tt
q,pir- . c,,
f.,
o ary Public al\ BLNG C '?
My Commission Expires: I
•
aratitiLame4j1 V A F lam1 A` • 1 1 �0 W il 'O
u. cr in
Mida �� W o ` V4 ia:ice: (n
CZ
y�. O am,
awzo � oV �J• w 0 W ( , � 1 r
CCE.
LINJ
< OOcUI It uni
If
(2 tui-- if) M a Cea re) , # k
C3 CCI
g % 4.
isizZ00 Si 9..... Ina laml I
• Orli, hi; / ( , ri,
0 Cm' ea o J l— CC c� -�-. Sri ,
i .11_ Lin I i I I)/
�� Z N Q2 z ? tea Q Q 'Ina >IC 6 , 3t1iv
_ CD ! " Zvz � z a � �'N^` 4 .
�.
Wlin M D.
illi LIRA1 ` • t
20 < ° � 742 ; ';! .
OQOUw ,n I . � �♦
0 Lail lir W CL I- w w w
tu
.. o a a a' a oN i l I , r ri g, Jr
ZZO .....
crcr ag - W Z
CAaCIMI) craw J = Men Acipi.
Ina %is 8 0 L L,,, i .:-.-, . ,_ (2 0 0 a
z ---% Pi AT
(,) _, . 0 . cr , , , . , ., , •
cc ....,
cizzi wc.,,,m< a ilc_ .7 6 (,) 0 , zi ‘ ..._
• ca IP
8 o 1 1
.0._,,t
s _.
4* F 9 =
B 4mompe
��_� .l o It Oa CO) W W O m 1.... c., et 0 all cr) +/b :'y
Wit Milo ID1) W `� ii \ ,pi�� ` y,�
IcS � � Q = z Q d cn W l , , . 1 �
0 Z o ,
% --
,
.1. . ., op/
i I e kIiii if g ?WI II : kitIgigalWaS Vitt 4j1 d146" ..
0 1 • •
Li1 21 CDl ; .
° � ® Ca ' Vii.
14;Ca I I__ O D w
- LL a WWI
CC 0 I; w.1
O av0- v0 V al '`\
\ U cc �J w a w v Q Q �� �.Iril kir _..... 1 cr < ::i> x w
�a W wv1 � 32CIC a �, w�
p CC e lie
Q O<COO OZ?
fa U z Z o y' .
1111 lawl co - co W <I F-- se M a Cei en '
!Y
. (1) } ° w ¢ 1
O pp m � ZU2 p W
_ wZ o0kr . , , .
-+ 1 o z � (iQa )1C ; : -� -
4i 2 (1 2 CC Cle...... z i§
vir
0 I- CCM O 1.- fr-
z w CrFin a I
U g,
w ,njF- O �
� owgLLi- 0 Q a , I1
az Uwe `z"�' ; may
OaOOzo y �y • s'
0 CC Fa
lL H FW- N -d W , , '
ni
WOea Q 5 Q a 6 Z CO , t . 1 �
pa w (1) if. N Wall 0
Wry CZ � z ° W � I _ ' . , ' '
v ell or a w i- D la, C� .� It
Ca'Ai � wauzi � s
�� Q w z r �_a 0 o u `�005 i If': I •1
ei gr 3 Is- (n _JU i < a i§db,, U° a = li?
; is
tz Cn S at 2e C:2 os ....... ' 444:-
• '�. Milo pr W L.a� -a i 111 ' '
�U 3 a Q LLD Q W 1 i . ,
f J ILL �•• , { , � 1
.) ```1(! ., 4')• iT 4 `�, / ,I �• '�-y� 41 [ ,l* 4
10/4/2011
•
. ,.
t Y . a
. L
l 1
- -
View to South
• fp tc •
•
1
10/4/2011
•
jelliiiiiiiiiiiiiiiiiiIMS- . -
1 -
k ti ,
•
E
. , • , ' .• x. vI 4o East
•
4
-
! ti
7-
b�
el,
} i N
• y
• • •
•
•
.
S
2
10/4/2011
•
•
r
S
r. 16
•1
I
p r
!
I
3
10/4/2011
•
.
•
•
went24,1
1 .
,r - --
• k •
r '< r "w to Northwest
mac +-�` Y 'L +
r .4J earl �� • 'r .. - � ~ _
•
•
4 '
p
View tc Last
korimudists4
•
4
10/4/2011
•
.•
•
••
.. . ..
I
4,41=3 VN- I
0.
1•♦ are... .''s'r r -rr7•
-p •
,4
r:
_.
•
I
„'
t. ye r ,•. ast
0
t r . �.
Jle. Illi ' -. mai -,,
•
•
a I 'r
View South from Site
iii
•
5
FIELD CHECK Inspection Date: August 25, 2011
• Case
Number: USR11-0005
Applicant: DCP MIDSTREAM, LP
Address: do Patrick Groom, Esq., of Witwer, Oldenburg, Barry & Johnson, LLP
822 7th Street, Suite 760, Greeley CO 80631
Request: A Site Specific Development Plan and a Special Review Permit for Oil and Gas Support
and Service, including oil and gas processing facilities and related equipment, including,
but not limited to, compressors associated with gas processing or which compress gas to
enter a pipeline for transport to market, in the A(Agricultural) Zone District
Legal Lot B RE-1905; Part NE4 of Section 10, T4N, R66W of the 6th P.M., Weld County,
Description: Colorado
Location: West of and adjacent to County Road 33; Approximately 0.5 miles North of CR 46
Size of Parcel: 150 +/- acres Parcel Number: 1057-10-1-00-018
Zoning Land Use
N Agricultural N Residential/Agricultural
E Agricultural E Residential/Agricultural
S Agricultural S Residential/Agricultural
W Agricultural W Agricultural
• Comments:
County Road 33 is an all weather road with bar ditches. There is no existing road to the North of the
property. County Road 46 is approximately 0.5 miles to the South of the site. There are oil and gas
encumbrances on site (well heads and tank battery(s)) operated by KPKauffman and Kauffman and
Weinberger. The site is relatively flat and appears to have historically been planted in an agricultural row
crop.
Off-site improvements include OH electric on wood poles, and underground telephone on east side of
CR 33. Public Service and Atmos have underground gas pipeline both sides of CR 33 and Central Weld
County Water District has an underground water line on the west side of CR 33.
There are six residences on CR 33, one in each dry corner of the center pivot and four residences to the
east, with three being located close to the road behind 6-foot in eight privacy fences. The fourth is sited
back from the road
Five Rivers Feedlot (JBS) is 0.5 miles to the west and Envirotech is located 1 mile north of this proposed
facility.
Sign
❑ Access to Property ❑ Irrigation Sprinkler
❑ Oil & Gas Structures
• Note any commercial business/commercial vehicles that are operating from the site.
Kristine Ranslem
From: Kristine Ranslem
art: Friday, August 05, 2011 4:01 PM
'pdpark@dcpmidstream.com'; 'pgroom@wobjlaw.com'
Subject: Case USR11-0005
Attachments: Applicant letter.pdf; image003.png
Please see the attached letter. If you have any questions, please let us know. Thank you!
K.VLstLvv,e R2v1,5Lewt
Planning Technician
Weld County Planning Services
1555 N 17th Ave, Greeley CO 80631
970-353-6100 ext. 3519
,. ,, ii
W FCo -€6.1 NTT
u_
Confidentiality Notice: This electronic transmission and any attached documents or other writings are intended only for
the person or entity to which it is addressed and may contain information that is privileged, confidential or otherwise
Ilitected from disclosure. If you have received this communication in error, please immediately notify sender by return
mail and destroy the communication. Any disclosure, copying, distribution or the taking of any action concerning the
contents of this communication or any attachments by anyone other than the named recipient is strictly prohibited.
•
1
• 1 8 6 I - 2 0 I I DEPARTMENT OF PLANNING SERVICES
1555 N 17th AVE
GREELEY, CO 80631
PHONE: (970)353-6100, Ext. 3540
FAX: (970)304-6498
WEL eO NTY
August 5, 2011
WETCO Farms, Inc.
do DCP Midstream
3026 4th Ave
Greeley CO 80631
Subject: USR11-0005 - Request for a Site Specific Development Plan and Use by Special Review
Permit for Oil and Gas Support and Service, including oil and gas processing facilities and
related equipment, including, but not limited to, compressors associated with gas processing
or which compress gas to enter a pipeline for transport to market, in the A (Agricultural) Zone
District on a parcel of land described as Lot B RE-1905; Part NE4 Section 10, T4N, R66W of
the 6th P.M., Weld County, Colorado of the 6th P.M., Weld County, Colorado.
Dear Applicants:
• Your application and related materials for the request described above are being processed. I will
schedule a meeting with you to discuss the referrals after we have received them.
Once the concerns and requirements of the referral agencies have been met or the applicant has shown
an attempt to meet their concerns and requirements, a Planning Commission Hearing will be scheduled.
It is the policy of Weld County to refer an application to any town or municipality lying within three miles of
the property or if the property is located within the comprehensive planning area of a town or municipality.
Therefore, our office has forwarded a copy of the submitted materials to the Evans and Greeley Planning
Commission for their review and comments. Please call Evans at 970-339-5344 and Greeley at 970-350-
9741 for further details regarding the date, time, and place of this meeting. It is recommended that you
and/or a representative be in attendance at the Evans and Greeley Planning Commission meeting to
answer any questions the Commission members may have with respect to your application.
If you have any questions concerning this application, please call.
Respectfunv.
1.4 Digitally signed by Kristine Ransom
Reason:I am the author of this document
Location:1555 N 17th Ave
Date:2011.08.05 13:34:12-06'00'
Kim Ogle
Planner
•
DEPARTMENT OF PLANNING SERVICES
Kit1555 North 17th Avenue
1l Greeley, CO 80631
u
• \ 7 ) 53-610 Ext.3 .40
l\\ Phone: (970)353-6100 3540
Fax: (970)304-6498
C
COLORADO
PLANNING INVOICE and RECEIPT SUMMARY
August 01, 2011
Permit Number: USR11-0005
Owner Name: Wetco Farms
Address:
Application Type: Planning\Use By Special Review\NA\NA
Applicant: Groom Patrick
DCP Midstream
INVOICES:
Invoice# 53606 Amount
ell Other Use by Special Review Permits $2,500.00
Total Fee: $2,500.00
PAYMENTS:
Payment Payment
Receipt# Method Ref# Pavor Date Amount Cashier
Check 292695 Groom Patrick DCP Midstream 08/01/2011 $2,500.00 KOGLE
Total Paid: $2,500.00
•
Report ID: PL00001v001 Page 1 of 1
Print Date-Time: 8/1/2011 10:56:01 AM
Hello