HomeMy WebLinkAbout20121129.tiff RESOLUTION
RE: APPROVE IMPROVEMENTS AGREEMENT ACCORDING TO POLICY REGARDING
COLLATERAL FOR IMPROVEMENTS, AUTHORIZE CHAIR TO SIGN, AND ACCEPT
COLLATERAL FOR USE BY SPECIAL REVIEW PERMIT #1668 - PETER AND
HEATHER VALCONESI
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, on October 29, 2008, the Weld County Board of Commissioners approved
Use by Special Review Permit #1668, for Joseph and Bonnie Rutledge, 2474 West 880 North,
Hurricane, Utah 84737-3473, c/o Pete and Heather Valconesi, 21769 County Road 15,
Johnstown, Colorado 80534, for a Use Permitted as a Use by Right or Accessory Use in the
Commercial or Industrial Zone Districts (assemble wall components for laundromats and a
secondary residence) in the A (Agricultural) Zone District, on the following described real estate,
to-wit:
Lot B of Recorded Exemption #4254; being part of
the NE1/4 of Section 14, Township 4 North, Range
68 West of 6th P.M., Weld County, Colorado
WHEREAS, pursuant to certain Conditions of Approval, the Board has been presented
with an Improvements Agreement According to Policy Regarding Collateral for Improvements
between the County of Weld, State of Colorado, by and through the Board of County
Commissioners of Weld County, and Peter and Heather Valconesi, with terms and conditions
being as stated in said agreement, and
WHEREAS, the Board has been presented with Cashier's Check #1000064515 from
Bank of the West, 500 Capital Mall, Suite 1200, Sacramento, California 95814, in the amount of
$16,500,00, and
WHEREAS, after review, the Board deems it advisable to approve said agreement and
accept said Cashier's Check as stated above, copies of which are attached hereto and
incorporated herein by reference.
WHEREAS, when the project is completed and the applicant requests the release of 85
percent of the above amount, the check needs to be addressed to both Bank of the West, and
Peter Valconesi, jointly, with the check being sent to Peter Valconesi, c/o High Mark
Manufacturing, Inc., P.O. Box 212, Johnstown, Colorado 80534, so that he can endorse it and
then forward the check to Bank of the West.
P�v 3849077 Pages: 1 of 24
05/30/2012 08:09 AM R Fee:$0.00
�_u ,i a Ill h'lti�IlY�lh��l�h'n4d 1Recorder
Weld
hrM1rGllb�Ih}County,
«ti I� l 11 III 2012-1129
PL198282
IMPROVEMENTS AGREEMENT- PETER AND HEATHER VALCONESI
PAGE 2
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of
Weld County, Colorado, that the Improvements Agreement According to Policy Regarding
Collateral for Improvements between the County of Weld, State of Colorado, by and through the
Board of County Commissioners of Weld County, and Peter and Heather Valconesi, be, and
hereby is, approved.
BE IT FURTHER RESOLVED that Cashier's Check #1000064515 from Bank of the
West, 500 Capital Mall, Suite 1200, Sacramento, California 95814, in the amount of$16,500,00,
be and hereby is, accepted.
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 30th day of April, A.D., 2012.
BOARD OF COUNTY COMMISSIONERS
' j WELD COUNTY, COLORADO
ATTEST: j �t..z O �c
Sean P. Conway, Chair
Weld County Clerk to the Board es4".
,illiam F. rcia,`Pro-T-m
BY: iM
Deputy Clbk to the Boantia.i � �� _ , At i > _,�
I/�pplll •� a Kirkmeyer
APP ED RM: ( T N \
ie avid E. Long
C unty Attorney It SY i`
CQ,
Dougl s Rademache
Date of signature: 5 (9,9 /a
3849077 Pages: 2 of 24
05/30/2012 08:09 AM R Fee:$0.00
�IY�II��r+���fne4 ��ehhl�ti�ty l I IN�L 11 111
2012-1129
PL1982
MEMORANDUM
TO: Clerk to the Board
1861
DATE: 4/25/2012
y FROM: Richard Hastings, Public Works Department
v2Ie -
11
� N T �
SUBJECT: BOCC Agenda Item - Approve Improvements
Agreement and Accept Collateral For:
Valconesi- (USR-1668)
Request for Approval of Improvements Agreement:
The Department of Public Works and the Department of Planning Services received a request
from the applicant, Peter Valconesi, requesting that the Board of County Commissioners consider
approving the Improvements Agreement for the Wall Component Assembly Facility for
Laundromats, and a secondary residence (USR-1668), located on CR's 46 & 11, northeast of the
town of Berthoud.
Weld County Public Works Department reviewed the above-mentioned signed original document
and observed the following:
• All Public Works related items, of the"Improvements Agreement According To Policy
Regarding Collateral For Improvements", are found to be acceptable.
Request for Acceptance of Collateral:
The Department of Public Works and the Department of Planning Services received a request
from the applicant, Peter Valconesi requesting that the Board of County Commissioners consider
accepting collateral in the form of a Cashier's Check—(Bank of the West) in the amount of
$16,500.00, for the above-mentioned Improvements Agreement.
Recommendation:
The Department's of Public Works and Planning Services are recommending approval of the
Improvements Agreement According To Policy Regarding Collateral For Improvements and the
acceptance of collateral, in the amount of$16,500.00 for Valconesi - (USR-1668).
pc: Don Carroll, Public Works
Kim Ogle, Planning Services
C:\Documents and Settings\dbechler\Local Settings\Temporary Internet Files\Contcnt.Outlook\HDO4AU84\Approve IA Accept Collateral(USR-
1668)-Valconesi-MEMO.docx
IMPROVEMENTS AGREEMENT ACCORDING TO
POLICY REGARDING COLLATERAL FOR IMPROVEMENTS
Valconesi — USR-1668
fl ,(�
THIS AGREEMENT, made and entered into this -/ day of /"la ceel
by and between the County of Weld, State of Colorado, acting through its Board of County
Commissioners, hereinafter called "County," and Peter and Heather Valconesi, hereinafter called
"Property Owner."
WITNESSETH:
WHEREAS, Property Owner is the owner of, the following described property in the
County of Weld, Colorado:
Part of Lot B of RE-4254; Part of NE4 of Section 14, Township 4 North, Range
68 West of the 6th P.M., Weld County, Colorado and
hereinafter referred to as "the Property," and
WHEREAS, County has approved land use permits for a Wall Component Assembly
Facility for Laundromats, and a secondary residence, on approximately 14.94 acres on the above
described real property, and the County is currently in the process of considering an Use-by-
Special Review for the Property (USR-1668), and
WHEREAS, the Property Owner acknowledges that the issuance of USR-1668 is
conditional upon Property Owner's performance of the on-site and off-site improvements which
are described in this Agreement and depicted in the USR Plat Map and the set of accepted
Construction Plans provided by Property Owner, copies of which shall be attached to this
Agreement as they become available and made a part hereof, as Exhibits C and D, respectively,
and
WHEREAS, Property Owner acknowledges that it may not engage in any activity
described in USR-1668 and/or any activity related to the businesses described above until said
improvements have been completed, and
WHEREAS, Property Owner agree that pursuant to the provisions of Weld County Code
Sec. 23-2-290, the failure to commence construction of the improvements outlined herein or to
commence the use of the Property as approved in USR-1668 within three (3) years of the
approval of the permit issued under USR-1668, may result in the revocation of USR-1668, upon
consideration and order of the Board of County Commissioners, and
WHEREAS, the Property Owner agrees that the failure to record the plat within the time
limits imposed by the Weld County Board of County Commissioners, may result in the
revocation of USR-1668, upon consideration and order of the Board of County Commissioners.
and
WHEREAS, the parties agree that Property Owner shall provide collateral for all on-site
M'.API ANN INC-DGVGLORM FAT RE.VIF.WVUSR-Lse by Special Rea lewNSR-1668 ValconcssiAhnpravements AgeeemwtlValconesi(USR-
1668)Final IA (3-7-I 2)dace
2012-1129
3849077 Pages: 3 of 24
05/30/2012 08:09 PM R Fee:$0.00
Steve Moreno, Clerk and Recorder. Weld County, CO
lull
and off-site improvements required by this Agreement when the Property Owner submits and
receives approval of an application for a Grading Permit, Building Permit or for a Right-Of-Way
Permit for construction of accesses and work within the County and/or State of Colorado Right-
Of-Way, or at a time determined acceptable by the Board of County Commissioners.
NOW, THEREFORE, IN CONSIDERATION OF the foregoing and of the promises and
covenants contained herein, the parties hereto promise. covenant and agree as follows:
A. Required Off-Site Improvements
1.0 Weld County Road 46: The Property Owner shall be responsible for the
construction of certain on-site and off-site safety improvements, which shall include:
construction of adequate turning radii sixty (60) feet at the main entrances and exits which
extend partially into CR 46 right-of-way (ROW), drainage and signage installations, as indicated
on the accepted Construction Plans. The main entrance improvements will include a double
cattle guard set (one right after the other), placed back to back across the entire width of the
roadway, to ensure a complete revolution of the truck tires in order minimize the tracking of mud
and debris onto the adjacent County road. (See Section D.2.0 of this Agreement). Granting of
any new point of access may generate additional obligations with County for Off-Site
Improvements and the need to post additional "Road Maintenance Collateral".
2.0 Road Improvements Responsibilities: Property Owner is solely responsible for all
designated improvements, as specified above in Section A.I.0. on CR 46 and for any
construction improvements mandated by the County, and for all expenses associated therewith.
These responsibilities include, but are not limited to the following: design, surveys, utility
locates, present and future right-of-way clearances and permits; coordination with oil and gas
operators and facilities, and affected irrigation facilities; traffic control; and project safety during
construction. Property Owner shall obey all applicable regulations issued by the Occupational
Safety and Health Administration (hereinafter "OSHA"), Colorado Department of Public Health
and Environment, (hereinafter "CDPHE") and other regulatory agencies.
3.0 Engineering Design and Construction Plans: All engineering designs and
construction plans must be provided by Property Owner. These Plans, when reviewed and
accepted by the Weld County Engineer, shall be a part of the Plans, which are a part of this
Agreement. All plans showing work within the County shall be reviewed and accepted by Weld
County, prior to the start of construction. For all construction in the County right-of-way, prior to
the issuance of any access permit or right-of-way permit, a construction schedule giving times
and locations of all proposed improvements shall be provided to Public Works for review and
acceptance.
4.0 Construction Standards: All construction and materials controls for a project and
any designated improvements shall conform to the requirements in effect as the time of the
completion of the improvements set forth in the "Standard Specifications for Road and Bridge
Construction" provided by CDOT.
5.0 Traffic Control: Prior to any construction in the County Right-Of-Way and as a
condition of issuance of any access permit or Right-Of-Way permit, the applicant shall submit a
M'.APLANNING-DEVELOPMENT REVIEWVUSR-Use by Special ReviewVUSR-I 668 ValconessiAImprovements AgreementAValconesi(I1SR-
1668)Final IA (3-7-I2).docx
3849077 Pages: 4 of 24
0 :0 qM Fee
Steve5/30/2012 Moreno 08
.. Cler9k and Recorder, Wel0d County, CO
VIII IVY IIPnYuVIRI+4 GWh IflL'bF11th�Yl+lil�,�ir MI°1 II III
traffic control plan for County review. During construction, appropriate safety signage shall be
posted in accordance with the then current version of the "Manual of Uniform Traffic Control
Devices".
6.0 Off-Site Dust Control/Abatement and/or Paving (If Applicable): The Property
Owner is required to provide dust abatement along affected County Roads approximately two to
five times per year, as determined by the County. County will determine the proportionate share
of dust control and/or paving costs to be paid by Property Owner based upon then current Truck
Trip — Equivalent Single Axle Load (ESAL) Counts that identify traffic loading due to Property
Owner-sourced traffic. The amount and extent of dust control will be determined by site-specific
conditions at the time, as determined exclusively by County personnel. In order to accurately
determine percentage of Property Owner haul truck traffic, the County reserves the right to
install traffic counters on the driveway(s) of their facility. The percentage of haul truck traffic
utilizing County roads in the vicinity of the site attributable to Property Owner (or their
contractors, clients, tenants, or customers) activities will be determined by traffic counts
conducted by the County on the primary and requested alternate or revised haul routes. The
County will have sole responsibility for determination of the percentage of truck traffic on all
affected roads.
7.0 Future Improvements: Future improvements to the haul route(s) may be required
by County. Property Owner shall address all County access issues associated with afore-
mentioned haul route. Future County mandated measures may include improvements to any haul
route intersections or roadways then utilized by Property Owner. Property Owner shall pay a
proportionate cost share based on the number of Truck Trip ESAL Counts using then current
data on the haul route in the implementation of the above-mentioned improvements. County
personnel alone shall make all determinations regarding the gathering of and use of traffic data
when making decisions regarding cost sharing. In order to accurately determine percentage of
Property Owner haul truck traffic, the County reserves the right to install traffic counters on the
driveway(s) of their facility.
8.0 Timing of Improvements: Subject to the provisions of Weld County Code Sec.
23-2-290 and any conditions or considerations granted by the Board of County Commissioners,
Property Owner shall not be required to complete the aforementioned offsite improvements as
described in Section A 1.0 until the occurrence of the triggering event for each improvement.
namely the application for the Grading Permit, Building Permit or Right-Of-Way access permit
or the commencement of activities on the property(s). At that time, Property Owner agrees that
the required collateral will be posted and all on-site and off-site improvements shall commence
and shall be completed within the parameters established in Section E.-7.2 and Exhibit B. herein.
9.0 Acceptance of Off-Site Improvements: Upon completion of the off-site
improvements, Property Owner shall contact a representative of the Weld County Department of
Public Works and request an inspection of the off-site improvements described in paragraph
A.1.0-2.0 above. The County's representatives may then initiate the acceptance process set forth
in Paragraphs E.6.0. sections 6.1-6.3.
9.1 All references in this Agreement to "Acceptance of Improvements' shall
refer to the County confirming completion of said improvement(s)
M.APLANNING-DFAGI,0MEN'r IiE VIE WVl1SR-Use by Special RavieA\1USR-1668 Valconessllmprovements Agreement AValcnnesi(U$R-
1668)Final IA (3-7-12).docy
3849077 Pages: 5 of 24
05/30/2012 08:09 RM R Fee:$0.00
Steve Moreno, Clerk and Recorder, Weld County, CO
VIII R�i IVIVIAA Wth ION Pi Bill
according to the accepted construction plans. By accepting any
improvement, the County does not thereby accept said improvement for
purposes of future maintenance, nor does the County accept any present or
future responsibilities or obligations relative to these improvements.
B. Haul Routes:
1.0 Established Haul Routes:
1.1 Exiting or entering the site: Haul trucks shall enter or exit the site at the
approved access onto CR 46, for further dispersal.
1.2 No haul truck may exceed CDOT required specifications for pounds per
axle.
1.3 In unusual or rare occasions, if particular projects mandate deviation from
the above-mentioned haul route for a limited period of time (which is
defined in this Agreement as a period of not more than thirty (30) days),
which shall be established by County at the time that the deviation is
allowed. If County approves such deviation, trucks will utilize paved
county roads whenever possible. A deviation from the established Haul
route lasting more than thirty (30) days or requests for two or more
deviations within a twelve month period shall be subject to the terms of
Paragraph 4.0 of this Section B. In the event that haul truck traffic, in
excess of 15% of the daily facility truck trips, utilizes alternate haul routes,
the provisions of Paragraph 4.0 of this Section B shall be triggered.
2.0 Haul Route Signage: (Not Applicable)
3.0 No Deviation from Permitted Haul Routes: No deviation in the use of any roads
other than those specifically authorized for use in this Agreement is permitted without the prior
written amendment of this Agreement.
4.0 Effect of Future Changes to Haul Routes: In the event that County is requested
by Property Owner or site operator to approve the use of an additional access, new haul route, or
an alternative haul route as a result of a change in Property Owner's site activities and/or truck
circulation patterns, and if the alternative or additional access or haul route utilizes any unpaved
portion of County roads, and if County determines that dust control or paving is required on the
unpaved portion of said haul route roads, Property Owner agrees that dust control or paving
measures to protect the public health, safety, and welfare shall be instituted. County will
determine the proportionate share of dust control and/or paving costs to be paid by Property
Owner based upon then current truck trip counts that identify traffic loading due to Property
Owner-sourced traffic. The amount and extent of dust control and/or paving measures will be
determined by site-specific conditions at the time, as determined exclusively by County
personnel.
C. Road Maintenance Requirements:
4
M:APLANNING-uLVELOPMENT REVIEWVUSR-Use IA Special RcviewVUSR-1668 ValconesslAImprovements Agreement\Valconesi(USR-
1668)Final IA (3-7-12).docx
3849077 Pages: 6 of 24
05/30/2012 08:09 AM R Fee:$0.00
Steve Moreno, Clerk and Recorder Weld County, COI 1`
1111Rt�iI IY�,Ih�I� IIhtCil I IC!itPhI Ilk
1.0 Obligation to Maintain Current and Future Haul Routes: Property Owner agrees
to excavate, repair, or patch any damage on current or future haul route roads, which in the sole
opinion of County has been created by truck hauling to and from the Property. Should Property
Owner's site activities and/or should Property Owner's truck circulation patterns change in the
future so that County approves an alternate haul route, and all or a significant portion of Property
Owner's sourced traffic no longer utilizes the above-described haul route and instead utilizes
other portions of County roads, Property Owner shall cooperate with County in maintenance of
said roads. The type and method of repair will be determined by the County Engineer or his
representative. All repairs shall commence within thirty (30) days of receipt of Weld County's
written notice.
2.0 Annual Road Inspection: County will conduct a road inspection annually with the
cooperation of Property Owner and all other Property Owners and/or Lessees who are required
by County to participate in road improvement/maintenance agreements. As a result of the annual
inspection. County, in its sole discretion, shall determine actual conditions and shall further
determine what road improvement/maintenance work is to be performed during that construction
season.
3.0 Future Road Replacement: At any time in the future, if, in the opinion of County,
road damage increases beyond the point that repair of damage cannot maintain the road in a safe
and usable condition, Property Owner shall pay a proportionate cost of a complete restoration
based on the number of Truck Trip ESAL Counts using then current data of truck trips entering
or exiting Property Owners' site onto the haul route in the implementation of the above-
mentioned improvements.
4.0 Sharing of Road Maintenance Responsibilities with Other Property Owners: It is
anticipated that Property Owner and other Property Owners and/or Lessees subject to agreements
similar to this Agreement will perform the required road maintenance work and will share in the
equipment, labor, and materials required. Any such sharing arrangement between Property
Owner, and other Property Owners and/or Lessees shall be conducted pursuant to separate
agreements between the Property Owner and other Property Owners and/or Lessees. County
shall approve the Agreements only to determine whether the required
improvements/maintenance projects have been adequately addressed. County alone shall
determine the sufficiency of all road improvement/maintenance projects when completed.
5.0 Violation of Terms of Agreement: If Property Owner does not perform as
outlined in this Agreement and Exhibits A and B such non-performance will constitute a
violation of Property Owner's land use permits granted by County, and County will take
whatever remedial measures it deems necessary, against Property Owner. In addition to any
other remedy available to the County in law or equity, a failure to comply with this Agreement
shall be considered grounds for setting a probable cause hearing according to the procedures
described in Section 2-4-40 of Weld County Code. Revocation of USR-1668 as it now exists or
may, from time to time, be amended is a remedy which County may impose.
D. On-Site Improvements:
s
M'.API.ANNIN(i—DF.VFI ORMEN'I REVIONA SR-Use by Special RCN lokAUSR-1668 Valconessiamprovements AgreementAValcon i(USR-
1668)Final IA (3-7-I2)dncs
3849077 Pages: 7 of 24
05/30/2012 08:09 AM R Fee:$0.00
Steve Moreno. Clerk and Recorder. Weld County, CO
����h'i �IlfMl�l�h 'lititi #r 4XhMiGIIG��I�'�.li�fd Ni't 11111
1.0 Landscaping and Fencing Requirements: Property Owner shall landscape and/or
maintain the landscaping and re-seeding of the property where applicable as shown on the
accepted Construction Plans and USR-1668 plat map. Specifically, Property Owner shall at its
own expense, plant, install and/or maintain all grass and other landscaping and re-seeding where
applicable as shown on the accepted Construction Plans and USR-1668 plat map. Additionally,
the Property Owner shall install and/or maintain fencing to screen the property where applicable
as indicated on the accepted Construction Plans and USR-1668 plat map. In the event any of
these improvements may include work extending into State or County Right-Of-Way in which
case a Right-Of-Way or access permit is required.
2.0 On-Site Grading, Drainage Facilities and Paving: Property Owner shall, at its
sole expense, grade and/or pave, if applicable, specified roadways, accesses, easements and
parking areas, and install accepted drainage and signage components, adjacent to or within the
interior portion of the property in accordance with the directives of the Weld County Department
of Public Works and Department of Planning Services, as further described in the accepted
Construction Plans and USR-1668 Plat Map. The main entrance improvements will include;
construction of adequate turning radii at the main site entrance onto CR 46, an appropriately
sized drainage culvert, and a double cattle guard set (one right after the other) across the entire
width of the roadway, to ensure a complete revolution of the truck tires to minimize the tracking
of mud and debris onto CR 46. Any other on-site improvements shall be completed as indicated
on the accepted Construction Plans for this facility. Property Owner shall be responsible for all
maintenance of the on-site improvements. Additional infrastructure improvements will be
addressed at the time of application for any future amended USR. Some of these improvements
may include work extending into County Right-Of-Way in which case a Right-Of-Way or access
permit is required.
3.0 Timing of Improvements: Subject to the provisions of Weld County Code Sec.
23-2-290 and any conditions or considerations granted by the Board of County Commissioners,
Property Owner shall not be required to initiate the landscaping requirements until the
occurrence of the triggering event for all improvements, namely the approval of the grading
permit or an amendment to the existing USR. No grading permit will be released until collateral
is posted for all on-site and off-site improvements and the final Construction Plans have been
submitted to and accepted by the Department of Public Works. Access and/or Right-Of-Way
permits might also be required prior to approval of the grading permit. Grading shall not
commence until Construction Plans are accepted. Any alterations to the accepted Construction
Plans must be accepted in writing by the County Planning and Public Works Departments. At
that time, and unless otherwise amended, Property Owner agrees that all landscaping and other
on-site improvements, as indicated in Section D. 2.0 above shall be completed within the
parameters established in Section E. 7.2 and Exhibit B.
4.0 Acceptance of On-Site Improvements: Upon completion of the on-site
improvements, Property Owner shall contact the Weld County Department of Planning Services
and the Weld County Department of Public Works and request an inspection of the on-site
improvements described in Paragraph D.1.0 and D.2.0 above. The County's representatives may
then initiate the process for "Acceptance of Improvements" set forth in Paragraphs E.6.0,
sections 6.1-6.3.
6
M VPLANNING—DEVELOPMENT REVIENnUSR-Useha Special ReviewVIISR-1668 ValconessiAlmpmvements AgreementAValumesi fUSR-
1668)Final IA (3-7-12).doey
3849077 Pages: 8 of 24
05/30/2012 08:09 AM R Fee:$0.00
Steve Moreno. Clerk and Recorder, Weld County, CO
tIII�Y'i IIINVAPINIfi'l lWtiilortai II III
E. General Requirements:
1.0 Engineering Services: Property Owner shall furnish, at its own expense, all
engineering services in connection with the design and construction of the improvements
identified on the accepted Construction Plans according to the construction schedule set forth in
Exhibit"B," both of which are attached hereto and incorporated herein by reference.
1.1 The required engineering services shall be performed by a Professional
Engineer and Land Surveyor registered in the State of Colorado, and shall
conform to the standards and criteria established by the County for public
improvements.
1.2 The required engineering services shall consist of, but not be limited to,
surveys, designs, plans and profiles, estimates, construction supervision.
and the submission of necessary documents to the County.
1.3 Property Owner shall furnish construction drawings for the road
improvements on public rights-of-way or easements and all improvements
interior on the Property for approval prior to the letting of any construction
contract.
2.0 Rights-of-way and Easements: Before commencing the construction of any
improvements herein agreed upon for public rights-of-way or easements, Property Owner shall
acquire, at the sole expense of Property Owner, good and sufficient rights-of-way and easements
on all lands and facilities traversed by the proposed improvements. All such rights-of-way and
easements used for the construction of roads to be accepted by the County shall be conveyed to
the County and the documents of conveyance shall be furnished to the County for recording.
3.0 Construction: Property Owner shall furnish and install, at its own expense, the
improvements identified on the accepted Construction Plans and USR-1668 Plat Map. be solely
responsible for the costs listed on Exhibit `A", and described in parts A and D of this agreement.
which are attached hereto and/or incorporated herein by reference, with the improvements
interior to the Property being completed by the dates set forth on Exhibit 'B" (On-site), and
improvements to public rights-of-way or easements being completed also in accordance with the
schedule set forth in Exhibit "B" (Off-site). The Board of County Commissioners. at its option,
may grant an extension of the time of completion set forth in Exhibit B stated herein upon
application by the Property Owner.
3.1 Said construction shall be in strict conformance to the plans and drawings
accepted by the County and the specifications adopted by the County.
3.2 Property Owner shall employ, at its own expense, a qualified testing
company previously approved by the County to perform all testing of
materials or construction; and shall furnish copies of test results to the
County. If County discovers inconsistencies in the testing results, Property
Owner shall employ at its expense a third party qualified testing company
7
NI'PI DEVELOPMCN I RI VIMAISR-Use by Special RevIeRAUSR-1668 Valconesselmprovements AgreementWalconesi al SR-
1668)Final IA (3-7-12)doe'
3849077 Pages: 9 of 24
05/30/2012 08:09 AM R Fee:$0.00
Steve Moreno, Clerk and Recorder. Weld County, CO
liii�l Ilrl, rM�,i�rla�,li �a�r
approved by County. Such third party shall furnish the certified results of
all such testing to the County.
3.3 At all times during said construction, the County shall have the right to
test and inspect, or to require testing and inspection of material and work,
at Property Owner's expense. Any material or work not conforming to the
approved plans and specifications, including but not limited to damages to
property adjacent to the construction plan area shall be repaired, removed
or replaced to the satisfaction of the County at the expense of Property
Owner.
4.0 Release of Liability: Property Owner shall indemnify and hold harmless the
County from any and all liability loss and damage County may suffer as a result of all suits,
actions or claims of every nature and description caused by, arising from, or on account of said
design and construction of improvements, and pay any and all judgments rendered against the
County on account of any such suit, action or claim, together with all reasonable expenses and
attorney fees incurred by County in defending such suit, action or claim whether the liability,
loss or damage is caused by, or arises out of the negligence of the County or its officers, agents,
employees, or otherwise except for the liability, loss, or damage arising from the intentional torts
or the gross negligence of the County or its employees while acting within the scope of their
employment. All contractors and other employees engaged in construction of the improvements
shall maintain adequate worker's compensation insurance and public liability insurance coverage,
and shall operate in strict accordance with the applicable laws and regulations of the State of
Colorado governing occupational safety and health.
5.0 Warranty of On-Site and Off-Site Improvements: Property Owner shall warranty
all improvements to public rights-of-way, (if any), and all privately created and maintained roads
or rights-of-way, or easements, and all on-site improvements for a period of two (2) years. The
warranty period shall begin only after the County's execution of a written acceptance of the
i m provement(s).
6.0 Acceptance of On-Site and/or Off-Site Improvements by the County: Upon
compliance with the following procedures by the Property Owner, the improvements shall be
deemed accepted by the County.
6.1 If requested by the Property Owner and approved by the County, portions
of the improvements may be placed in service when completed according
to the schedule shown on Exhibit "B," but such use and operation shall
not, alone, constitute an acceptance of said portions of the improvements.
6.2 County may, at its option, issue building permits for construction for
which the improvements detailed herein have been started but not
completed according to the schedule shown on Exhibit `B." and may
continue to issue building permits so long as the progress of work on the
USR improvements in that phase of the USR is satisfactory to the County,
and all terms of this Agreement have been faithfully kept by Applicant.
8
M'.APLANNING DEVELOPMENT REVIFWVUSR-Use 6y Special Rat iew\USR-1668 ValconessiAlmprovcments AgreementAvalconesi(USR-
1668)Final IA (3-7-12)dock
3849077 Pages: 10 of 24
05/30/2012 08:09 AM R Fee:$0.00
Steve Moreno. Clerk and Recorder, Weld County: CO
lIll h'f IV I l'Il4'NRrt!lei 11111
6.3a Upon completion of the construction of the required off-site
improvements, and the filing of a Statement of Substantial Compliance by
Property Owner's engineer, the Property Owner may, as set forth in
Paragraph A.9.0, request in writing that the County inspect the
improvements and recommend to the Board of County Commissioners
that the improvements be accepted and further that the two-year warranty
period begin. Upon completion of the two-year warranty period, the
County Engineer shall, upon request by the applicant, inspect the subject
improvements, and notify the Property Owner of any deficiencies. If any
deficiencies are discovered, the Property Owner shall correct the
deficiencies. The County Engineer shall reinspect the improvements after
notification from the Property Owner that said deficiencies have been
corrected. If the County Engineer finds that the improvements are
constructed according to County standards, he or she shall recommend full
acceptance. Upon a receipt of a positive unqualified written
recommendation from the County Engineer for acceptance of
improvements within the USR, the Board of County Commissioners shall
fully accept said improvements.
6.3b Upon completion of the construction of the required on-site
improvements, and the filing of a Statement of Substantial Compliance,
when necessary, by Property Owner's engineer, the Property Owner may,
as set forth in Paragraph D.4.0, request in writing that the County inspect
the improvements and recommend to the Board of County Commissioners
that the improvements be accepted and further that the two-year warranty
period begin. Upon completion of the two-year warranty period, the
County Engineer and/or the Weld County Department of Planning
Services shall, upon request of the Property Owner, inspect the subject
improvements, and notify the Property Owner of any deficiencies. If any
deficiencies are discovered, the Property Owner shall correct the
deficiencies. The County Engineer and /or the Department of Planning
Services shall reinspect the improvements after notification from the
Property Owner that said deficiencies have been corrected. If the County
Engineer and/or Department of Planning Services find that the
improvements are constructed according to County standards, he or she
shall recommend full acceptance. Upon a receipt of a positive unqualified
written recommendation from the County Engineer and/or the Department
of Planning Services for acceptance of improvements within the USR, the
Board of County Commissioners shall fully accept said improvements.
7.0 General Requirements for Collateral:
7.1 County requires Property Owner to provide collateral to guaranty all of
Property Owner's obligations under this Agreement: (I) Project Collateral
for completion of all improvements described in this Agreement shall be
provided separately for on-site improvements and off-site improvements;
(2) Warranty Collateral required for all improvements during the warranty
9
M VPLANNING-DEVELOPMENT REV'LW VUSR-Use he Spatial ReviewVUSR-1668 VaIeoncssiAImpmccmcnts AgnxmentAValconesi(USR-
1665)Final IA (3-7-I2).docy
3849077 Pages: 11 of 24
05/30/2012 08:09 AM R Fee:$0.00
Steve Moreno, Clerk and Recorder, Weld County, CO
X114?1.HI'+1 Bill
phase; and (3) Road Maintenance Collateral (If Applicable) to be kept in
place for the life of the permit.
7.2 Project Collateral submitted to Weld County to guarantee completion of
the improvements indentified on the accepted Construction Plans and
USR-1668 Plat Map and further enumerated in the costs listed in Exhibit
"A," must he equivalent to One-Hundred Percent (100%) of the value of
the improvements as shown in this Agreement. Collateral for Off- site
improvements that extend partially off-site as mentioned in Section A., 1.0
(if any) or D.2.0 of this Agreement that include only improvements
involving turning radii and approaches can be included as part of the On-
site collateral amount, if clearly delineated on accepted Construction Plans
and differentiated as "Entrance Improvements" on Exhibit "A" On-Site
Improvements of this Agreement. This collateral must be submitted to
County upon the submission of the Property Owner's application of a
grading, building, and/or right-of way permit, and shall be held in total by
County as provided in Paragraph E. 7.3 below until all improvements have
been completed.
7.3 Warranty Collateral for all on-site and off-site improvements shall be
submitted to County and shall be held in total by the County for two (2)
years following its written acceptance of the improvement(s).
7.4 In the event Property Owner fails to adequately complete and/or repair
improvements associated with this Improvements Agreement. County will
access, in its sole discretion, Project or Warranty Collateral to the extent
necessary to complete said improvements or repairs in order to preserve
public interest.
7.5 Road Maintenance Collateral shall be submitted to County upon the
release of the warranty collateral by the Board of County Commissioners.
Road Maintenance Collateral is held for use on roads associated with the
designated haul route. The amount of the collateral required for road
maintenance shall be one percent(%) of the initial Project Collateral listed
on Exhibit "A"—Cost Sheet (OFF-SITE) of this agreement. If no Off-Site
Collateral is submitted, the amount of Road Maintenance Collateral shall
be one percent (%) of the initial Project Collateral listed on Exhibit "A"-
Cost Sheet (ON-SITE).Road Maintenance Collateral shall be held by
County as long as this Agreement is in effect and returned to the Property
Owner upon vacation of associated land use agreement or permit. The
Road Maintenance Collateral will only be accessed by the County, if upon
notification to Property Owner of required roadway safety related repairs:
Property Owner fails to perform said repairs. If any of this collateral shall
be collected by County. Property Owner shall replace the amount, plus
interest, within six (6) months.
7.5.1 Road Maintenance Collateral Option (For Materials Haulers):
M'.APL ANN ING—UEVELOPMIiNI'RHVIEWVL15R-Use he special Ito Ink VUSR-166R ValconessiAImprovanen(s Agreement AVelconcsi(US R-
1668)Final IA (3-7-12).docx
3849077 Pages: 12 of 24
05/30/2012 08:09 A11 R Fee:$0.00
Steve Moreno. Clerk and Recorder, Weld County. CO
gillFY' PAIIIrIIIVINUMSi,NIL N ,0111?lit 11111
In lieu of cash collateral, with its obligated yearly inflationary cost
adjustments, Property Owner may submit funds quarterly to Weld
County, at a rate of ten (10) cents per ton, based on the amount of
processed material leaving the site. These funds will be escrowed
by the County and utilized for roadway repairs specific to the
USR's designated haul route. The first payment of funds will be
due three months after the initial sale of materials from the USR
site. Subsequent quarterly payments will be deposited in the
associated escrow account until the USR permit is terminated.
Utilization of this collateral option will negate any further
obligations of the Property Owner and/or Applicant to participate
in any future maintenance and/or improvements projects for the
associated Haul Route. Upon vacation of the USR for this facility
and following determination by Public Works staff that no
immediate repairs are required for the Haul Route, any remaining
funds in the escrow account will be returned to the USR Permitee.
7.5.2 Road Maintenance Collateral (For Off-Site Dust Control) If
Applicable:
The total costs for materials and application, will be listed on
Exhibit "A" (OFF-SITE) — Dust Control, of this agreement. These
funds will be utilized by the County for roadway applications
specific to the USR's designated haul route, only if the applicant
does not adhere to the requirements for dust suppression as
specified in Section A.6.0 of this agreement. Following completion
of all construction phases, and/or upon vacation of this USR, and
following determination by Public Works staff that no immediate
repairs are required for the Haul Route, any remaining Dust
Control collateral will be returned to the USR Permittee.
7.6 Acceptable Project Collateral shall be submitted when the Property Owner
submits an application for the Grading Permit, Building Permit, or Right-
of-Way Access Permit prior to commencement of Site Preparation, as
herein defined.
7.6.1 No grading or building permits shall be issued for any site related
activities, on the property and no Site Preparation shall commence
until cost estimates for all improvements are updated and collateral
is provided in the amount of One-Hundred percent (100%) of the
then current value of the improvements to be completed, and the
development plans are revised to comply with all current County
standards, policies and regulations. The improvements shall be
completed within the time schedule set forth in Exhibit "B", which
is attached hereto and made a part of this Agreement. "Site
Preparation" shall mean earthwork grading or performance of
work, or construction or installation of improvements related to
Applicant's operations pursuant to USR-1668 that require a
M'.API ANN ING—DEVr:L0PMIfKT RI_VICWVUSR-Use be Special RevicwVUSR-1668 VnlconcssiAhnpmvements Agreement AValeonesi(USR-
1668)Final IA (3-7-12).doc.
3849077 Pages: 13 of 24
05 08:09 Pant
R Fee:$000
Steve/30/2012 Moreno, Clerk and Recorder, Weld County, CO
liii kt�PY}IPI�I'I�lti I�IELI+Grl +,f+ X11,«+11N1+1 lI iii
grading or building permit from the County pursuant to the Weld
County Code. In the event that the Improvements outlined in this
Agreement and Exhibit A are not completed within one year of the
execution of this Agreement Weld County may require Property
Owner to obtain current cost figures for one or more of the
Improvements.
7.7 Collateral may be in the form of an irrevocable letter of credit (LOC) in
an amount equivalent to (100%) of the total value of the improvements set
forth in the Improvements Agreement and the Plat; the LOC shall be
subject to the requirements of Weld County Code Section 2-3-30 B. The
Property Owner shall utilize only a County approved form when obtaining
an LOC: (IRRVEVOCABLE STANDBY LETTER OF CREDIT FOR
BOARD OF COUNTY COMMISSIONERS OF WELD COUNTY,
COLORADO). A copy of said form shall be provided to Applicant upon
request.
7.8 Collateral may be in the form of a surety bond given by a corporate surety
authorized to do business in the State of Colorado in an amount equivalent
to one hundred percent (100%) of the value of the improvements set forth
in the Improvements Agreement and the Plat. The surety bond shall
conform to and be subject to the requirements of Weld County Code
Section 2-3-30 B.4. The Property Owner shall utilize only a County
approved form when obtaining a surety bond: (PERFORMANCE BOND
FOR BOARD OF COUNTY COMMISSIONERS OF WELD COUNTY,
COLORADO). A copy of said form shall be provided to Applicant upon
request.
7.9 Collateral may be in the form of a cash deposit made with the Board in an
amount equivalent to One Hundred Percent (100%) of the value of the
improvements set forth in the Improvements Agreement. In the event the
applicant is required to warranty the improvements, the applicant shall
replace the original deposit with a deposit in the amount of fifteen percent
(15%) of the original amount and those funds shall remain available to the
County until released by the County at the end of the warranty period.
7.10 The Board of County Commissioners reserves the right to reject collateral
which is deemed inappropriate or insufficient, which may be either as
collateral in the form of a letter of credit offered by a banking institution
which does not have at least a"three star" rating given by Bauer Financial,
or as collateral in the form of a performance bond offered by an insurance
company which does not have at least a B+ rating given by A.M. Best.
The Board further reserves the right to require Property Owner to obtain
replacement collateral if the rating of the financial institution providing
said collateral drops below the levels stated above. Replacement collateral
shall be submitted by Property Owner within sixty (60) days of the
Board's notice to Property Owner that the rating has fallen and that the
12
M.APLANNING-DEVELOPMENT REVIEWVUSR-Use by Special RevioN USR-1668 ValconessiAlmprovements AgreementAValconesi(USR-
1668)Final IA (3-7-12)_doev 3849077 Pages: 14 of 24
0 : Re e: .00
Steve05/30/2 Moreno12 08 Cler09k anMd RecorRFder$0, Weld County, CO
����h11iPY}IPIrI�«h��? '' AM ME Pkii.:I0.1001I O!
collateral must be replaced. Property Owner may not terminate existing
collateral until replacement collateral has been secured.
8.0 Request for Release of Collateral: Collateral shall be released in accordance with
the provisions of Weld County Code Section 2-3-30.C. Prior to release of collateral for the entire
project or for a portion of the project by Weld County, the Property Owner must present a
Statement of Substantial Compliance from an Engineer registered in the State of Colorado. The
Statement of Substantial Compliance shall state that the project or a portion of the project has
been completed in substantial compliance with accepted plans and specifications documenting
the following:
8.1 The Property Owner's Engineer or his representative has made regular
on-site inspections during the course of construction and the construction
plans utilized are the same as those accepted by Weld County.
8.2 For the improvements to public rights-of-way or easements, test results
must be submitted for all phases of this project as per Colorado
Department of Transportation (CDOT) Schedule for minimum materials
sampling, testing and inspections found in CDOT Materials Manual.
8.3 "As-built" plans shall be submitted at the time the letter requesting release
of collateral is submitted. The Property Owner's Engineer shall certify
that the project "as-built' is in substantial compliance with the plans and
specifications as approved, or that any material deviations have received
prior written acceptance from the County Engineer.
8.4 The Statements of Substantial Compliance must be accompanied, if
appropriate, by a letter of acceptance of maintenance and responsibility by
the appropriate utility company, special district or town for any utilities.
8.5 A letter must be submitted from the appropriate Fire Authority, if
applicable, indicating the lire hydrants are in place in accordance with the
approved plans. The letter shall indicate if the fire hydrants are operational
and state the results of fire flow tests.
8.6 The requirements in the paragraphs 8.0 through 8.5 shall be noted in the
final Construction Plans.
8.7 Following the submittal of the Statement of Substantial Compliance and
written recommendation of acceptance of the improvements by the Weld
County Department of Planning Services and the Weld County
Department of Public Works, the Property Owner (if Property Owner has
supplied any or all of the collateral) may request release of the collateral
for the project or portion of the project by the Board. This action will be
taken at a regularly scheduled public meeting of the Board.
3
M PLANNING -DP.VLI.OPMLNI REVILVOUSR-Use by Special Rex.WAN Valconessi)Improvements Amement`Vnlconesi(USR-
1668)Final IA (3-7-12).doc%
3849077 Pages: 15 of 24
05/30/2012 08.09 RM R Fee:$0.00
Steve Moreno, Clerk and Recorder, Weld County CO
&FWUN U 144tl4 .l'd "Ill
8.8 Following the written request for partial release of the "Project
Collateral", the Weld County Department of Planning Services and the
Weld County Department of Public Works County shall inspect the on-site
and/or off-site improvements. If the improvements require mitigation or
further repairs are required. said work must be completed prior to the
partial release of "Project Collateral". For all otT-site and on-site
improvements (including improvements to public rights-of-way or
easements), the written request for release of"Project Collateral" shall be
accompanied by "Warranty Collateral" in the amount of fifteen percent
(15%) of the value of the improvements as shown in this Agreement.
However, collateral for improvements fully accepted for maintenance by a
responsible governmental entity, special district or utility company will be
fully refunded to Property Owner.
8.9 Following the written request for release of the `Warranty Collateral", the
Weld County Department of Planning Services and the Weld County
Department of Public Works County shall inspect the on-site and/or off-
site improvements. If the improvements require mitigation or further
repairs are required, said work must be completed prior to the conclusion
of the Warranty period. The "Warranty Collateral" shall be released to the
Property Owner following the expiration of the warranty period upon final
written acceptance by the Board of County Commissioners.
8.10 For all off-site and on-site improvements (including improvements to
public rights-of-way or easements), the written request for release of
"Warranty Collateral" shall be accompanied by "Road Maintenance
Collateral" (If Applicable) as specified in Section E.7.5 of this Agreement.
"Road Maintenance Collateral" for roads associated with the designated
haul route shall be maintained as long as the USR is active.
9.0 Successors and Assigns: This Agreement may not be delegated, transferred or
assigned in whole or in part by Property Owner without the express written consent of County
and the written agreement of the party to whom the obligations under this Agreement are
assigned. Consent to a delegation or an assignment will not be unreasonably withheld by County.
In the event of sale of the Property, County may agree to release Property Owner in whole or in
part from obligations under this Agreement. County's rights and obligations under this
Agreement shall automatically be delegated, transferred or assigned to any municipality which,
by and through annexation proceedings, has assumed jurisdiction and maintenance responsibility
over the roads affected by this Agreement. All of the terms and conditions set forth in this
Agreement shall be binding upon the heirs, executors, personal representatives, successors and
assigns of Property Owner, and upon recording by the County. shall be deemed a covenant
running with the land herein described.
10.0 County Engineer: All references in this Agreement to "County Engineer' shall
refer to the any individual or individuals appointed by the County Engineer to act on his/her
behalf.
14
M'.AI'LANN INC-DEVELOPM EN'r RFVIFWVtISR-Use In Special Rex.lev4AUSR-1668 ValconcssiAImprovements AgreementAValconcsi(USR-
1668)Final IA (3-7-12).docv
3849077 Pages: 16 of 24
05/30/2012 08:09 AM R Fee:$0.00
Steve Moreno, Clerk and Recorder.. Weld County, CO
tr'IW�WWW M WI 1 "Ill
11.0 Violation of Terms of Agreement: If in County's opinion, Property Owner has
violated any of the terms of this Agreement, County shall notify Property Owner of its belief that
the Agreement has been violated and shall state with specificity the facts and circumstances
which County believes constitute the violation. Property Owner shall have fifteen (15) days
within which to either cure the violation or demonstrate compliance. If. after fifteen (15) days
have elapsed. County believes in good faith that there has been a violation of the terms of this
Agreement, County shall initiate proceedings to revoke the permit which is the subject matter of
this Agreement. Violations of the terms of this Agreement include violations of the agreements
contemplated by Paragraphs C. 4.0 & C. 5.0 of this Agreement, and a failure to enter into such
Agreements in a timely manner.
F. Termination of Agreement:
1.0 Termination Event: This Agreement shall terminate upon the earliest of the
following events:
1.1 Cessation of all Permit Related Activities. Termination of this Agreement
shall occur upon Operator's complete cessation of all activities permitted under USR-
1668 or any amendments thereto. A partial cessation of activities shall not constitute a
Termination of this Agreement, nor shall County's issuance of a partial release constitute
a Termination. Operator shall provide written notice to Property Owner and County of
said cessation of activity, which County shall then verify. If written notice is not provided
to County. Termination of this Agreement shall not occur until County has determined
that the Use by Special Review is inactive, which shall be three (3) years following
County's observance of the cessation of activities, as provided in Sec. 23-2-200.E of the
Weld County Code.
1.2 Execution of Replacement "Improvements Agreement According to
Policy Regarding Collateral for Improvements — USR-1668 by New Property Owner:
This Agreement shall terminate following County's execution of a new Improvements
Agreement According to Policy Regarding Collateral for Improvements — USR-1668
with a new Property Owner who has purchased the Property, and intends to make use of
the rights and privileges available to it through the then existing USR.
1.3 Execution of Replacement "Improvements Agreement According to
Policy Regarding Collateral for Improvements — USR-1668 by New Operator: This
Agreement shall terminate following County's execution of a new Improvements
Agreement According to Policy Regarding Collateral for Improvements — USR-1668
with a new operator who has assumed the operation of the business on the Property
which business activities are permitted by the then existing USR.
2.0 Termination Procedures.
2.1 Termination Procedures Following Cessation of Permit Related Activities:
Following the events outlined in paragraph 1.1 above, County shall conduct its annual
road inspection. Said road inspection shall be conducted on or before May 31 following
the announcement or determination of the cessation of permit related activities on the
15
M.APLANNING—DEVELOPMENT RI VIEWby Special ReviovVUSR-1668 Vulcon ssiAImprovements AgreementAValconesi(USR-
1668)Final IA (3-7-12).docx
3849077 Pages: 17 of 24
05/30/2ve 012 08:09 and Re Fede$0 kl00d County, Co
N1}INILI '�:«I��"k tin
Property. The results of the inspection shall be delivered in writing to the Property Owner
and Operator. If the County determines that pursuant to the terms of this Agreement, the
Operator must complete any of the improvements and/or road maintenance obligations
outlined herein, said obligations must be completed within a reasonable period of time
thereafter, but in no event later than six (6) months following the determination that
permit related activities have ceased. Collateral shall not be released by County until such
time as county determines that all of the improvements have been completed.
2.2 Termination Procedures Pursuant to Transfer of Ownership of the
Property or Transfer of Operations: If the Property Owner or Operator desires to assign
its rights and obligations under this Agreement to a successor Property Owner or
Operator, the Property Owner or Operator shall, prior to the transfer, provide County with
a written Notice to Transfer, stating the date of transfer, and identifying the party to
whom the transfer shall be made. Following receipt of the Noticc to Transfer, County
shall inspect the improvements required under the terms of this Agreement to determine
whether the improvements have been completed. If the improvements have not been
completed. the Property Owner and/or Operator shall either complete the improvements
or post collateral equal to the cost of the completion of the improvements, if such
collateral is not in place. If collateral is available at the time, County shall hold a hearing
to determine whether the collateral should be called upon to pay County or a contractor
of the County to complete the improvements. County shall also inspect the road(s) which
are covered by this Agreement to assess the current condition of the road(s) and
determine whether Operator and/or Property Owner would be required to perform road
maintenance within the following twelve months had the Agreement not been assigned. If
road maintenance is. in the opinion of County, required, Property Owner and/or Operator
shall be required to either perform the road maintenance or to post collateral equal to the
cost of said maintenance. County shall not execute a new Improvements Agreement
According to Policy Regarding Collateral for Improvements — USR-1668 with a
successor Property Owner and/or Operator prior to the performance of the road
maintenance or the posting of collateral for said maintenance, unless the new Property
Owner and/or Operator posts collateral for the required maintenance.
3.0 Consequence of Termination by Cessation of Permit Related Activities:
Following County's confirmation that Property Owner and/or Operator has/have ceased all
permit related activities and has/have completed previously uncompleted Improvements and or
completed any required road maintenance. County shall release Property Owner and/or Operator
from all further obligations under this Agreement. No Further permit related activities shall be
permitted unless and until approved by County following execution of a new Improvements
Agreement According to Policy Regarding Collateral for Improvements — USR-1668 with a
Property Owner and Operator.
4.0 Consequence of Termination by Execution of Replacement Improvements
Agreement: Following County's execution of an Improvements Agreement According to
Policy Regarding Collateral for Improvements — USR-1668 with a successor Property Owner
and/or Operator, the predecessor Property Owner and/or Operator shall have no further rights
and/or obligations under this Agreement or in USR-1668.
la
M'\PI AN INU—DEVELOPMENT REVIEW by Special Re‘.iewVU SR-1665 ValconcssiAl npmvements Agreementwalconesi(USR-
1668)Final IA (3-7-12).doey
3849077 Pages: 18
08:09 RM R
05/30/2012 Fee:$0.00
Steve Moreno Clerk and Recorder, Weld County, CO
■iiikl�111006I, I r�u, 11.KI iea44Bill
5.0 Consequence of Termination Pursuant to Paragraph E.11.0: In the event that
activities related to USR-1668 cease as a result of the revocation of the permit as described in
Paragraph E.I 1.0 of this Agreement, neither Property Owner nor Operator will be released from
any of the obligations imposed by the terms of this Agreement only after Property Owner's
successful completion of all improvements required under this Agreement or after County
accesses the collateral to the extent necessary to complete improvements County, in its sole
discretion, deems necessary to preserve public interests.
G. Governmental Immunity: No term or condition of this agreement shall be construed or
interpreted as a waiver, express or implied, of any of the immunities, rights, benefits, protections
or other provisions, of the Colorado Governmental Immunity Act §§24-10-101 et seq., as
applicable now or hereafter amended.
H. Enforcement: If, in the County's opinion, Property Owner has violated any of the terms
of this Agreement, County shall notify property Owner of its belief that the Agreement has been
violated and shall state with specificity the facts and circumstances which the County believes
constitute violation. Property Owner shall have thirty (30) days within which to either cure the
violation or demonstrate compliance. If, after thirty (30) days have elapsed, County believes in
good faith that a violation of the terms and conditions of this Agreement still exists (despite
cure), County may enforce by any legal means, including, but not limited to, legal action for
equitable or monetary relief filed in the Weld District Court, execution upon submitted collateral
(if applicable), and/or administrative action of the County to suspend or revoke the underlying
land use permit or approval pursuant to the procedural provisions of Section 2-4-40 of the Weld
County Code. Violations of the terms and conditions of this Agreement include, but are not
limited to. violations of the agreements Property Owner must enter into as required by this
Agreement, and/or failure to enter into such agreements in a timely manner.
1. No Third Party Beneficiary Enforcement: It is expressly understood and agreed that the
enforcement of the terms and conditions of this Agreement, and all rights of action relating to
such enforcement, shall be strictly reserved to the undersigned parties, and nothing contained in
this Agreement shall give or allow any claim or right of action whatsoever by any other person
or entity not included in this Agreement. It is the express intention of the undersigned parties that
any person or entity, other than the undersigned parties, receiving services or benefits under this
Agreement shall be an incidental beneficiary only.
J. Authority to Sign: Each person signing this Agreement, and associated Exhibits,
represents and warrants that he or she is duly authorized and has legal capacity to execute and
deliver this Agreement. Each party represents and warrants to the other that the execution and
delivery of the Agreement and the performance of such party's obligations hereunder have been
duly authorized and that the Agreement is a valid and legal agreement binding on such party and
enforceable in accordance with its terms. If requested by the County, Property Owner shall
provide the County with proof of Property Owner's authority to enter into this Agreement within
five (5) days of receiving such request.
I7
M_APLANNING-DLVLLOI'MCNI RPVILWVUSR-Use b)Special RCN iavAIJSR-1668 valconessiAImprovements AgreementAValconesi(USR-
1668)Filial IA (3-7-12)docx
3849077 Pages: 19 of 24
05/30/2012 08.09
CCleer9k antd Recorrder$0 Weld County, CO
����Ii iPJ'hPu'I t hFNRLIFIY,N41 11111
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed
on the day and year first above written.
PROPERTY
OWNER:
SIGNATURE _44 6/1.4"---
PRINTED PRINTED NAME e--2,!e•/ U (ce-.0<s,r
TITLE (If Other Than Property Owner)
STATE OF COLORADO
ss.
County of Weld
SXLI T fo p meet was acknowledged before me this day of
-2444-1, by
•
My commiysiop
AItr
30
or...coco BOARD OF COUNTY COMMISSIONERS
My Commission Expires WELD COUNTY,COLORADO
JULY 6,2014
ATTEST:
Sean
Conway, Chair
APR 3 01u12
ty Clerk to the Board
teat
(ti
e to the Board
aJr
APPROVED AS TO FORM:
`ounty Attorney
18
M:APLANNING—DEVELOPMENT REVIEWVUSR-Use by Special Rev iets1USK-1668 ValcnnessiAImprovements Agreement AValconesi(USR-
1668)Final IA (3-7-I2).docv
3849077 Pages: 20 of 24
05/30/2012 08:09 AM R Fee:$0.00
Steve Moreno, Clerk and Recorder. Weld County, CO �6/ 1/_ //
079
1111 iPY?IPIiilU44'19f'CWIAL Wt +'�I�IgIn IH"111111 rX
EXHIBIT A - Cost Sheet (ON-SITE) G`6/
Name of Subdivision, PIT),,USR,RE,S Filing/Case p: /6 Location:r.JOItk bdoN w
Personnel Contact: Name ettc U ..ICwfi.' Title Ow /-t'« Phone 970 -J 7o-79r
Intending to be legally bound,the undersi•ned Applicant hereby agrees to provide throughout this facility the following improvements.
Improvements (ON-SITE)
(Leave spaces blank where they do not apply)
Quantity Units l nit Costs(S) Estimated Construction
Cost isi
Site Grading /0 jot) SO Ft_ 2, typo.ao _
Street Grading
Street Base
Street Paving
Entrance Improvements(Per Sec. E.-7.2) i Z-OO Sacs 31 �W • C30 -
Curbs,Gutters,and Culverts
Sidewalk / SC) L I cc) .OO
Stormwater/Drainage Facilities
Retention/Detention Ponds 7 S oc Sc Z G CX1.cc _
Road Culvert
Grass Lined Swale
Ditch Improvements
Subsurface Drainage
Sanitary Sewers/Sewage Facilities
Water Supply
Erosion Control Measures/BMP's
Fire Hydrants
Survey,Street Monuments/Boxes
Parking Area / 5000 3OFF
3 Loo.v� ...
L
Street Lighting
Street Names
Signage& Pavement Marking
Fencing Requirements
Landscaping(Seeding,Trees,etc.) rye es S 2w . ud
r
Park Improvements
SUB-TOTAL: Grp /..p /6,
C S�7O. cm)
and Supervision CostsS /i p�C). 00 e"...„.N[+�,( Ic,;c( ;.) �,Jtt7 &Oat/V.'S,'O'U ' oc&)C.....- 71, -its--
(Testing,inspection,as-built plans and work in addition to preliminary and final final plat;supervision of actual construction by contractors)
TOTAL ESTIMATED COST OF IMPROVEMENTS AM)SUPERVISION S /4.. So° . dC3
3849077 Pages: 21 of 24
05/30/2012 08:09 AM R Fee:$0.00
Steve Moreno. Clerk and Recorder. Weld County, CO
III iiiPY}iPtiiffrilit lief Aril itiN.I0.IN"l11III
E 4HIB T A � Cost Sheet (ON-SITE) ~;Signature Page
The above improvements shall be constructed in accordance with all County requirements and specifications,
and conformance with this provision shall be determined solely by Weld County, or its duly authorized agent.
Said impro ents shall be completed according to the construction schedule set out in Exhibit B
By: 4
Applicant
OWJ-,ti/— Date —3 / G . 20 ( Z—
Title
By:
Applicant
Date , 20
Title
3849077 Pages: 22 of 24
05/30/2012 08:09 RM R Fee:$0.00
Steve Moreno. Clerk and Recorder. Weld County, CO
����I 'iPYIIPill'ANNA NIt IIii ikM PI Dim lull l
EXHIBIT B-Time Schedule(ON-SITE)& (OFF-SITE)Si
Name of Subdivision,PFD,CSR,RE,SPR: Filing/Case#: I 66 Location:e.c(xt A/St
Intending robe legalt'.hound,the undersigned Applicant herebp agrees to provide throughout drisjaeilitv theJollow/ng improvements.
All improvements shall be completed within I years from the date of approval of the final plat.
Construction of the umprovements listed in Exhibit A shall be completed as follows:
Improvements Time Schedule
(leave spaces blank where(her do not ripply )
jfIN-S/Tt1 (OFY=SI Z'Cl
Site Grading (1( J44/S
Street Grading 1
Street Base
Street Paving
Curbs,Gutters,and Culverts
Sidewalk 2- b4'[_.S
Stormwater/Drainage Facilities
Retention/Detention Ponds -1 (.�
cy
Road Culvert
Grass Lined Swale
Ditch Improvements
Subsurface Drainage
Sanitary Sewers/Sewage Facilities /y U h w
6 v
Sanitary Sewer Forced Main
Erosion('ontrol.Measures/BM P's
Laterals(house or building connected)
Water Supply and Storage
Water Mains(includes bore)
Fire Ilydrants
Survey,Street Monuments/Boxes
Parking,Area G lJ f\
l/ ys
Street lighting
Street Names
Signage& Pavement Marking
Fencing Requirements
Landscaping 5 ()t4y$ .
Park Improvements
Telephone
Gas
Electric
Water Transfer
Final Completion Date for Entire Project -/,1V,Zof
3849077 Pages: 23 of 24
05/30/2012 08:09 RPI R Fee:$0.00
Steve Moreno, Clerk and Recorder, Weld County. co
■III Ri ei li�,WL! EI r+,Nltill lihriVelliItIHll ■I III
EXHIBIT B - Time Schedule- Signature Page
The County, at its option, and upon the request of the Applicant. may grant an extension of time for completion
for any particular improvements shown above, upon a showing by the Applicant that the above schedule cannot
be met.
By:
Applicant
Pc- _ Date 3/6 , 20
t
Title
By:
Applicant
Date .20
Title
05/ es: 24 of 24
43012012 0809�FlMd R Dads$O 01�d county CO
�����IriNIMVVI� 5a '���'��'� �Q�'1.�1+11+��"1�����
B.f KTHE S
April ?4,2012 RECEIVED
APR 70i :
\Veld Count'-Public Works Weld County
Richard Hastings Public Works Dept.,
Compliance Analyst 4:Construction Inspector
1111 H Street
ireeiev. CO 80632
Re: Case=i.SR-1668
Dear Mr. Hastings,
'lease find attached a cashier's check in the amount of 516,500 as required by the
completion agreement for the above case.
This letter is to document the agreement between Peter& Heather Valconesi and Bank of
the West where at the completion of the project and request for release of the 85%of the
above fee a check will be cut jointly between Mr. &Mrs. Valconesi and Bark of the
\Vest.
Agree
•
•
Peter Valconesi Mafia Hifner.VP—BOW
Should you have any questions regarding this matter please do not hesitate contacting tae
a*.(916) 552-4330. C4r poi,e &al/ ic bank an V710).,;-
Sincerely,
when oalak ral is released, eAce
of
be made oil -Ia )boM ipa rA/es, redf� ��
wild Me. Meek fa /g7e Vale oiiesi sv d
�131ia Hltner,VP can e4da irse f /x/lAen /f£ ai 7I 5er/d
Construction Loan Manager re /�
,6a4k �� /4e s>` /]po Q
)6a/beer )/—Ae lvas> / err Yd/Cenes
4.'A/a/;a /`f/)ei) 11)1' %-t/ Arlark/�aaui
500 e a,o;'la///a// � �y a/ -�%
SME SBA Lending Division Sul/e /cQ"e l`
5;,fl Capitol Mall.Suiteat2ce Sacramento,CA 95Sl ‘sca rome`i7a a5EN
7,71
Member MP Paribas GroL{T �C
(12e-5 '7 W /
•A WATERMARK'S PRESENT ON THE BACK HOLD AT AN ANGLE TO VIEW.•VERIFY COLOR CHANGES ON FACE LEFT TO RIGHT.•THE BACK OF THIS DOCUMENT HASA HEAT-REACTIVE INK THAT CHANGES FROM ORANGE TO YELLOW WHEN HEAT IS APPLIED.
— 1000064515
BANtctEWES _ sore 211
1-800-488-2265 00332
DATE14106i2012
PURCHASER PETER 8 HEATHER VALCOHESI
1Y' Q -_
iao€tifr WELD COUNTY $16,500.00
Sixteei7ld# Iced and 00/100ths Ddllars ---
Memo R
•
'1.6‘
'CASHIER'S CHE€ SAID OVER $16,500.00
Hello