HomeMy WebLinkAbout20133004.tiffMEMORANDUM
TO: Kim Ogle, Planning Services DATE: August 27, 2013
FROM: Donald Carroll, Engineering Administrator
Public Works Department
SUBJECT: USR13-0045, Robert Brown
do Clean Energy Collective
The Weld County Public Works Department reviewed the submitted application for critical items,
including but not limited to Site Plan, Traffic Study, Preliminary Drainage Report, Geotechnical
Soils Report, and Flood Hazard Development Permit. A detailed review of these items was not
completed at this step in process. Comments made during this stage of the review process will
not be all inclusive; as revised materials are submitted other concerns or issues may arise. All
issues of concern and critical issues during further review must be resolved with the Public
Works Department.
COMMENTS:
CR 54 is an arterial road, which requires a 140 -foot right-of-way at full build out. There is
presently a 60 -foot right-of-way. This road is maintained by Weld County. Pursuant to the
definition of SETBACK in the Weld County Zoning (23-1-90), the required setback is measured
from the future right-of-way line. The applicant shall delineate or dedicate an additional 40 -foot
of right-of-way parallel to the CR 54 right-of-way for full build -out. In 2010, the average daily
traffic (ADT) count was 2600 vehicles per day (VPD)
CR 15.5 is a local gravel road and requires a 60 -foot right-of-way at full build out. There is
presently a 60 -foot right-of-way. This road is maintained by Weld County. Pursuant to the
definition of SETBACK in the Weld County Zoning (23-1-90), the required setback is measured
from the future right-of-way line. In 2012, the ADT count was 54 VPD.
REQUIREMENTS:
Access Permit Application Form:
Show the approved access on the plat and label it with the approved access permit number
(AP#).
Noxious Weeds:
Should noxious weeds exist on the property or become established as a result of the proposed
development, the applicant/landowner shall be responsible for controlling the noxious weeds,
pursuant to Section 15-1-180 of the Weld County Code.
Traffic Study:
The applicant in the questionnaire is indicating that there will be a concrete truck that delivers
concrete for the inverter pad. Once the construction phase is completed, a standard half -ton
pickup truck will visit the site.
C:\Users\kford\NppData\Local\Microsoft\Windows\Temporary Internet Files\Low\Content.lE5\32TCUENI\USR13-0045[1].docx
Drainage Report:
No drainage report or water quality feature is required. The site has minimal impacts to
stormwater quantity and quality.
The historical flow patterns and runoff amounts will be maintained on the site.
Grading Permit:
If more than one acre is to be disturbed, a Weld County Grading Permit will be required prior to
the start of construction.
Flood Hazard Development Standards:
This area IS NOT in a Special Flood Hazard Area (SFHA) as determined by the Federal
Emergency Management Agency (FEMA).
C:\Users\kford\NppData\Local\Microsoft\Windows\Temporary Internet Files\Low\Content.lE5\32TCUENI\USR13-0045[1].docx
MEMORANDUM
TO: KIM OGLE, PLANNING SERVICES
FROM: MARY EVETT, ENVIRONMENTAL HEALTH
SUBJECT: USR13-0045
DATE: SEPTEMBER 4, 2013
Environmental Health Services has reviewed this proposal for a community solar
garden. As no employees will be located at the site, permanent water and sewer is not
required. Portable toilets and hand washing units can be utilized during construction of
the expansion. Bottled water is sufficient for drinking provisions during construction.
There is an existing residence on the property that is served by Little Thompson Water
District and an individual sewage disposal system (Permit No. SP -9800376). The
applicant plotted the location of the existing septic system on the proposed site plan as
requested by Environmental Health Services. According to the site plan, the solar
panels will be located in a fenced area to the south of the existing septic system.
We have no objections to the proposal; however, we do recommend that the following
requirements are incorporated into the permit as development standards:
1. All liquid and solid wastes (as defined in the Solid Wastes Disposal Sites and
Facilities Act, 30-20-100.5, C.R.S., as amended) shall be stored and removed for
final disposal in a manner that protects against surface and groundwater
contamination.
2. No permanent disposal of wastes shall be permitted at this site. This is not
meant to include those wastes specifically excluded from the definition of a solid
waste in the Solid Wastes Disposal Sites and Facilities Act, 30-20-100.5, C.R.S.,
as amended.
3. Waste materials shall be handled, stored, and disposed in a manner that controls
fugitive dust, fugitive particulate emissions, blowing debris, and other potential
nuisance conditions.
4. Fugitive dust and fugitive particulate emissions shall be controlled on this site.
5. Adequate drinking (bottled water), toilet facilities (portable toilets) and hand
washing units shall be provided during construction of the facility.
6. The operation shall comply with all applicable rules and regulations of State and
Federal agencies and the Weld County Code.
2
Department of Planning Services
1555 N 17th Ave
Greeley, CO 80631
(970) 353-6100
Weld County Referral
Date: September 3 , 2013
Applicant: Robert Brown, do Clean Energy Collective
Project: A Site Specific Development Plan and Use by Special Review Permit for any use permitted as a
Use by Right, an Accessory Use, or a Use by Special Review in the Commercial or Industrial Zone
Districts, (577kW Community Solar Garden) provided that the property is not a Lot in an approved or
recorded subdivision plat or lots parts of a map or plan filed prior to adoption of any regulations
controlling subdivisions in the A (Agricultural) Zone District
Case Number: USR13-0045
Parcel Number: 095729000048-R8586700
After reviewing the application and documents submitted the Building Department has the following
comments:
A building permit may be required, for any new construction, alteration, or addition to any building on the
property, per Section 29-3-10 of the Weld County Code.
Buildings and structures shall conform to the requirements of the various codes adopted at the time of
permit application. Currently the following has been adopted by Weld County: 2012 International Building
Code; 2012 International Mechanical Code; 2012 International Plumbing Code:; 2012 International Fuel
Gas Code; 2006 International Energy Code; 2011 National Electrical Code; 2009 ANSI 117.1
Accessibility Code and Chapter 29 of the Weld County Code.
All building permit requirements can be found on the Weld County web -site
www.co.weld.co.us/building inspection/permits
Frank Piacentino
Department of Building Inspection
Submit by Email
Weld County Referral
August 15, 2013
The Weld County Department of Planning Services has received the following item for review:
Applicant: Robert Brown, c/o Clean Energy Collective Case Number: USR13-0045
Please Reply By: September 12, 2013 Planner: Kim Ogle
Project: A Site Specific Development Plan and Use by Special Review Permit for any use permitted as a
Use by Right, an Accessory Use, or a Use by Special Review in the Commercial or Industrial Zone
Districts, (577kW Community Solar Garden) provided that the property is not a Lot in an approved or
recorded subdivision plat or lots parts of a map or plan filed prior to adoption of any regulations
controlling subdivisions in the A (Agricultural) Zone District
Location: SOUTH OF AND ADJACENT TO COUNTY ROAD 54; WEST OF AND ADJACENT TO
COUNTY ROAD 15.5
Parcel Number: 095729000048-R8586700 Legal: PT W2 SECTION 29, T5N, R67W LOT B REC
EXEMPT RE -2496 (.57R.18D.53RR) of the 6th P.M., Weld County, Colorado.
The application is submitted to you for review and recommendation. Any comments or
recommendation you consider relevant to this request would be appreciated. Please reply by the
above listed date so that we may give full consideration to your recommendation. Any response not
received before or on this date may be deemed to be a positive response to the Department of Planning
Services. If you have any further questions regarding the application, please call the Planner
associated with the request. Please note that new information may be added to applications
under review during the review process. If you desire to examine or obtain this additional
information, please call the Department of Planning Services.
We have reviewed the request and find that it does / does not comply with our Comprehensive
Plan because:
We have reviewed the request and find no conflicts with our interests.
See attached letter.
Signature
Agency
Roger Ainsworth
Weld County Sheriffs Office
Date 081913
Weld County Planning Dept. 1555 N 17th Ave, Greeley, CO. 80631 (970) 353-6100 ext.3540 (970) 304-6498 fax
From: Roger Ainsworth
To: Kim Ogle
Subject: Form Returned: Referral°/ 20Form[1].pdf
Date: Monday, August 19, 2013 2:05:18 PM
Attachments: Referral- '-n20Fornif1Lpdf
I would like to see more thought put into security of the site. The past few years we have seen an
upswing in the solar panel thefts from railroad and oil well sites.