July 17, 2013
To: Board of County Commissioners
From: Toby Taylor
Subject: HVAC Equipment -1950 O -Street; Bid #61300134
As advertised, this bid is upgrade the HVAC system in the data center of 1950 O -Street. The low bid is
from Horizon Mechanical Solutions and meets specifications. Therefore, Buildings & Grounds is
recommending the bid be awarded to Horizon Mechanical Solutions in the amount of $138,819.
If you have any questions, please contact me at extension 2023.
Sincerely,
Toby Taylor
Director
7419/20/,3
,61,5- /2/r
3660/5
DATE OF BID: JULY 11TH, 2013
REQUEST FOR: HVAC EQUIPMENT -1950 O STREET
DEPARTMENT: BUILDINGS & GROUNDS
BID NO: #61300134
PRESENT DATE: JULY 15TH, 2013
APPROVAL DATE: JULY 29TH, 2013
VENDORS
WELD COUNTY PURCHASING
1150 O Street Room 107, Greeley CO 80631
E -Mail: mwalters@co.weld.co.us
E-mail: reverettAco.weld.co.us
Phone: (970) 356-4000, Ext 4222 or 4223
Fax: (970) 336-7226
TOTAL
PROJECT COST
HORIZON MECHANICAL SOLUTIONS $138,819.00
126 HEMLOCK ST
FT COLLINS CO 80524
COLORADO MECHANICAL
SYSTEM INC
1690 S ABILENE ST #107
AURORA CO 80012
ESCO
960 W 124TH AVE #900
WESTMINSTER CO 80234
CLASSIC CONTRACTORS INC
P O BOX 2798
LOVELAND CO 80539
$145,800.00
$146,151.00
$159,994.00
**TOBY TAYLOR IS REVIEWING THE BIDS AT THIS TIME.
*75
PROPOSED COMPLETION
START DATE DATE
Upon arrival
of equipment
Sept 9th, 2013
1 week ARO
(6 weeks lead time for
Liebert units)
Oct 1st, 2013
(60 days
after NTP)
Approx 6 weeks
Oct 31st, 2013
10 weeks RO
Nov. 8th, 2013
2013-1814
Ed ows