HomeMy WebLinkAbout20132300.tiffRESOLUTION
RE: APPROVE SITE SPECIFIC DEVELOPMENT PLAN AND USE BY SPECIAL REVIEW
PERMIT, USR13-0025, FOR A MINERAL RESOURCE DEVELOPMENT FACILITY
FOR OIL AND GAS SUPPORT AND SERVICE, INCLUDING OIL AND GAS
PROCESSING FACILITIES AND RELATED EQUIPMENT, FIVE (5) COMPRESSORS
ASSOCIATED WITH GAS PROCESSING OR WHICH COMPRESS GAS TO ENTER A
PIPELINE FOR TRANSPORT TO MARKET, AND ONE (1) SEVENTY-FOOT IN
HEIGHT COMMUNICATIONS TOWER IN THE A (AGRICULTURAL) ZONE DISTRICT
- SLW RANCH COMPANY, C/O DCP MIDSTREAM, LP
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, the Board of County Commissioners held a public hearing on the 14th day
of August, 2013, at the hour of 10:00 a.m., in the Chambers of the Board, for the purpose of
hearing the application of SLW Ranch Company, 822 7th Street, Suite 760, Greeley, CO 80631,
c/o DCP Midstream, LP, 3026 4th Avenue, Greeley, CO 80631, for a Site Specific Development
Plan and Use by Special Review Permit, USR13-0025, for a Mineral Resource Development
Facility for Oil and Gas Service, including oil and gas processing facilities and related
equipment, five (5) compressors associated with gas processing or which compress gas to
enter a pipeline for transport to market, and one (1) seventy-foot in height communications
tower in the A (Agricultural) Zone District, on the following described real estate, being more
particularly described as follows:
Subdivision Exemption, SUBX13-0013, for 20 acres
pending; All in Section 7, Township 5 North, Range
63 West of the 6th P.M., Weld County, Colorado
WHEREAS, at said hearing, the applicant was represented by Patrick Groom, 822
7th Street, Suite 760, Greeley, Colorado 80631, and
WHEREAS, Section 23-2-230 of the Weld County Code provides standards for review of
said Use by Special Review Permit, and
WHEREAS, the Board of County Commissioners heard all of the testimony and
statements of those present, studied the request of the applicant and the recommendation of
the Weld County Planning Commission and all of the exhibits and evidence presented in this
matter and, having been fully informed, finds that this request shall be approved for the following
reasons:
1. The submitted materials are in compliance with the application requirements of
Section 23-2-260 of the Weld County Code.
2. It is the opinion of the Board of County Commissioners that the applicant has
shown compliance with Section 23-2-230.B of the Weld County Code as follows:
A. Section 23-2-230.B.1 -- The proposed use is consistent with Chapter 22
and any other applicable code provisions or ordinance in effect.
c e : CE, ,o[ Pld /�L, flp* i2jenf
9-9-/3
2013-2300
PL2234
SPECIAL REVIEW PERMIT (USR13-0025) - SLW RANCH COMPANY, C/O DCP
MIDSTREAM, LP
PAGE 2
1) Section 22-5-100.A (OG.Goal 1) states: "Promote the reasonable
and orderly exploration and development of oil and gas mineral
resources."
2) Section 22-5-100.B (OG.Goal 2) states: "Ensure that the
extraction of oil and gas resources conserves the land and
minimizes the impact on surrounding land and the existing
surrounding land uses."
3) Section 22-6-20.C.1 (ECON.Policy 3.1) states: "County activities
and regulation should protect the rights of private property owners
and the public health, safety and welfare, recognizing that these
basic rights and protections allow the free market to prosper and
grow the local economy." DCP is a business that is in the
midstream segment of the natural gas industry. As part of its
business, DCP Midstream, LP, gathers natural gas from
wellheads, performs gas processing, and transmits final products
to customers via pipelines. In Weld County, DCP operates an
extensive network of gathering pipelines as well as seven gas
processing plants. The DJ Basin area has recently seen rapid
expansion as new drilling technologies are allowing more oil and
gas to be produced. As a result, gas gathering and processing
capacity needs to be expanded in order to meet the growing
production. To meet these needs, DCP is proposing the SLW
Ranch compressor station necessitated by the need to move
larger volumes of gas due to the recent increases in drilling
activity and projected additional production increases anticipated
by producers. Further, this need is based on new technology for
uncovering natural gas discoveries and the ability of the DJ Basin
to expand based on these new technologies. The proposed
compressor will be sited on private property leased to DCP
Midstream, LP. This proposal has been reviewed by the
appropriate referral agencies and it has been determined that the
attached Conditions of Approval (noise limits and the requirement
that the applicant submit a Lighting Plan) and Development
Standards ensure that there are adequate provisions for the
protection of the health, safety and welfare of the inhabitants of
the neighborhood and County, and will address and mitigate
impacts on the surrounding area due to the construction of this
facility.
B. Section 23-2-230.B.2 -- The proposed use is consistent with the intent of
the A (Agricultural) Zone District. Section 23-3-40.A.2 of the Weld County
Code provides for Mineral Resource Development, Oil and Gas Support
and Service, and Section 23-3-40.K allows one (1) or more microwave,
radio, television or other communication transmission or relay tower over
2013-2300
PL2234
SPECIAL REVIEW PERMIT (USR13-0025) - SLW RANCH COMPANY, C/O DCP
MIDSTREAM, LP
PAGE 3
seventy (70) feet in height per Lot as a Use by Special Review in the
A (Agricultural) Zone District.
C. Section 23-2-230.6.3 -- The uses which will be permitted will be
compatible with the existing surrounding land uses. The property is
generally flat with a slight slope to the southwest toward Crow Creek.
This land and surrounding lands in each direction are utilized as grazing
lands for livestock and are in native grasses with numerous oil and gas
facilities, well heads and tank batteries present in each direction. There
are five (5) property owners on nine (9) parcels within 500 feet of this
facility, there are no residences in the immediate area, and staff has
received no letters, telephone calls or electronic mail from interested
parties.
D. Section 23-2-230.B.4 -- The uses which will be permitted will be
compatible with future development of the surrounding area, as permitted
by the existing zoning, and with the future development as projected by
Chapter 22 of the Weld County Code and any other applicable code
provisions or ordinances in effect, or the adopted Master Plans of affected
municipalities. The site is not within a three-mile referral area of a
municipality.
E. Section 23-2-230.6.5 -- The application complies with Chapter 23,
Article V, of the Weld County Code. Building Permits issued on the lot
will be required to adhere to the fee structure of the County -Wide Road
Impact Fee Program, County Facility Fee and Drainage Impact Fee
Programs. The existing site is not within a recognized overlay district,
including the Geologic Hazard, Flood Hazard or Airport Overlay District.
F. Section 23-2-230.B.6 -- The applicant has demonstrated a diligent effort
to conserve prime agricultural land in the locational decision for the
proposed use. This proposed facility is located on a 20 -acre Subdivision
Exemption lot (SUBX13-0013) utilizing approximately 12 acres for the
compressor site. Ongoing agricultural production will continue on lands
not impacted by this proposed facility. The proposed facility is sited on
lands that are without a designation on the Important Farmlands of Weld
County map dated 1979.
Section 23-2-230.6.7 -- The Design Standards (Section 23-2-240, Weld
County Code), Operation Standards (Section 23-2-250, Weld County
Code), Conditions of Approval and Development Standards ensure that
there are adequate provisions for the protection of health, safety, and
welfare of the inhabitants of the neighborhood and County.
2013-2300
PL2234
SPECIAL REVIEW PERMIT (USR13-0025) - SLW RANCH COMPANY, CIO DCP
MIDSTREAM, LP
PAGE 4
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of
Weld County, Colorado, that the application of SLW Ranch Company, c/o DCP Midstream, LP,
for a Site Specific Development Plan and Use by Special Review Permit, USR13-0025, for a
Mineral Resource Development Facility for Oil and Gas Support and Service, including oil and
gas processing facilities and related equipment, five (5) compressors associated with gas
processing or which compress gas to enter a pipeline for transport to market, and one (1)
seventy-foot in height communications tower in the A (Agricultural) Zone District, on the parcel
of land described above be, and hereby is, granted subject to the following conditions:
1. Prior to recording the plat:
A. The plat shall be amended to delineate the following:
1) All sheets of the plat shall be labeled USR13-0025.
2) The attached Development Standards.
3) The plat shall be prepared in accordance with Section 23-2-260.D
of the Weld County Code.
4) County Road (CR) 61 is designated on the Weld County Road
Classification Plan as a local road, which requires 60 feet of
right-of-way at full buildout. The applicant shall verify the existing
right-of-way and the documents creating the right-of-way and this
information shall be noted on the plat. All setbacks shall be
measured from the edge of future right-of-way. If the right-of-way
cannot be verified, it shall be dedicated. This road is maintained
by Weld County.
5) Show the approved accesses on the plat and label with the
approved access permit number.
B. The applicant shall provide an accepted water quality depression for this
site.
C. An Improvements and Road Maintenance Agreement is required for this
site during construction. Road maintenance, including dust control and
damage repairs, during construction will be required.
D. The applicant shall submit evidence of an Air Pollution Emission Notice
(A.P.E.N.) and Emissions Permit Application from the Air Pollution Control
Division (APCD), Colorado Department of Public Health and Environment
(CDPHE) to the Environmental Health Services Division of the Weld
County Department of Public Health and Environment. Alternately, the
applicant may provide evidence from the APCD that they are not subject
to these requirements.
2013-2300
PL2234
SPECIAL REVIEW PERMIT (USR13-0025) - SLW RANCH COMPANY, C/O DCP
MIDSTREAM, LP
PAGE 5
A. If more than one (1) acre is to be disturbed, a Weld County Grading Permit
will be required prior to the start of construction.
3. Prior to Operation:
A. A signed copy of the Spill Prevention, Control and Countermeasure Plan
shall be provided to the Environmental Health Services Division of the
Weld County Department of Public Health and Environment.
B. The applicant shall develop an Emergency Action and Safety Plan with the
Office of Emergency Management and the Fire District. The plan shall be
reviewed on an annual basis by the facility operator, the Fire District and
the Weld County Office of Emergency Management. The applicant shall
submit evidence of acceptance to the Department of Planning Services.
4. Upon completion of Condition of Approval #1 above, the applicant shall submit
an electronic version (.pdf), or three (3) paper copies, of the plat to the Weld
County Department of Planning Services for preliminary approval. The plat shall
be prepared in accordance with the requirements of Section 23-2-260.D of the
Weld County Code. Upon approval of the plat, the applicant shall submit a Mylar
plat, along with all other documentation required as Conditions of Approval. The
Mylar plat and additional requirements shall be submitted within one hundred
twenty (120) days from the date of the Board of County Commissioners
Resolution. The Mylar plat shall be recorded in the office of the Weld County
Clerk and Recorder by the Department of Planning Services. The applicant shall
be responsible for paying the recording fee.
5. The Department of Planning Services respectfully requests a digital copy of this
Use by Special Review, as appropriate. Acceptable CAD formats are .dwg, .dxf,
and .dgn (Microstation); acceptable GIS formats are ArcView shapefiles or
ArcGIS Personal GeoDataBase (MDB). The preferred format for Images is .tif
(Group 4). (Group 6 is not acceptable). This digital file may be sent to
maps@co.weld.co.us.
6. In accordance with Weld County Code Ordinance #2012-3, approved April 30,
2012, should the plat not be recorded within the required one hundred twenty
(120) days from the date of the Board of County Commissioners Resolution, a
$50.00 recording continuance charge shall added for each additional three (3)
month period.
7. The Use by Special Review activity shall not occur, nor shall any building or
electrical permits be issued on the property, until the Use by Special Review plat
is ready to be recorded in the office of the Weld County Clerk and Recorder.
2013-2300
PL2234
SITE SPECIFIC DEVELOPMENT PLAN
USE BY SPECIAL REVIEW PERMIT
DEVELOPMENT STANDARDS
SLW RANCH COMPANY, C/O DCP MIDSTREAM, LP
USR13-0025
1. The Site Specific Development Plan and Use by Special Review Permit, USR13-0025, is
for a Mineral Resource Development Facility, Oil and Gas Support and Service,
including oil and gas processing facilities and related equipment, including, but not
limited to, five (5) compressors associated with gas processing or which compress gas
to enter a pipeline for transport to market, and one (1) seventy-foot in height
communications tower in the A (Agricultural) Zone District, and subject to the
Development Standards stated hereon.
2. Approval of this plan may create a vested property right pursuant to Section 23-8-10 of
the Weld County Code.
3. All liquid and solid wastes (as defined in the Solid Wastes Disposal Sites and Facilities
Act, Section 30-20-100.5, C.R.S.) shall be stored and removed for final disposal in a
manner that protects against surface and groundwater contamination.
4. No permanent disposal of wastes shall be permitted at this site. This is not meant to
include those wastes specifically excluded from the definition of a solid waste in the
Solid Wastes Disposal Sites and Facilities Act, Section 30-20-100.5, C.R.S.
5. Waste materials shall be handled, stored, and disposed of in a manner that controls
fugitive dust, blowing debris, and other potential nuisance conditions.
6. Fugitive dust and fugitive particulate emissions shall be controlled on this site. The
facility shall be operated in accordance with the approved Dust Abatement Plan, at all
times.
7. Adequate drinking, hand washing and toilet facilities shall be provided for employees
and patrons of the facility, at all times. As employees or contractors are on the site for
less than two (2) consecutive hours a day, portable toilets and bottled water are
acceptable. Records of maintenance and proper disposal for portable toilets shall be
retained on a quarterly basis and available for review by the Weld County Department of
Public Health and Environment. Portable toilets shall be serviced by a cleaner licensed
in Weld County and shall contain hand sanitizers.
8. All potentially hazardous chemicals must be handled in a safe manner in accordance
with product labeling and in a manner that minimizes the release of Hazardous Air
Pollutants (HAP's) and Volatile Organic Compounds (VOC's). All chemicals must be
stored secure, on an impervious surface, and in accordance with manufacturer's
recommendations.
9. The Spill Prevention, Control and Countermeasure Plan shall be available on the site, at
all times.
2013-2300
PL2234
DEVELOPMENT STANDARDS (USR13-0025) - SLW RANCH COMPANY, C/O DCP
MIDSTREAM, LP
PAGE 2
10. The operation shall comply with all applicable rules and regulations of state and federal
agencies and the Weld County Code.
11. Building permits may be required for the Oil and Gas Support and Service Facilities and
associated buildings and equipment.
12. Buildings and structures shall conform to the requirements of the various codes adopted
at the time of permit application. Currently, the following have been adopted by Weld
County: 2012 International Building Code, 2012 International Mechanical Code, 2012
International Plumbing Code, 2006 International Energy Code, 2012 International Fuel
Gas Code, 2011 National Electrical Code, 2003 ANSI 117.1 Accessibility Code, and
Chapter 29 of the Weld County Code.
13. The historical flow patterns and runoff amounts will be maintained on the site.
14. Should noxious weeds exist on the property, or become established as a result of the
proposed development, the applicant/landowner shall be responsible for controlling the
noxious weeds, pursuant to Chapter 15, Articles I and II, of the Weld County Code.
15. Building permits issued on the property will be required to adhere to the fee structure of
the County -Wide Road Impact Fee Program.
16. Building permits issued on the property will be required to adhere to the fee structure of
the County Facility Fee and Drainage Impact Fee Programs.
17. The facility will operate 24 hours per day, 365 days per year.
18. The property owner or operator shall be responsible for complying with the Design
Standards of Section 23-2-240 of the Weld County Code.
19. The property owner or operator shall be responsible for complying with the Operation
Standards of Section 23-2-250 of the Weld County Code.
20. The property owner or operator shall provide written evidence of an Emergency Action
and Safety Plan on or before March 1st of any given year signed by representatives for
the Fire District and the Weld County Office of Emergency Management to the
Department of Planning Services.
21. Necessary personnel from the Weld County Departments of Planning Services, Public
Works, and Public Health and Environment shall be granted access onto the property at
any reasonable time in order to ensure the activities carried out on the property comply
with the Conditions of Approval and Development Standards stated herein and all
applicable Weld County regulations.
2013-2300
PL2234
DEVELOPMENT STANDARDS (USR13-0025) - SLW RANCH COMPANY, C/O DCP
MIDSTREAM, LP
PAGE 3
22. The Use by Special Review area shall be limited to the plans shown hereon and
governed by the foregoing standards and all applicable Weld County regulations.
Substantial changes from the plans or Development Standards, as shown or stated,
shall require the approval of an amendment of the Permit by the Weld County Board of
County Commissioners before such changes from the plans or Development Standards
are permitted. Any other changes shall be filed in the office of the Department of
Planning Services.
23. The property owner or operator shall be responsible for complying with all of the
foregoing Development Standards. Noncompliance with any of the foregoing
Development Standards may be reason for revocation of the Permit by the Board of
County Commissioners.
24. The Weld County Right to Farm Statement, as it appears in Section 22-2-20.J.2 of the
Weld County Code, shall be placed on the plat and recognized at all times.
2013-2300
PL2234
SPECIAL REVIEW PERMIT (USR13-0025) - SLW RANCH COMPANY, C/O DCP
MIDSTREAM, LP
PAGE 6
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 14th day of August, A.D., 2013.
BOARD OF COUNTY COMMISSIONERS
WELD COUNT�Fj COLORADO
ATTE
Weld County Clerk to the Board
EXCUSED
Douglas Rademacher, Pro -Tern
BY:
Deputy Clerk o e Board
P. Conway
APP
eeman
Attorney
ara Kirkmeyer
Date of signatureSEP ® 5 2013
2013-2300
PL2234